Attachment_1_Statement_of_Work_20170629.pdf
PDF 149 KB Posted
- Attached to
- Ramstein AB Combined ESS Federal contract opportunity
- Solicitation number
- FA5641-17-T-0007
About this file
RFQ documents
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_7_USAFE_Ramstein_B526_B528_B529_ACS_Conceptual_Design.pdf | ||
| Attachment_3_DD254_-_CONTINUATION_OF_BLOCK_13__Ramstein_AB_Combined_ESS_Upgrades.pdf | ||
| Attachment_6_USAFE_Ramstein_AB_B3334_RM_127_PCU_Upgrade_Conceptual_Design.pdf | ||
| Attachment_5_RAMSTEIN_HEAD_END_AS_BUILT.pdf | ||
| Attachment_4_B543_ESS_Conduit_and_Cable_Routing.pdf | ||
| Brand_Name_J&A_-_USAFE_Ramstein_AB_Combined_ESS_Upgrades_Redacted.pdf | ||
| Request_for_Quote.pdf | ||
| Attachment_2_DD254_-Ramstein_AB_Combined_ESS_Upgrades.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW Ramstein AB Combined ESS Upgrades Page 1 of 28 Pages
STATEMENT OF WORK
FOR
United States Air Force-Europe (USAFE) Ramstein Air Base Combined
Electronic Security System (ESS) Upgrades
6 July 2017
Page 2 of 28 Pages
CONTENTS
1. Description of Need………………………………………………….………….3
2. Scope……………………………………………………………………………3
3. Background….……………………………..…………………………………...3
4. Objectives……………………………………………………………………
5. Specific Tasks…………………………..……………………………………
6. Place of Performance…………..………………………………………………19
7. Date of Delivery……..……..…………………………………………………..20
8. Security……………………………..………………………………………….20
9. Key Personnel………………………………………………………………….21
10. Government-Furnished Supplies/Government Access……….………….…
11. Section 508 Accessibility Standards…….…………………………………….22
12. Required Reports and Notifications …….…………………………………….22
13. Applicable Publications………………………………………………………..24
14. Acronyms……….……………………………………………………………...26
Page 3 of 28 Pages
1. DESCRIPTION OF NEED: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to develop a 100% Installation Design Package (IDP) and post-installation As-Built IDP, procurement of equipment/materials, installation, and 100% Space and Naval Warfare Systems Center (SPAWARSYSCEN) Atlantic System Operation and Verification (SOVT) / United States Air Force — Europe (USAFE) Phase 1 – 3 certification of installed Electronic Security System (ESS) components, as defined in this SOW, except for those items specified as government furnished services (GFS). The Contractor shall perform to the standards in this contract
2. SCOPE: The Contractor shall provide non-personal services including procurement, installation, and USAFE Phase 1 - 3 testing of ESS to meet AFI 31-101, and Intelligence Community Directive (ICD) 705 requirements at Ramstein Air Base in accordance with this SOW.
3. BACKGROUND: The U.S. Navy’s SPAWARSYSCEN Atlantic Command Stuttgart Office and 764th Specialized Contracting Squadron (SCONS) are providing USAFE with assistance in the Ramstein Air Base Combined Electronic Security System (ESS) Upgrades.
4. OBJECTIVES: The objective of this project is to procure and install ESS materials/equipment for multiple buildings at Ramstein AB in accordance with Air Force Instruction 31-101 (AFI 31-101) and the Intelligence Community Directive Number 705 (ICD-705).
5. SPECIFIC TASKS:
The U.S. Navy’s SPAWARSYSCEN Atlantic Command Stuttgart Office and 764th Specialized Contracting Squadron (SCONS) are providing USAFE with assistance in the Ramstein Air Base Combined ESS Upgrades.
The Contractor shall design, procure, and install ESS Upgrades in accordance with AFI 31-101 at Ramstein Air Base, Germany.
5.1. Basic Task: The Contractor shall procure and install new materials and equipment to upgrade the ESS at buildings 201, 526, 528, 529, 543, 2371, and 3334 at Ramstein Air Base. The Contractor shall comply with the AFI 31-101, ICD 705, and the approved USAF/USAFE equipment list for all installation parameters and activities. In addition, the Contractor shall abide to standards and regulations specified in this SOW, Paragraph 13.
5.2. Progress Meetings: The Contractor shall attend in-person all the meetings relevant to the Ramstein Air Base Combined ESS Upgrades and closely coordinate access/survey/materials delivery/installation/testing with the Technical Point of Contact (TPOC), tenants, Command Security and all other stakeholders. The TPOC will defined at the time of award.
5.3. Coordination Support: The Contractor shall work closely with the TPOC and support the needs of the project at the sponsor level. On-site coordination of meetings, developing agenda items, attending high-level meetings, generating minutes, and tracking action items shall be required. Support may require the Contractor to recommend policies, doctrine, tactics, and procedures at the DoD, Federal, State, and Local level given their past experience, expert opinion or using analysis of actual outcomes. Project support may require significant coordination and interface with various DoD and non-DoD activities located in and out of OCONUS. The TPOC shall be included on all data and non-data deliverables listed in this SOW. Meeting minutes shall be submitted no later than 10 days after each meeting.
5.4. Plans of Action and Milestone (POA&M): The Contractor shall develop a Plan of Action and Milestones (POA&M) for all tasks and milestones associated with this SOW and submit to the TPOC in accordance with section 12. The POA&M shall show the completion of all tasks, including review periods. The POA&M shall also include all contract and installation milestones. It shall utilize a Work Breakdown Structure (WBS) to compartmentalize the effort into definable work efforts and to show assigned resources to each work element and the amount of time in business days necessary to complete
Page 4 of 28 Pages each element. The POA&M shall show the inter-dependencies between all tasks and sub-tasks. It shall have a Projected versus Actual versus Baseline tracking basis and shall identify tasks, dependencies, baseline start dates, baseline finish dates, baseline durations, and percent complete for each task and sub-task. It shall be developed in Microsoft Office Project 2007 or later version.
A draft POA&M, baseline POA&M, and monthly POA&M updates shall be submitted within two (2) weeks after award . Monthly updates for the POA&M and all other monthly project management artifacts shall be submitted simultaneously prior to 5:00PM Eastern time on the 10th of each month at which time the Government TPOC has three (3) business days to provide comments and the Contractor shall update three (3) business days thereafter. At the discretion of the Government, the Contractor shall re-baseline the POA&M and provide up to two (2) intra-monthly schedule updates.
