SIMP Solicitation Questions and Answers.pdf
PDF 125 KB Posted
- Attached to
- USAFA Surgical Instrument Maintenance Program Federal contract opportunity
- Solicitation number
- FA700021Q0021
About this file
This document contains questions and answers regarding a solicitation for a Surgical Instrument Maintenance Program for the 10th Medical Group at the United States Air Force Academy. The solicitation seeks a contractor to provide maintenance and repair services three days per month to service endoscopy and other surgical equipment listed in Attachment 1, Appendix A. The Performance Work Statement provides additional details on requirements. The document extends the response deadline to Friday, March 19, 2021 at 5:00 PM MDT to allow clarification of discrepancies between the frequency of on-site visits specified in the PWS and Attachment 3.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS
Questions from various vendors have been listed below. The Government’s answers are in bold.
1. Under Part III - Past Performance: Will the Air Force of its own accord review the CPARS and SAM information available regarding our cage code?
Yes, that is correct.
2. Under Part III – Past Performance: For Part III, what information is required to be provided by the offeror?
The Air Force will pull this information from SAM and CPARS.
3. Do all of the separate parts (1-4) need to be separate documents when submitted?
No.
4. What Part (1-4) should the “Financial Information” be included in?
Part 4, Contract Documentation.
5. When looking at CPARS/SAM for “Past Performance Part III”- What relevant experience is required in order to receive an “acceptable” evaluation rating?
Reference Page 6 of the Instructions to Offerors for the description of an “acceptable” evaluation rating.
6. Question #1-Can a prime contractor use their sub-contractors past performance and mission essential contractor service plan?
IAW FAR 19.1507(a)(1), there are limitations on subcontracting under the WOSB program. Since the prime contractor must perform at least 50 percent of the effort for a contract awarded under the WOSB program, we need to ensure that the prime contractor’s past performance and mission-essential plan are acceptable. Therefore, prime contractors cannot substitute their past performance and mission-essential plan for that of their subcontractors.
7. In reference to Attachment 1 Appendix B (attached), is this list posted under a different solicitation number? I ask this because the equipment in Appendix B is what we would be able service.
This solicitation for USAFA’s SIMP requirement includes equipment referenced in both PWS Appendix A (on-site maintenance list) and PWS Appendix B (off-site maintenance list). There is not a separate solicitation for only Appendix B equipment.
8. Regarding Attachment 1 and the Performance of Work, I would like to get some clarification on the type of equipment we will be working with. According to attachment 1, it looks like it is endoscopy equipment, however on the Performance of Work, it mentions sharpening equipment etc. Would you be able to specify if this bid is for only endoscopy equipment or if there are surgical instruments requiring sharpening services?
In response to your question, after discussion with our requirements owners, the solicitation has been updated on Beta.Sam with an updated Attachment 1, Appendix A. This is the current list of on-site equipment to be serviced. So to clarify, the equipment listed in Attachment 1 on Beta.Sam is the type of equipment that your organization would be working with.
9. The PWS says the contractor “will provide maintenance and repair services three consecutive days per month”. (Page 4. 3.1). The attachment 3 (see attached) says “On-site visits shall be provided three (3) times per year for the 10 MDG. Visits will occur approximately in January, May, and September or as specified by the 10 MDG”. Please clarify that the PWS is the correct document regarding the required service.
This is still under discussion with the requirements owners, so we are extending the solicitation until Friday, 19 March 2021 at 5 PM MDT so that we can determine the best path forward.
10. This is in regard to "USAFA Surgical Instrument Maintenance Program FA700021Q0021".
We are very much interested to submit this opportunity.Our SUB is preparing the quote for this opportunity. I request you to please extend the bid deadline till 03/19/2021 (Friday), 05 PM CDT.
We are extending the solicitation until Friday, 19 March 2021 at 5 PM MDT.