ASHE_15-1017_Addedum___1.pdf
PDF 8 KB Posted
- Solicitation number
- FA568218R0009
About this file
The purpose of this modification is to: A) Incorporate ADDENDUM #1 to Technical Specifications B) Correct the extended description of CLINS 0001 and 0002, C) Correct Section J Period of performance is not extended.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum__1_Revised_ASHE_15-1017.pdf | ||
| FA568218R0009_0005.pdf | ||
| ASHE_15-1017_Safety_Plan.pdf | ||
| FA568218R0009_0004.pdf | ||
| A-1_A-3_Drawings_REV2.pdf | ||
| C-1_C-2_C-4_C-5_Drawings_REV2.pdf | ||
| S-2_S-3_S-4_Drawings_REV2.pdf | ||
| Solicitation_Amendment__3_ASHE_15-1017.pdf | ||
| Addendum__1_ASHE_15-1017.pdf | ||
| E-3_E-4_Drawings_REV2.pdf | ||
| M-1_Drawing_REV2.pdf | ||
| Amendment__2.docx | DOCX document | |
| FA568218R0009_Mod.pdf | ||
| FA568218R0009_27_Dec_17.pdf | ||
| Additional_Requirements,_Dec_2017.pdf | ||
| ASHE_15-1017_CCEB_2018.xls | XLS spreadsheet | |
| M_Drawings.pdf | ||
| S_Drawings.pdf | ||
| C_Drawings.pdf | ||
| A_Drawings.pdf | ||
| E_Drawings.pdf | ||
| ASHE_15-1017_TECHNICAL_SPECIFICATIONS_ENG.pdf |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project # ASHE 15-1035 Addendum#1 Statement of Work
DATE: JAN 2018
31CES/CENM 1
ASHE 15-1017
CNS NEW EOD STORAGE FACILITY 9391 - DEMO SHEDS
AVIANO AB, AVIANO, ITALY
ADDENDUM #1
A1.1. Change item 6, Architectural works Part IIa and drawing A-5 to read:
A1.1.1 “Furnishing and installation of external wall insulation package. Item includes:
A1.1.1.1 Thermal insulation coating for exterior walls complete with fireproof class 1, density 40 kg/m3, high mechanical resistance, foamed polystyrene panel 10.0 cm thick, finished with fiberglass wire mesh reinforced thin exterior stucco “intonachino” type, 1.0cm thick
A1.1.1.2 All operations necessary for the workmanlike execution of the work.
563.0 m2
A1.2. Item 10, Architectural Works Part II, drawing A-4 change to read Aluminum Door.
A1.3. Item 13–Architectural Works – Part IIa of Technical Specifications, change to read:
A1.3.1 Furnishing and installation of metal certified fire rated 90’ door, color selected by the Contracting Officer’s Technical Representative. Door shall be complete with galvanized S235 steel frame and counter-frame, fixing hardware, sealing gaskets, handle, lockset, door closer, accessories and any other item to provide a job in a workmanlike manner.
A1.3.1.1 FIRE RATED REI 90 Door 1200x2150 mm, symbol "D4”, complete with certified lockset system.
A1.3.1.2 Item includes all operations necessary for the workmanlike execution of the work.
1 Ea.
A1.4. Drawing A-4 change to read, referred to door “D4”, “certified lock system” instead of “BEST
LOCK”.
A1.5. Drawing A-4 window “W1”, change to read window size will be 2500x900mm;
A1.6. Item 3, Part IV of Technical Specifications –Electrical Work– describes the static converter to be furnished and its technical characteristics. It does not need a by-pass and it does not need batteries, just the predisposition of their installation;
A1.7. Drawing E-7 detail #2 “Telecom voice and data schematic diagram” the quantity to be furnished is #1 HUB EX 3300-2X.
A1.8. Item 14 Part IIa –Window W1 will be equipped with motor, control panel, cabling and electrical accessories.
A1.9. Part IIc, Item 2, “Supply and Installation of industrial concrete floor….” Is referred to external concrete pad/sidewalks shown on drawing C-2 Rev.