5.5. Monthly Status Report
The Contractor shall provide a monthly status report of all activities within this contract to the TPOC. The Contractor shall develop and deliver, each month, a monthly progress report which shall describe sponsor information, project information, 30-day look back of activities and deliverables, 30-day look ahead of schedule of activities and deliverables, contract history, project status, deliverable status, action items, requests for information, risks/issues, and service requests. All active and completed within the last reporting period level of effort tasks shall be identified with a description, completion status, estimated completion date, total amount, and any comments on the status.
This item shall be submitted prior to 5:00 PM Eastern Time on the 10th of each month at which time the Government has three (3) business days to provide comments and the Contractor shall update three (3) business days thereafter. All monthly contract management and project management submittals shall be submitted at the same time.
5.6. Site Survey: The Contractor shall conduct a site survey to verify current site conditions, conduct interviews for functional requirements elicitation, and prepare for design. The Contractor shall come equipped with necessary equipment to conduct the site survey such as a GPS, camera, distance wheel, PPE, and other necessary tools. A camera pass shall be requested. All pictures shall be reviewed by the site security personnel prior to leaving the site. The contractor shall prepare an in-brief and site survey checklist and submit two weeks prior to the site survey to the government. The contractor shall prepare an out-brief and submit to the government 2 days prior to the completion of the site survey. The contractor shall develop a detailed 90% site survey report and submit within 2 weeks after the site survey. After review from the government, the contractor shall submit the finalized 100% site survey report. The contractor shall scan and submit survey notes and completed checklists. The contractor shall provide a copy of the pictures taken during the survey.
5.7. IDP Development: The Contractor shall produce an Installation Design Plan (IDP) according to the Shore Installation Process Handbook (SIPH) v4.0 requirements. The Contractor shall submit IDPs to the TPOC 60%, 90%, and 100% stages. The government will require a minimum of five (5) business days to review and provide comments. The Contractor shall respond to the review and comments using a design review comments resolution matrix. The Contractor shall incorporate changes to the next stage of the IDP. If the Contractor is unsure of comments or way forward they shall coordinate a design review meeting within five (5) business days from receipt of the government review and comments.
The Contractor shall submit As-built drawings 30 days prior to the completion of the contract. The Contractor shall ensure to incorporate all the redline changes and review comments from the government.
The contractor shall turn over all IDP drawing files in both PDF and native .dwg form. All .dwg files used are mandatory deliverables to the government, including any and all XREFs used and all drawings shall be unlocked. The contractor shall also provide an excel version of the Master Parts List and any and all parts lists per series. If XREF drawing files are used in the design, the contractor shall bind all XREFs to the drawing file before final submission.
Page 5 of 28 Pages
5.8. Project Support Agreement (PSA): The contractor shall develop and track completion of the PSA through USAFE IMSC DET 4/SF, TPOC, Ramstein Air Base ESS NCO, Civil Engineering Squadron (CES), and Communication Squadron (CS). PSA shall be submitted with the 60% IDP submission.
5.9. Materials Procurement: The Contractor shall procure all equipment and material as defined in the design (SOW para 5.7) In Accordance With (IAW) ICD 705 when required. The Contractor shall submit a detailed material list to the government at the 60% design stage. The material list shall include:
manufacturer, model number, quantity, unit price, and total price. No material shall be procured by the Contractor until approved by the government in writing. After approval, the Contractor shall provide monthly material/inventory list that includes: manufacturer, model number, quantity, unit price, total price, Contractor purchase request number, Contractor purchase order number, shipping tracking information to the Contractor’s facility, and shipping tracking information to the government facility. In addition, the Contractor shall be required to provide equipment warranties from Original Equipment Manufacturer (OEM) and extended warranties, if available from OEM.
The Contractor shall inspect, conduct power tests, and other reasonable dead on arrival tests for all applicable equipment to minimize any schedule delays with faulty equipment and materials. The Contractor shall notify the Government of any faulty material via the weekly teleconferences and monthly report. The Contractor shall serve as the warranty manager by tracking the applicable government acceptance dates/receipt dates against the serial number of equipment.
5.10. Materials Storage/Site Delivery: The Contractor shall store procured installation equipment/materials in the local ICD 705 compliant Contractor-provided storage facility.
5.11. Pre-Installation Test and Checkout (PITCO)
5.11.1. The contractor shall conduct a Pre-installation Test and Checkout (PITCO) to the test the system or subcomponents to verify that they meet system performance requirements. The contractor shall prepare a PITCO plan and submit along with 90% IDP. The PITCO shall be conducted in the contractor’s ICD 705 complaint facility. The Contractor shall implement the required Information Assurance (IA) / Cyber Security controls per the applicable Security Technical Implementation Guides (STIGs) on the network switches and develop checklists to document the STIG implementations. Apply network port security.
Configure the switches with the required Virtual Local Area Networks (VLANs).
5.11.2. Digital Management Product (DMP) panel shall be programmed with representative sensors during PITCO. DMP panel, sensors, and Arming Control Unit (ACU) shall be connected and tested to verify programming and the output of dry contact alarms through an Advanced Encryption Standard
(AES) 1500.
5.11.3. All ESS equipment shall be fully programmed prior to shipment to site. All IDS alarm points, voltage windows and IP addresses shall be programmed during PITCO and shipped to the site for final Baptizing (BAP) and programming into the system.
5.11.4. The government will require a minimum of 10 business days to review and provide comments.
The contractor shall respond to the review and comments using the design review comments resolution matrix.
5.11.5. The contractor shall incorporate changes to a revised PITCO document. If necessary, the contractor shall coordinate a PITCO review meeting within five (5) business days from receipt of the government review and comments.
5.12. Installation Cutover Plan
5.12.1. The contractor shall develop an Installation Cutover plan and submit along with 90% IDP. The plan shall describe the installation steps in a sequential manner, identify any risks, provide risk mitigations, and identify any downtime with durations.
Page 6 of 28 Pages
5.12.2. The government will require a minimum of 5 business days to review and provide comments. The contractor shall respond to the review and comments using the design review comments resolution matrix.
5.12.3. The contractor shall incorporate changes to a revised Installation Cutover plan.
5.13. Installation
5.13.1. The Contractor shall procure and install all equipment/materials in accordance with SOW sections 5.13 – 5.14 and section 13. Installation will take place only after an approved 100% IDP has been delivered to the Government.
5.13.2. The Contractor shall install field devices, make connections between head end location to newly installed field devices, and troubleshoot any fiber/communication connection issues between locations.
5.13.3. The Contractor shall provide maps in a bitmap file type with 1024x768 and up to 1080p resolutions that need to be loaded into Vindicator Command and Control (VCC) for the new site location
ESS.
