ANSWERS_TO_CONTRACTOR_QUESTIONS.pdf

PDF 42 KB Posted

Attached to
Repair Fire Alarms in Bldg 238 Federal contract opportunity
Solicitation number
FA8201-16-B-0008
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Answers to Contractors' Questions

View the file

Other files for this federal contract opportunity

Other files attached to Repair Fire Alarms in Bldg 238, newest first.
File Type Posted
Amendment_to_Solicitation_0002.pdf PDF
SOW_238_mod_(002).pdf PDF
Amendment_to_Solicitation_2.pdf PDF
FIRE_ALARM_128_129.pdf PDF
FIRE_PROTECTION_128_129.pdf PDF
FA8201-16-B-0008_-_Bldg_238_-_Fire_Alarms_-_Attendance_Records.pdf PDF
Index_of_Specifications.pdf PDF
Davis_Bacon.pdf PDF
SPECS.pdf PDF
LBP_Inspection_Report.pdf PDF
2016_05_05_BASE_FACILITY_DESIGN_STANDARD.pdf PDF
B238_Solicitation.pdf PDF
KRSM238_152063_Fire Protection Drawings IFC 12-07-2015.pdf PDF
Asbestos_Inspection_Report.pdf PDF
Schedule_of_Drawings.pdf PDF
SOW_238.pdf PDF
KRSM238_152063_Electrical_Drawings_IFC_12-07-2015.pdf PDF
Pricing_Schedule.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR QUESTIONS

REPAIR FIRE ALARM BLDG 238

August 29, 2016

Q1: Is the contractor to provide new tamper and flow switches or only hook up to existing?

A: Installation of new tamper and flow switches is a requirement and to better clarify this the statement of work has been modified to read “The installation shall include new water flow/tamper/PIV monitor modules and new water flow switches for all suppression systems per current Base and NFPA guidelines.”

Q2: Is the PIV new or existing?

A: All PIVs are existing and to better clarify this the statement of work has been modified by removing the reference to new PIVs to read “The installation shall include new water flow/tamper/PIV monitor modules and new water flow switches for all suppression systems per current Base and NFPA guidelines.”

Q3: Can the contractor count on the conduit to the PIV being intact or will a new underground conduit need to be run?

A: This will need to be field verified. Contractors shall assume new underground conduit will be needed as they will be required to make these connections to the PIVs one way or the other.

Q4: Can the work performance Delivery date be extended from 120 days to say 240 days?

A: The period of performance shall be increased to 180 days.