F108 Engine Turbine Clearance Control Valve (TCCV) Responses to Questions from Industry 29 Oct 14
1. QUESTION: With respect to 52.222-41, will the Government accept the Contractor's collective bargaining agreement in lieu of prevailing wages?
RESPONSE: It is acceptable for contractors to use their CBA in the preparation of proposal for TCCV RFP.
29 Oct 14
File details come from the government source that posted it. Updated .