5.13.4. The Contractor shall be responsible for procuring all the necessary miscellaneous and consumable components to ensure the system is functional and operational to include but not limited to:
Electro metallic (EMT) conduits Rigid metal conduits Flex conduits Polyvinyl chloride (PVC) conduits Panduits Mounting equipment Brackets Cables Wires Connectors Anchor mounts Cable ties Junction boxes Gang boxes Cover plates Nuts Bolts Lugs Heat shrinks Tape Sealant
5.14. Electronic Security System (ESS) Installation Details
The Contractor shall execute the following installation details:
5.14.1. Buildings 526 528 and 529 ACS Installation and ESS Upgrades
5.14.1.1. Building 526 1st Floor Communications Room
5.14.1.1.1. Procure and install a new Hoffman enclosure with wall mount [CSD362410], mounting panel [CP3624], and keylock handle [CWHK] composed of the following items:
a. 1 x Cisco Catalyst, Layer 2, 8-port, Network Switch [WS-C3560CPD-8PT-S]
Page 7 of 28 Pages
b. 1 x Tycon 10-15Volts Direct Current (VDC) Input, 56VDC 1.25A 70W Output Voltage Converter [TP-VRHP-1256]
c. 1 x ComNet Mini 10/100/1000Mbps Ethernet Media Converter, B-side [CNMCSFP/M]
d. 1 x ComNet Small Form-factor Pluggable (SFP) Copper and Optical Fiber Transceiver
[SFP-12B]
e. 1 x CablesToGo 20m LC-ST 9/125 OS2 Simplex Single-Mode PVC Fiber Optic Cable –
Yellow [34722] (Or Equivalent)
f. 1 x Honeywell Vindicator Network Security Appliance V5 [548-333-00-10]
g. 1 x Honeywell Vindicator Sensor Input Module [536-33002-01]
h. 1 x Mercury Single Door Controller [MR50]
i. 1 x LifeSafety Power Supply, 150 Watts [FPO150]
j. 1 x LifeSafety Power Distribution Module [D8]
k. 2 x Power Sonic 18 ampere hour (Ah), 12VDC batteries with F2 terminal [PS-12180F2]
l. 1 x Honeywell Enclosure Tamper Switches [2AC59]
m. 1 x RS Electronics Battery Test Switch [448-1065]
n. 1 x 220 Volts Alternating Current (VAC) Europe-style Single outlet with cover
o. 1 x Weiland Terminal board [29.401.1653.0] (Or Equivalent)
p. 1 x CAT6 patch cable
q. Cable Tie Anchor Mounts
r. Wire Ducts
5.14.1.1.2. Install the single-mode duplex OS2 fiber cable from the new ACS enclosure to the fiber enclosure inside the communications room and port to be designated by Communications Squadron (CS). Install the necessary cabling in EMT conduit.
5.14.1.1.3. Procure and install power cables from the new ACS enclosure to nearest power panel to be designated by Civil Engineering Squadron (CES). Install the necessary cabling in EMT conduit.
5.14.1.2. Building 526 1st Floor Front Entrance
5.14.1.2.1. Remove the existing double-door and frame and procure and install two (2) doors with door closers, a center mullion, and door frame. One door leaf will be for egress only. The other door leaf will be will be controlled by the access control system. On the egress only door, it will have a lever handle to retract the latch bolt on the secure side, but will not have any handles on the unsecured side. On the ACS door leaf, it will have a fixed dummy vertical hand to pull the door on the unsecured side and a lever handle to retract the latch bolt on the secure side.
5.14.1.2.2. Procure and install one (1) Eff Eff electric door strike [142UR series] (Or Equivalent) on the center mullion for the ACS door leaf.
5.14.1.2.3. Procure and install one (1) HID multiclass card reader [RPK40]. The card reader will be wired and configured to control the electric door strike.
5.14.1.2.4. Connect the ACS devices to ACS enclosure in building 526 1st floor communications room.
5.14.1.2.5. Install the necessary cabling for the ACS devices in EMT conduit.
5.14.1.3. Building 526 1st Floor Side Entrance
5.14.1.3.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.4. Building 526 1st Floor Back Entrance
5.14.1.4.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the
Page 8 of 28 Pages emergency exit door.
5.14.1.5. Building 526 2nd Room 201
5.14.1.5.1. Inside the existing Vindicator IDS enclosure, procure and install one (1) Honeywell Vindicator AES-1500T Security Device, Wire/RJ45 [548-34081-21]. Remove the unneeded equipment and properly dispose via DRMO.
5.14.1.5.2. Reconnect the existing IDS sensors on the new Vindicator panel.
5.14.1.5.3. Procure and installed one (1) riser-rated CAT6 cable to connect the Ethernet switch in the ACS enclosure in building 526 1st floor communications room.
5.14.1.5.4. Install the necessary cabling in EMT conduit.
5.14.1.6. Building 526 2nd Room 213
5.14.1.6.1. Inside the existing Vindicator IDS enclosure, procure and install one (1) Honeywell Vindicator AES-1500T Security Device, Wire/RJ45 [548-34081-21]. Remove the unneeded equipment and properly dispose via DRMO.
5.14.1.6.2. Reconnect the existing IDS sensors on the new Vindicator panel.
5.14.1.6.3. Procure and installed one (1) riser-rated CAT6 cable to connect the Ethernet switch in the ACS enclosure in building 526 1st floor communications room.
5.14.1.6.4. Install the necessary cabling in EMT conduit.
5.14.1.7. Building 526 3rd Floor Side Entrance
5.14.1.7.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.8. Building 526 3rd Floor Back Entrance
5.14.1.8.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.9. Building 528 1st Floor Communications Room
5.14.1.9.1. Procure and install one (1) Hoffman enclosure with wall mount [CSD242410], mounting panel [CP2424], and keylock handle [CWHK] composed of the following items:
a. 1 x ComNet Mini 10/100/1000Mbps Ethernet Media Converter, B-side [CNMCSFP/M]
b. 1 x ComNet Small Form-factor Pluggable (SFP) Copper and Optical Fiber Transceiver
[SFP-12B]
c. 1 x CablesToGo 20m LC-ST 9/125 OS2 Simplex Single-Mode PVC Fiber Optic Cable –
Yellow [34722] (Or Equivalent)
d. 1 x Honeywell Vindicator Network Security Appliance V5 [548-333-00-10]
e. 1 x Honeywell Vindicator Sensor Input Module [536-33002-01]
f. 1 x Mercury Single Door Controller [MR50]
g. 1 x LifeSafety Power Supply, 75 Watts [FPO75]
h. 1 x LifeSafety Power Distribution Module [D8]
i. 2 x Power Sonic 18 Ah, 12VDC batteries with F2 terminal [PS-12180F2]
j. 1 x Honeywell Enclosure Tamper Switch [2AC59]
k. 1 x RS Electronics Battery Test Switch [448-1065]
l. 1 x 220 Volts Alternating Current (VAC) Europe-style Single outlet with cover
m. 1 x Weiland Terminal board [29.401.1653.0] (Or Equivalent)
n. 1 x CAT6 patch cable
o. Cable Tie Anchor Mounts
Page 9 of 28 Pages
p. Wire Ducts
5.14.1.9.2. Install the single-mode duplex OS2 fiber cable from the new ACS enclosure to the fiber enclosure inside the communications room and port to be designated by Communications Squadron (CS). Install the necessary cabling in EMT conduit.
