SABER solicitation FA665617R0001 Questions, Answers, Clarifications (continued)

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Acquisition For Base Engineering Requirements(SABER), newest first.
File Type Posted
SABERamendment3.docx DOCX document
SABER_HeavyHighway_Wages_Attachment3(revision1).docx DOCX document
SABER_Building_Wages_Attachment_2(revision1).docx DOCX document
SABER_QandA.doc DOC document
SABERSiteVisitAttendees.pdf PDF
SABER2017_Agenda.docx DOCX document
Amendment2Saber2017.docx DOCX document
Amendment1Saber2017.docx DOCX document
Project_ZQEL_15-0026_proposed_layout.pdf PDF
CoEfficient_Pricing_Proposal_Spreadsheet_Attachment_5.docx DOCX document
SolicitationSaber2017.docx DOCX document
Question_Submission_Form_Attachment_6.doc DOC document
SABER_HeavyHighway_Wages_Attachment3.docx DOCX document
SOW_Project_15-0026_Renovate_Building_510_Attachment_4.doc DOC document
SABER_Basic_SOW_Attachment_1.doc DOC document
Site_Visit_Registration_FormAttachment7.xls XLS spreadsheet
SABER_Building_Wages_Attachment_2.docx DOCX document
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SABER Solicitation FA665617R0001

Questions with Answers/Clarifications (continued) as of 31 October 2017

6. Which maximum single award/task order performance and payment bonding capacity and aggregate amount is required from the contractors?

Response: The maximum amount for a single award task order is $1M; the potential aggregate is $2.5M.

7. The only attachment for pricing was attachment 5, “Coefficient Pricing Proposal Spreadsheet.” It is in Word format. Is this what we’re supposed to be using in this section?

Response: YES. The Coefficient Pricing Proposal Spreadsheet Attachement 5 is the required document for submission of pricing proposal Section I Price TAB #3

8. The SF1442, Block 13. D. states” Offers providing less than 120 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected. Which is correct, 180 or 120 days?

Response: 180 days

9. (a) Please confirm the government DOES NOT require an electronic copy of proposals. Only 1 original and 1 hard copy of proposals are required?

(b) How many proposal “Copies” does the Offeror submit with the proposal “Original”?

Response: Paper copies only: an original clearly marked and one copy. (elaborate submissions are not necessary so that the sections can be easily separated for evaluation and review purposes)

10. Please confirm; a bid bond is not required for the SEED project?

Response: The letter from your bonding company takes the place of the bid bond for all task orders. Performance and Payment bonds are required for task order awards of $150,000 or higher.

11. The SOW states to replace all existing crankout windows. The existing windows are “residential” style for new construction. Does the Government want aluminum windows similar to “storefront” construction like on the entrances to B510, or is a residential vinyl replacement what is desired?

Response: Desired windows are to be aluminum same as existing on building 510.

12. What is the tint for the new windows, Is there a U value or SHGC Value? What is the exact finish of the windows we are matching?

Response: No tint required. Had there been a tint on the existing windows tint would have been required. NO tint required. Dark Bronze finish.

13. In Walk thru it was mentioned that no blinds would be required for this contract. If blinds are required for this contract, Do you have a specification, style, color?

Response: New blinds shall match existing blinds in style, material, color and size. Contractor responsible for measurements.

14. In Walk thru it was decided to replace carpet in entire hallway out to kitchen area. Do you have a spec, style, color, pile to price up?

Response: BROADLOOM

STYLE: Faculty IV

PATTERN: DK166

COLOR: 4267 Aruba Blue

Face yarn: Antron Legacy Nylon With Dura Tech Soil Protection By INVISTA

28 Ounce

15. In Walk thru it was discussed to make one wall in hallway only 4’ high in lieu of 7’ as on detail. On top of this wall would be a finish board as a shelf to cover top of wall.

Response: Use a solid oak board with polyurethane natural finish.

16. In walk thru it was decided that no additional detectors, voice speakers HVAC or sprinklers would be added to project. We would only be moving around existing.

Response: Correct

17. In Walk Thru it was decided no switch would be added but the two lights would be added to the hallway lights circuit and existing switching.

Response: Correct

18. Is there a page limit for the Quality Control Plan?

Response: No