Technical Specifications English
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Running Grooving Q A.docx | DOCX document | |
| PPI Questionnaire.docx | DOCX document | |
| PPI Reference List.docx | DOCX document | |
| FA5575-11-R-0006 Groove North Touchdown Zone.doc | DOC document | |
| AF 3052 Contractor.xls | XLS spreadsheet | |
| 10-1029 Specs Spanish.pdf | ||
| 10-1029 Drawings.pdf | ||
| 10-1029 Schedule of Material Submittals.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PREPARED FOR DEPARTMENT OF THE
AIR FORCE
BY
VINNELL, BROWN & ROOT
ENGINEERING DESIGN SECTION
MORON AIR BASE
TECHNICAL PROVISIONS & SPECIFICATIONS FOR:
PROJECT QUUG 10-1029
GROOVE NORTH TOUCHDOWN ZONE
Prepared by: _____________________________________________________________________ Name: Antonio Menéndez, CECD Date: 24 Jun 11
Approved by:____________________________________________________________________ Name: Britton L. Clair, CEC Date: 24 Jun 11
TP-2
LIST OF SPECIFICATIONS
DIVISION 1 - GENERAL REQUIREMENTS
01000 Scope of Work, Drawings and Special Conditions 4 01011 General Conditions 15
DIVISION 2 - SITE WORK
02960 Grooving for Airfield Pavements 4 02961 Rigid Pavement Repair 19
DIVISION 3 TO 16 - NOT USED
01000 - 1
SECTION 01000
SCOPE OF WORK, DRAWINGS AND SPECIAL CONDITIONS
1. SCOPE OF WORK: The work includes, but is not limited to, the following items:
- On-site layout.
- Grooving by means of saw cut of pavement.
- Loading of material coming from grooving operations.
- Transportation of material coming from grooving operations to an authorized dump.
- Final cleaning.
- Delivery of As-Built drawings.
- Delivery of Spatial Data.
If repairs are required due to the damages occurring to the pavement as a result of the grooving operations, the scope of work includes also
- Patch repair.
- Loading of material coming from repair operations.
- Transportation of material coming from repair operations to an authorized dump.
- Quality Control by means of tests performed by a laboratory.
Note: The Contractor shall be paid for work interruptions due to aircraft traffic. The minimum payment for each interruption will be one hour. If the interruption is more than one hour, the payment for the interruption will be proportional to the unit cost per hour of interruption. Estimate a total 211 hours of work interruption.
2. PERFORMANCE PERIOD: The Period of Performance for this contract shall be of 45 calendar days and includes provisions for the submittal and approval of all the materials, the execution of work on the field and Final Inspection. The Contracting Office will notify the Contractor in advance when the execution of work at the field may commence. The total calendar days in advance shall be established during the Preconstruction meeting after agreement between Contracting Office and the Contractor.
The performance period proposed for the execution of this project, 45 calendar days, is for informational purposes only and includes average inclement weather days.
The contractor shall provide a Construction Schedule and Work Plan. The Work Plan shall show the sequence of operations planned for accomplishment of the work.
01000 - 2
3. DRAWINGS:
No. of Drawing Sheet Date Title
R-655-01 1 of 9 24 Jun 11 Cover Sheet, Drawing Schedule R-655-02 2 of 9 24 Jun 11 Access Route and Details R-655-03 3 of 9 24 Jun 11 Lights and Signs R-655-04 4 of 9 24 Jun 11 Temporary Markings R-655-05 5 of 9 24 Jun 11 Work Zone, Section & Detail R-655-06 6 of 9 24 Jun 11 Runway Permanent Markings I R-655-07 7 of 9 24 Jun 11 Runway Permanent Markings II R-655-08 8 of 9 24 Jun 11 Overrun Zone Permanent Markings R-655-09 9 of 9 24 Jun 11 Repair Type Details
4. GOVERNMENT-FURNISHED MATERIAL (GFM): Not used.
5. EQUIPMENT, CONTROLS, AND MATERIAL OF THE UNITED STATES OF
AMERICA: Not used.
6. CERTIFICATION OF CLASSIFICATION: Bidders and/or their subcontractors must hold an updated Certificate of Classification issued by the "Registro Oficial de Contratistas de Obras del Estado" of the "Ministerio de Economía y Hacienda" covering the following groups, subgroups, and categories.
Group Subgroup Category
O 2 d
The contractor shall have the following certificates:
- Certificate of Quality ISO 9001 for maintenance works and services of airport pavements.
- Certificate of Environment ISO 14001 for maintenance works and services of airport pavements.
7. SPECIAL REQUIREMENTS:
7.1 Vehicle Operations on the Aerodrome: The contractor shall receive the applicable traffic rules and regulations regarding driving on the aerodrome. The contractor shall abide by
01000 - 3 what is instructed in that regard.
7.2 Stockpiling Area of Demolished/Removed Material: The Contractor shall transport the material to an authorized dump. Should any of the Moron Air Base shops need all or part of any of the materials from the demolition operations the Construction Management shall notify Contracting Office and coordinate with the Base Chief of Operations and Maintenance the exact location to stockpile said material.
7.3 Stockpiling Area for Contractor Material and Contractor Offices: The Construction Management shall coordinate with the Base Chief of Operations and Maintenance the exact location for Contractor offices stockpiling.
7.4 Escorts: Escorts shall be provided for Base access by the Contractor for personnel, subcontractors or material suppliers during the construction period. Contractor shall provide their escorts with training, transportation, cell phones, permits, etc. Escorts shall be in possession of a valid driving license and if required, flight line driving permits.