5.14.1.9.3. Procure and install power cables from the new ACS enclosure to nearest power panel to be designated by Civil Engineering Squadron (CES). Install the necessary cabling in EMT conduit.
5.14.1.10. Building 528 1st Floor Front Entrance
5.14.1.10.1. Remove the existing double-door and frame and procure and install two (2) doors with door closers, a center mullion, and door frame. One door leaf will be for egress only. The other door leaf will be will be controlled by the access control system. On the egress only door, it will have a lever handle to retract the latch bolt on the secure side, but will not have any handles on the unsecured side. On the ACS door leaf, it will have a fixed dummy vertical hand to pull the door on the unsecured side and a lever handle to retract the latch bolt on the secure side.
5.14.1.10.2. Procure and install one (1) Eff Eff electric door strike [142UR series] (Or Equivalent) on the center mullion for the ACS door leaf.
5.14.1.10.3. Procure and install one (1) HID multiclass card reader [RPK40]. The card reader will be wired and configured to control the electric door strike.
5.14.1.10.4. Connect the ACS devices to ACS enclosure in building 528 1st floor communications room.
5.14.1.10.5. Install the necessary cabling for the ACS devices in EMT conduit.
5.14.1.11. Building 528 1st Floor Side Entrance 1
5.14.1.11.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.12. Building 528 1st Floor Side Entrance 2
5.14.1.12.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.13. Building 528 2nd Floor Side Entrance 1
5.14.1.13.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.14. Building 528 2nd Floor Side Entrance 2
5.14.1.14.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.15. Building 528 3rd Floor Side Entrance 1
5.14.1.15.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.16. Building 528 3rd Floor Side Entrance 2
5.14.1.16.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the
5.14.1.17. Building 529 1st Floor Communications Room 113
Page 10 of 28 Pages
5.14.1.17.1. Procure and install a new Hoffman enclosure with wall mount [CSD362410], mounting panel [CP3624], and keylock handle [CWHK] composed of the following items:
a. 1 x Cisco Catalyst, Layer 2, 8-port, Network Switch [WS-C3560CPD-8PT-S]
b. 1 x Tycon 10-15VDC Input, 56VDC 1.25A 70W Output Voltage Converter [TP-VRHP-
1256]
c. 1 x ComNet Mini 10/100/1000Mbps Ethernet Media Converter, B-side [CNMCSFP/M]
d. 1 x ComNet Small Form-factor Pluggable (SFP) Copper and Optical Fiber Transceiver
[SFP-12B]
e. 1 x CablesToGo 20m LC-ST 9/125 OS2 Simplex Single-Mode PVC Fiber Optic Cable –
Yellow [34722] (Or Equivalent)
f. 1 x Honeywell Vindicator Network Security Appliance V5 [548-333-00-10]
g. 1 x Honeywell Vindicator Sensor Input Module [536-33002-01]
h. 2 x Mercury Single Door Controllers [MR50]
i. 1 x LifeSafety Power Supply, 150 Watts [FPO150]
j. 1 x LifeSafety Power Distribution Module [D8]
k. 2 x Power Sonic 18 Ah, 12VDC batteries with F2 terminal [PS-12180F2]
l. 1 x Honeywell Enclosure Tamper Switches [2AC59]
m. 1 x RS Electronics Battery Test Switch [448-1065]
n. 1 x 220 Volts Alternating Current (VAC) Europe-style Single outlet with cover
o. 1 x Weiland Terminal board [29.401.1653.0] (Or Equivalent)
p. 1 x CAT6 patch cable
q. 1 x Riser-rated Plenum CAT6 cable
r. Cable Tie Anchor Mounts
s. Wire Ducts
5.14.1.17.2. Install the single-mode duplex OS2 fiber cable from the new ACS enclosure in room 113 to the fiber enclosure inside the other communications room 106 and port to be designated by Communications Squadron (CS). Install the necessary cabling in EMT conduit.
5.14.1.17.3. Procure and install power cables from the new ACS enclosure to nearest power panel to be designated by Civil Engineering Squadron (CES). Install the necessary cabling in EMT conduit.
5.14.1.18. Building 529 1st Floor Front Entrance
5.14.1.18.1. Remove the existing double-door and frame and procure and install two (2) doors with door closers, a center mullion, and door frame. One door leaf will be for egress only. The other door leaf will be will be controlled by the access control system. On the egress only door, it will have a lever handle to retract the latch bolt on the secure side, but will not have any handles on the unsecured side. On the ACS door leaf, it will have a fixed dummy vertical hand to pull the door on the unsecured side and a lever handle to retract the latch bolt on the secure side.
5.14.1.18.2. Procure and install one (1) Eff Eff electric door strike [142UR series] (Or Equivalent) on the center mullion for the ACS door leaf.
5.14.1.18.3. Procure and install one (1) HID multiclass card reader [RPK40]. The card reader will be wired and configured to control the electric door strike.
5.14.1.18.4. Connect the ACS devices to ACS enclosure in building 529 1st floor communications room.
5.14.1.18.5. Install the necessary cabling for the ACS devices in EMT conduit.
5.14.1.19. Building 529 1st Floor Side Entrance 1 - South
5.14.1.19.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the
Page 11 of 28 Pages
5.14.1.20. Building 529 1st Floor Rear Wing Side Entrance
5.14.1.20.1. Remove the existing double-door and frame and procure and install two (2) doors with door closers, a center mullion, and door frame. One door leaf will be for egress only. The other door leaf will be will be controlled by the access control system. On the egress only door, it will have a lever handle to retract the latch bolt on the secure side, but will not have any handles on the unsecured side. On the ACS door leaf, it will have a fixed dummy vertical hand to pull the door on the unsecured side and a lever handle to retract the latch bolt on the secure side.
