ES7034Rework_and_RepairofNonconformingMaterial.pdf
PDF 47 KB Posted
- Attached to
- F-16 Rocket Motor Federal contract opportunity
- Solicitation number
- FA8213-20-R-0080
About this file
This document outlines rework and repair procedures for nonconforming materials on federal contracts. The contractor must document rework procedures and submit them to the government quality assurance representative for review before implementation. Repair procedures require submission of a request for deviation/waiver to the contracting officer for written approval. For any rework or repair submission, the contractor must include a description of the nonconformance cause and actions taken to prevent recurrence. The procedure must also specify a reinspection provision taking precedence over technical data package requirements and providing assurance the item meets processing requirements. Rework and repair requirements flow down to contractors, suppliers, vendors and subcontractors.
The related federal contract opportunity is a solicitation for 311 F-16 rocket motors and 302 canopy jettisoned rocket motors. The solicitation number is FA8213-20-R-0080. The Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base issued the solicitation. The contract period will last until all units are produced and delivered. An electronic procedure will be used for the solicitation.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(ES7034)
REWORK AND REP AIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework-The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
( c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
( e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendo.rs or subcontractors.
(ES7034)