5.14.1.20.2. Procure and install one (1) Eff Eff electric door strike [142UR series] (Or Equivalent) on the center mullion for the ACS door leaf.
5.14.1.20.3. Procure and install one (1) HID multiclass card reader [RPK40]. The card reader will be wired and configured to control the electric door strike.
5.14.1.20.4. Connect the ACS devices to ACS enclosure in building 529 1st floor communications room.
5.14.1.20.5. Install the necessary cabling for the ACS devices in EMT conduit.
5.14.1.21. Building 529 1st Floor Rear Wing Back Entrance
5.14.1.21.1. Procure and install one (1) STI Exit Stopper Multifunction Door Alarm [STI-6400] on the emergency exit door.
5.14.1.22. Building 529 2nd Floor Room 222
5.14.1.22.1. Remove existing Hoffman CSD24168 enclosure and it components. Procure and install one
(1) Hoffman enclosure with wall mount [CSD242410], mounting panel [CP2424], and keylock handle [CWHK] composed of the following items:
a. 1 x Honeywell Vindicator Network Security Appliance V5 [548-333-00-10]
b. 2 x Honeywell Vindicator Sensor Input Modules [536-33002-01]
c. 2 x Mercury Single Door Controllers [MR50]
d. 1 x LifeSafety Power Supply, 75 Watts [FPO75]
e. 2 x LifeSafety Power Distribution Modules [D8]
f. 2 x Power Sonic 18 Ah, 12VDC batteries with F2 terminal [PS-12180F2]
g. 1 x Honeywell Enclosure Tamper Switch [2AC59]
h. 1 x RS Electronics Battery Test Switch [448-1065]
i. 1 x Omron Relay for ACU
j. 1 x 220 Volts Alternating Current (VAC) Europe-style Single outlet with cover
k. 1 x Weiland Terminal board [29.401.1653.0] (Or Equivalent)
l. 1 x CAT6 patch cable
m. Cable Tie Anchor Mounts
n. Wire Ducts
5.14.1.22.2. Reconnect the existing IDS sensors on the new Vindicator panel.
5.14.1.22.3. Procure and install one (1) GE Security 360 Degree Passive Infrared (PIR) [AP669] (Or Equivalent) to cover both the windows at the back of the room.
5.14.1.22.4. Remove existing flex conduit and procure and install EMT conduit for the existing and new IDS and ACS devices.
5.14.1.23. Procure and installed one (1) riser-rated CAT6 cable to connect the new Vindicator V5 to the Ethernet switch in the ACS enclosure in building 529 1st floor communications room. Install the necessary cabling in EMT conduit.
Page 12 of 28 Pages
5.14.1.24. Building 529 2nd Floor Rear Wing Back Entrance
5.14.1.24.1. Remove the existing door and frame and procure and install one (1) door with a door closer and door frame. The door leaf will have a fixed dummy vertical hand to pull the door on the unsecured side and a lever handle to retract the latch bolt on the secure side.
5.14.1.24.2. Procure and install one (1) Eff Eff electric door strike [142UR series] (Or Equivalent).
5.14.1.24.3. Procure and install one (1) HID multiclass card reader [RPK40]. The card reader will be wired and configured to control the electric door strike.
5.14.1.24.4. Connect the ACS devices to ESS enclosure in building 529 2nd floor room 222.
5.14.1.24.5. Install the necessary cabling for the ACS devices in EMT conduit.
5.14.1.25. Building 529 3rd Floor Rear Wing Back Entrance
5.14.1.25.1. Remove the existing door and frame and procure and install one (1) door with a door closer and door frame. The door leaf will have a fixed dummy vertical hand to pull the door on the unsecured side and a lever handle to retract the latch bolt on the secure side.
5.14.1.25.2. Procure and install one (1) Eff Eff electric door strike [142UR series] (Or Equivalent).
5.14.1.25.3. Procure and install one (1) HID multiclass card reader [RPK40]. The card reader will be wired and configured to control the electric door strike.
5.14.1.25.4. Connect the ACS devices to ESS enclosure in building 529 2nd floor room 222.
5.14.1.25.5. Install the necessary cabling for the ACS devices in EMT conduit. Transition from EMT to rigid metal conduit if it is determined that it will be more efficient to penetrate outside the exterior wall to go up from 2nd floor rear wing back entrance to the 3rd floor rear wing back entrance.
5.14.1.26. Building 203 Visitor Control ACS Enrollment
5.14.1.26.1. Update the ACS enrollment station to program the new locations.
5.14.1.27. Building 201 Room B024
5.14.1.27.1. Procure and install one (1) x Cisco Catalyst Layer 3 48-port 4 SFP, Network Switch [WS- C3560-48TS-S] inside the existing equipment rack.
5.14.1.27.2. Program and configure Virtual Local Area Networks (VLANs) for building 2371 Intrusion Detection System (IDS), building 2371 Federal Information Processing Standard 140-2 compliant IDS encrypted network, building 201 IDS and Access Control System (ACS), building 201 IDS encrypted network, Closed Circuit Television (CCTV) system, and Public Address (PA) system on the network switch
5.14.1.27.3. Procure and install four (4) Cisco Gigabit SFP Transceivers [GLC-LH-SMD] into the 4 SFP ports of the new network switch. Ensure the Cisco SFP Transceivers are compatible with the ComNet SFP transceivers and media converters.
5.14.1.27.4. Procure and install four (4) CablesToGo 20m LC-ST 9/125 OS2 Simplex Single-Mode PVC Fiber Optic Cable – Yellow [34722] (Or Equivalent) from the patch panels and ports to be designated by Communications Squadron (CS) to the Cisco SFP Transceivers. Install the necessary cabling in EMT conduit or in existing cable trays.
5.14.1.27.5. Procure and (1) CAT6 patch cable to connect the new Ethernet Switch to the existing Ethernet Switch for B201 Vindicator System.
5.14.1.27.6. Ensure all of the new Honey Vindicator ACS components are compatible with the existing
Page 13 of 28 Pages
ACS V5 server firmware, release, and service pack.
5.14.1.28. Building 2371 Room 133
5.14.1.28.1. Procure and install one (1) x Cisco Catalyst Layer 3 48-port 4 SFP, Network Switch [WS- C3560-48TS-S] inside the existing equipment rack.
5.14.1.28.2. Program and configure the Virtual Local Area Networks (VLANs) for building 2371 Intrusion Detection System (IDS), building 2371 Federal Information Processing Standard 140-2 compliant IDS encrypted network, and building 201 IDS.
5.14.1.28.3. Procure and install one (1) Cisco Gigabit SFP Transceiver [GLC-LH-SMD] into the SFP port of the new network switch
5.14.1.28.4. Procure and install one (1) CablesToGo 20m LC-ST 9/125 OS2 Simplex Single-Mode PVC Fiber Optic Cable – Yellow [34722] (Or Equivalent) from the patch panel and port to be designated by Communications Squadron (CS) to the Cisco SFP Transceiver. Install the necessary cabling in EMT conduit or in existing cable trays.
5.14.1.28.5. Procure and (1) CAT6 patch cable to connect the new Ethernet Switch to the existing Ethernet Switch for B2371 Vindicator System.
5.14.1.28.6. Program the alarms points to report to the existing Vindicator V5 IDS Server. Provide and load the associated maps in bitmap file type into the Vindicator IDS VCC. Only show the card reader tampers and offline alarms into the IDS VCC for the alarm operators as there are no Balanced Magnetic Switches (BMS) to be installed for the ACS.
5.14.1.28.7. Ensure all of the new Honey Vindicator IDS components are compatible with the existing IDS V5 server firmware, release, and service pack
5.14.1.29. Required Site Support
5.14.1.29.1. Building 526 1st Floor Communications Room
5.14.1.29.1.1. Site / CE / CS to provide room for a new Vindicator ACS enclosure
5.14.1.29.1.2. Site / Civil Engineering Squadron (CES) to provide one (1) dedicated 16 Amp 230 50 Hz VAC circuit breaker to supply power to the new ACS enclosure
5.14.1.29.1.3. Site / Communications Squadron to provide 2 strands / duplex of single-mode OS2 fiber cable from building 526 to building 407
5.14.1.29.1.4. Site / Communications Squadron to provide 2 strands / duplex of single-mode OS2 fiber cable from building 407 to building 201
5.14.1.29.2. Building 528 1st Floor Communications Room
5.14.1.29.2.1. Site / CE / CS to provide room for a new Vindicator ACS enclosure
5.14.1.29.2.2. Site / Civil Engineering Squadron (CES) to provide one (1) dedicated 16 Amp 230 50 Hz VAC circuit breaker to supply power to the new ACS enclosure
5.14.1.29.2.3. Site / Communications Squadron to provide 2 strands / duplex of single-mode OS2 fiber cable from building 528 to building 407
5.14.1.29.2.4. Site / Communications Squadron to provide 2 strands / duplex of single-mode OS2 fiber cable from building 407 to building 201
5.14.1.29.3. Building 529 1st Floor Communications Room
5.14.1.29.3.1. Site / CE / CS to provide room for a new Vindicator ACS enclosure
Page 14 of 28 Pages
5.14.1.29.3.2. Site / Civil Engineering Squadron (CES) to provide one (1) dedicated 16 Amp 230 50 Hz VAC circuit breaker to supply power to the new ACS enclosure
5.14.1.29.3.3. Site / Communications Squadron to provide 2 strands of single-mode fiber from building 529 to building 221
5.14.1.29.3.4. Site / Communications Squadron to provide 2 strands of single-mode fiber from building 221 to building 201
5.14.1.29.4. Building 201 Room B024 to Building 2371 Room 133
5.14.1.29.5. Site / Communications Squadron to provide 2 strands / duplex of single-mode OS2 fiber cable from building 201 room B204 to building 2371 room 133 Vindicator server room
5.14.2. Building 543 ESS Upgrades
5.14.2.1. Building 543 Room 26
5.14.2.1.1. Procure and install a Middle Atlantic EWR Series wall-mounted equipment rack [EWR-10- 17] with the following components:
a. 1 x Middle Atlantic Vented Front Door, 10 RU Racks, 64% Open [LVFD-10] (Or Equiva-lent)
b. 1 x Rackmount Power, 9 Outlet, 15A, 230VAC, Basic Surge (Or Equivalent)
c. 2 x Middle Atlantic Horizontal Cable Manager, 1 RU, Micro-clip [HCM-1] (Or Equivalent)
d. 1 x Corning Closet Connector Housing (CCH), Black, Empty, One Rack Unit High (1
RMU), Holds Two CCH Connector Panels [CCH-01U]
e. 1 x Corning Closet Connector Housing Cassette for 1 CCH Panel [CCH-CS]
f. 1 x Corning Closet Connector Housing (CCH) Panel, ST Compatible adapters, Simplex, UPC, 12 fiber, Single-mode (OS2) [CCH-CP12-19T]
g. 1 x ComNet Card Cage, 19” Rack Mount, 90-264 VAC [C1-EU]
h. 2 x ComNet 1 Channel Fiber Media Converter, A-side [CNFE1002S1A]
i. 2 x Corning UniCam High-Performance Connector, ST Compatible, Single-mode (OS2), ceramic ferrule, logo, single pack, amber housing, blue boot [95-200-51] (Or Equivalent)
j. 1 x ComNet Video Transmitter, multi-mode fiber (MMF) [FVT10]
k. 1 x Panduit OptiCam ST OM1 62.5/125µm Composite Ferrule Multimode Simplex Con-nector, For 900µm Buffered Fiber Installation, Includes Electric White Boot [FSTMPC6EI] (Or Equivalent)
l. 1 x Cisco Catalyst, Layer 2, 24-port, 4 SFP, Network Switch [WS-C2960X-24TS-L]
m. 2 x Cisco Gigabit SFP Transceiver [GLC-LH-SMD]
n. 2 x Panduit LC OptiCam 9µm Single-mode Duplex Connector Blue Boots -Pre-polish
[FLCDSCBUY] (Or Equivalent)
o. 2 x Honeywell Enclosure Tamper Switch [2AC59]
p. 1 x Single, 12 VDC power supply, 1 Amp, 230 VAC input
q. 1 x 220 Volts Alternating Current (VAC) Europe-style Single outlet with cover
r. 1 x Riser-rated Plenum CAT6 cable
s. CAT6 Patch cables
t. Power cables
u. Coax cable
5.14.2.1.2. Connect and terminate the fiber optic cables (to be installed by local Communications Squadron) into the corresponding components in the equipment rack
5.14.2.1.3. Procure and install 18AWG 6 conductor wire to connect the tamper switches to the existing IDS in room 25.
5.14.2.1.4. Program and configure the Virtual Local Area Networks (VLANs) for building 2371
Page 15 of 28 Pages
Intrusion Detection System (IDS), building 2371 Federal Information Processing Standard (FIPS) 140-2 compliant IDS encrypted network, building 201 IDS and Access Control System (ACS), Closed Circuit Television (CCTV) system, and Public Address (PA) system on the network switch
5.14.2.1.5. Implement the required Information Assurance (IA) / Cyber Security controls per the applicable Security Technical Implementation Guides (STIGs) on the network switch
5.14.2.1.6. Procure and install power cable from the new equipment to nearest power panel to be designated by the Site / Construction Contractor. Install the necessary cabling in EMT conduit.
5.14.2.1.7. Utilize existing conduit as much as possible. Procure and install EMT conduit when necessary.
5.14.2.2. Building 543 Room 25
5.14.2.2.1. Install the riser-rated CAT6 cables from the equipment rack in room 26 into the existing IDS enclosure ENC-0543-0025-01 in room 25. Connect the CAT6 cable into the existing Vindicator V5 panel.
5.14.2.2.2. Procure and install one (1) Honeywell Vindicator Sensor Input Module (SIM) [536-33002- 01] into the existing V5 panel.
5.14.2.2.3. Connect and terminate the cable/wires from the tamper switches in the equipment rack in room 26 into the new V5 SIM.
5.14.2.2.4. Install the necessary cabling in EMT conduit.
5.14.2.2.5. Remove the existing ComNet Media Converter inside the ENC-0543-0025-01 to be turned over for maintenance spares.
5.14.2.3. Building 543 Room 25 Entrance Camera
5.14.2.3.1. Install the coax cable from the equipment rack in room 26, through room 25 IDS enclosure ENC-0543-0025-01, and into the existing camera. Install EMT conduit when necessary.
5.14.2.4. Building 543 Room 23
5.14.2.4.1. Procure and install one (1) ComNet 1 Channel Fiber Media Converter, B-side, mini [CNFE1002S1B-M] to replace the existing modem inside IDS enclosure ENC-0543-0023-
01. Turn over the modem to ESS Maintenance for spares inventory.
5.14.2.4.2. Procure and install a ST connector to terminate the OS2 fiber optic simplex cable (to be installed by local Communications Squadron) into the media converter
5.14.2.4.3. Procure and install one (1) CAT6 Patch cable to connect from media converter to the existing DCB FT-6602 Line Encryptor
5.14.2.5. Building 543 Room 21A
5.14.2.5.1. Procure and install one (1) ComNet 1 Channel Fiber Media Converter, B-side, mini [CNFE1002S1B-M] to replace the existing modem inside IDS enclosure ENC-0543-021A-
01. Turn over the modem to ESS Maintenance for spares inventory.
5.14.2.5.2. Procure and install a ST connector to terminate the OS2 fiber optic simplex cable (to be installed by local Communications Squadron) into the media converter
5.14.2.5.3. Procure and install one (1) CAT6 Patch cable to connect from media converter to the existing DCB FT-6602 Line Encryptor
Page 16 of 28 Pages
5.14.2.5.4. Procure and install one (1) ComNet Video Receiver, MMF, mini [FVR10M] inside the existing IDS enclosure ENC-0543-021A-01
5.14.2.5.5. Procure and install a ST connector to terminate the OM1 fiber optic cable (to be installed by local Communications Squadron) into the Video receiver.
5.14.2.5.6. Connect the existing coax cable from the existing 22” CCTV LCD monitor into the Video receiver
5.14.2.6. Building 543 Room 101
5.14.2.6.1. Procure and install the following inside ENC-0543-0101-01 and/or ENC-0543-0101-02 depending on space availability:
a. 1 x Tycon 10-15VDC Input, 56VDC 1.25A 70W Output Voltage Converter [TP-VRHP- 1256]
b. 1 x Cisco Catalyst, Layer 2, 8-port, Network Switch [WS-C3560CPD-8PT-S]
c. 1 x Cisco Gigabit SFP Transceiver [GLC-LH-SMD]
d. 1 x Panduit LC OptiCam 9µm Single-mode Duplex Connector Blue Boots -Pre-polish
[FLCDSCBUY] (Or Equivalent)
e. 1 x ComNet 1 Channel Fiber Media Converter, A-side, mini [CNFE1002S1A-M]
f. 1 x Corning UniCam High-Performance Connector, ST Compatible, Single-mode (OS2), ceramic ferrule, logo, single pack, amber housing, blue boot [95-200-51] (Or Equivalent)
g. 1 x ComNet Video Transmitter, MMF, mini [FVT11M]
h. 1 x ComNet Video Receiver, MMF, mini [FVR10M]
i. 2 x Panduit OptiCam ST OM1 62.5/125µm Composite Ferrule Multimode Simplex Con-nector, For 900µm Buffered Fiber Installation, Includes Electric White Boot [FSTMPC6EI] (Or Equivalent)
j. CAT6 patch cables
k. Power cables
5.14.2.6.2. Connect and terminate the fiber optic cables (to be installed by local Communications Squadron) into the corresponding components
5.14.2.6.3. Program and configure the Virtual Local Area Networks (VLANs) for building 2371 Intrusion Detection System (IDS), building 2371 Federal Information Processing Standard (FIPS) 140-2 compliant IDS encrypted network, building 201 IDS and Access Control System (ACS), Closed Circuit Television (CCTV) system, and Public Address (PA) system on the network switch
5.14.2.6.4. Implement the required Information Assurance (IA) / Cyber Security controls per the applicable Security Technical Implementation Guides (STIGs) on the network switch
5.14.2.6.5. Utilize existing conduit as much as possible. Procure and install EMT conduit when necessary.
5.14.2.7. Required Site Support
5.14.2.7.1. Building 543 Room 26
5.14.2.7.1.1. Site / Construction Contractor to provide one (1) dedicated 16 Amp 230 50 Hz VAC circuit breaker to supply power to the new equipment rack.
5.14.2.7.2. Building 543 Communication Entry Point to Room 26
5.14.2.7.2.1. Site / Communications Squadron to provide 2 strands / duplex of single-mode OS2 fiber cable or a 6-12 strands of OS2 distribution fiber cable
5.14.2.7.3. Building 543 Room 23 to Room 26
Page 17 of 28 Pages
5.14.2.7.3.1. Site / Communications Squadron to provide 1 strand / simplex of single-mode OS2 fiber cable
5.14.2.7.4. Building 543 Room 21A to Room 26
5.14.2.7.4.1. Site / Communications Squadron to provide 1 strand / simplex of single-mode OS2 fiber cable
5.14.2.7.5. Building 543 Room 101 (Basement Corridor) to Room 26
5.14.2.7.5.1. Site / Communications Squadron to provide 2 strands / duplex of single-mode OS2 fiber cable
5.14.2.7.5.2. Site / Communications Squadron to provide 1 strand / simplex of multi-mode OM1 fiber cable
5.14.2.7.6. Building 543 Room 101 (Basement Corridor) to Room 21A
5.14.2.7.6.1. Site / Communications Squadron to provide 1 strand / simplex of multi-mode OM1 fiber cable
5.14.2.7.7. Building 543 Communication Entry Point to Room 26 to Building 201 Room B024
5.14.2.7.7.1. Communications Squadron to provide 2 strands of single-mode fiber
5.14.2.7.8. Building 201 Room B024 to Building 2371 Room 133
5.14.2.7.8.1. Communications Squadron to provide 2 strands of single-mode fiber
5.14.3. Building 3334 ESS Upgrades
5.14.3.1. Building 3334 Room 127
5.14.3.1.1. Remove the existing Honeywell 548-31378-01 UHS-1600 Data Transmitter and procure and install one (1) Honeywell Vindicator AES-1500T Security Device, Wire/RJ45 [548-34081- 21] in the existing enclosure CP-3334-0127-01. Program the new AES-1500T Security Device with all of the required inputs and outputs.
5.14.3.1.2. Procure and install one (1) ComNet 1 Channel Fiber Media Converter, single-mode, B-side [CNFE1002S1B-M] inside the existing enclosure.
5.14.3.1.3. Procure and install one (1) DCB Line Encryptor [FT-6602] inside the existing enclosure and connect it in-line with CAT6 Ethernet patch cables from the new AES-1500T Security Device before connecting to the ComNet Fiber Media Converter.
5.14.3.1.4. Procure and install one (1) Life Safety Power Supply [FPO75] to replace the existing Altronix OLS180220 Power Supply
5.14.3.1.5. Procure and install one (1) Power Sonic 18 Ah, 12VDC battery [PS-12180F2] to replace the existing YUASA NP7-12 batteries
5.14.3.1.6. Procure and install one (1) LifeSafety 8-port Power Distribution Module [D8] to replace the existing Altronix PD8
5.14.3.1.7. Right next to existing enclosure CP-3334-0127-01, procure and install one (1) Digital Monitoring Products (DMP) Premise Control Unit (PCU) with enclosure composed of the following items:
a. 1 x DMP Security Panel PCU [XR550]
b. 1 x GRI Tamper Switch [TSC-20]
c. 2 x Yuasa 12V, 7AH Battery [NP7-12]
d. 1 x DMP Output Module [860]
Page 18 of 28 Pages
e. 1 x DMP Relay Module [305]
f. 1 x DMP Wire Harness [300]
g. 1 x DMP Expansion Input Module [712-8]
h. 1 x Terminal Board Weiland [29.401.1653.0] (Or Equivalent)
i. 1 x Datwyler Lockable RJ-45 Outlet [DAT-417503]
j. 1 x Datwyler RJ-45 Module [DAT-418061]
k. 1 x Kussmaul Low Voltage Alarm Relay [091-85-12]
l. 1 x AlarmSaf 12VDC Fail Relay [RBK-124AC]
5.14.3.1.8. Procure and install one (1) DMP Arming Control Unit (ACU) [7060AN-W]
5.14.3.1.9. Procure and install one (1) Dell Latitude laptop for the management of the DMP PCU.
Remove built-in microphones and webcams hardware and at the device manager and BIOS
5.14.3.1.10. Procure and install one (1) Magnasphere High Security Switch Level 2 BMS [HSS-L2D- 000] Balance Magnetic Switches (BMS) to replace the existing BMS on the main entrance door.
5.14.3.1.11. Procure and install one (1) curtain Passive Infrared (PIR) motion detector to cover the main entrance.
5.14.3.1.12. Remove the existing 360 degree PIR near the main entrance that is currently being blocked by a column.
5.14.3.1.13. Procure and install one (1) Magnasphere High Security Switch Level 2 BMS [HSS-L2D- 000] to replace the existing BMS on the side door.
5.14.3.1.14. Procure and install one (1) curtain PIR motion detector to cover the side door.
5.14.3.1.15. Procure and install two (2) Magnasphere rollup door bracket w/o embedded End of Line Resister (HSS-L2D Mount) [HSS-1451-L2S000] on the roll-up door.
5.14.3.1.16. Remove the existing 360 degree PIR and curtain PIR near on the west wall.
5.14.3.1.17. Procure and install one (1) curtain PIR motion detector on a bracket and angled to cover the roll-up door.
5.14.3.1.18. Remove the existing 360 degree PIR southeast wall.
5.14.3.1.19. Rewire and connect all the field sensors to the new DMP PCU.
5.14.3.1.20. Output all of the alarms from the DMP PCU to the new AES-1500T Security Device.
5.14.3.1.21. Procure and install fiber jumper cable and connectors in EMT conduit to connect one (1) single-mode fiber strand from one of the designated ports of the existing patch panel in the Communications Room to the ComNet Fiber Media Converter inside the IDS enclosure.
5.14.3.1.22. Install the necessary IDS cabling in EMT conduit
5.14.3.2. Building 2371 Room 133 ESS Sever Room
5.14.3.2.1. Procure and install one (1) single-mode fiber patch cable to the port to be designated by Communications Squadron to the existing Vindicator ESS equipment rack.
5.14.3.2.2. Procure and install one (1) ComNet Fiber Media Converter, [CNFE1002S1A] into a spare slot in the existing card cage.
5.14.3.2.3. Procure and install one (1) CAT6 Ethernet patch cable to connect the ComNet Fiber Media Converter and into the existing Cisco Ethernet network switch in the existing ESS equipment rack.
Page 19 of 28 Pages
5.14.3.2.4. Program all IDS alarms to report to Vindicator V5 IDS server.
5.14.3.3. Required Site Support
5.14.3.3.1. Site / Communications Squadron to provide 1 strand / simplex of single-mode OS2 fiber cable from building 3334 Communications Room to building 2371 room 133 ESS Server Room.
5.15. System Operational Verification Test (SOVT):
5.15.1. The Contractor shall conduct testing and evaluation to ensure that all equipment and systems comply with the performance specifications outlined in the applicable technical manuals, test specifications and requirement documents. The Contractor shall adhere the testing phases of the AFI 31-
101. The Contractor shall develop a 90% System Operation Verification Test (SOVT) document, and submit to the government TPOC at the 90% IDP stage.