7.4.1 Escort Responsibility:
7.4.1.1 General:
a. Maintaining visual and voice contact with escorted personnel and vehicle at all times.
b. Insuring visitor has base access pass attached to outer garment in a visible location, and that vehicle passes are visible from the dashboard.
c. Insuring that escorted personnel do not abandon the work site and that they remain with the escort when moving from one part of the base to another.
d. Insuring that the escorted persons and equipment leave the base and surrender the base access paperwork with the security guard at the gate.
e. Insuring that escorted personnel fully understand these requirements.
f. Insuring that the instructions from base personnel as well as the vouching authority are followed.
g. Maintaining visual and radio contact with control tower at all times.
The Government shall provide two radios at least to the contractor.
01000 - 4
The contractor shall return the radios after the completion of the work.
Construction Management shall establish the location where the contractor has to recharge the battery of the radios.
h. Insuring that Airfield Management Operations Office is informed every day when the contractor is going to access the work site and when the contractor has left the work site.
7.4.1.2 Work Performance on the Flightline:
Flightline Driving: A Certificate of Competency (AF 483) and a POV
Flightline pass (USAFE Form 449) must be obtained to perform as an escort on the Flightline. To obtain these items, the person must complete the following:
- Written Flightline test.
- Practical Flightline test.
- Both of the above require learning radio communications with the Control Tower. The contractor should anticipate a minimum of 2 weeks to complete this process.
- During FPCON Charlie or higher, the escorts must be on the Entry Authority list (EAL list) to be able to enter some areas of the base such as the Flightline.
*** END OF SECTION ***
01011 - 1
SECTION 01011
GENERAL CONDITIONS
1. GENERAL: The work consists of furnishing all labor, materials, plant, transportation, equipment, and services to complete the project described in Section 01000, Scope of Work, Drawings and Special Conditions, in accordance with the drawings and specifications, complete and ready for use by means of a firm fixed price construction contract.
Measurements given in the drawings and specifications are given for reference use only. It is the Contractor’s responsibility to verify any and all of said measurements.
2. GENERAL DESCRIPTION: The work consists in, but is not limited to, executing the line items indicated in the scope of work. All line items indicated in the scope of work do not limit or reduce the Contractor’s responsibility to perform all work as required by the project in order to provide a complete and operable facility.
3. LOCATION: The work is located in Morón Air Base, Spain, as shown on the contract drawings.
4. DRAWINGS ACCOMPANYING SPECIFICATION: The drawings accompanying this specification are a part thereof. Drawings are the property of the Government, and shall not be used for any purpose other than that contemplated by the specification. The drawings included in this specification are similar to A1.
5. WARRANTY: For this contract the Contractor shall provide a two year standard commercial warranty associated with all scope of work items including materials and workmanship.
The warranty should cover all defects noticed and reported to the Contractor within two years after acceptance of the project. The Contractor shall repair or replace defective materials at the Contractor's expense within a reasonable time, and as approved by the Contracting Officer
6. BASE ACCESS:
6.1 Permits or Authorizations: The Contractor shall obtain all permits or authorizations to access Morón Air Base. Once the works have finalized, the Contractor will return the permits or authorizations.
6.2 Delays and Interruptions: Contractors are advised that due to security reasons, during the access/egress process of personnel and materials from the Morón Air Base delays are liable to occur. Additionally, the Contractor shall immediately interrupt work when required to do so if security warning/alarm situations occur.
01011 - 2
7. WORK CLEARANCE REQUEST: The Contractor shall request AF Form 103 “BCE Work Clearance Request” in order to obtain all the information pertaining to the current status of general utilities. Requests shall be processed through the Contracting Officer or authorized representative, minimum of 7 duty days beforehand. The Contractor shall not perform any excavation works under any circumstances without an approved Work Clearance Request at the work site (hard copy). Work Clearance Request will only be processed once all materials and documentation necessary to commence work have been submitted and approved.
The Contractor shall be held responsible for any damage caused to general utilities indicated on the AF Form 103 and related drawings and shall be repaired at no additional cost to the Government of the United States.
8. BASE UTILITIES:
8.1 Use of Base Utilities: Base utilities are available to the Contactor at no additional expense to the Contractor. The following utilities shall be available from the existing Base utility connections in reasonable quantities:
a. Electricity 120/208 volts, 60 Hz.
b. Non-potable water.
Connection requests shall indicate the type of utility service required, type of connection and disconnection, utility service use and maximum duration. All connection and disconnection works for Base utilities shall be programmed during normal Base personnel operating hours. It shall be the Contractor’s responsibility to effect the connections and disconnections and shall reimburse costs incurred in the connection, disconnection, conversion, transportation of Base utility services to the work site, including providing the mechanisms that avoid water from flowing back into the system (backflow preventers) and furnishing and installing the necessary transformers. The Contractor shall not activate or alter any control device of the system of the utility services, including water, sewage and electricity. Control devices will be Government operated. The Contractor shall notify the Contracting Officer or authorized representative 5 duty days prior to any connection, disconnection or manipulation of the control system of the utility services required. Temporary overhead connections to utility services are prohibited. All systems shall be restored to their original condition prior to satisfying final contractual payments.
8.2 Base Utility Outages: Utility outage requests shall indicate the type of outage to be performed, the scope of work and the maximum duration. All utility outages shall be programmed during normal Base personnel operating hours. The Contractor shall not activate or alter any control device of the system of the utility services, including water, sewage and electricity. Control devices will be Government operated. The Contractor shall notify the Contracting Officer or authorized representative 5 duty days prior to any connection, disconnection or manipulation of the control system of the utility services required. Temporary
01011 - 3 overhead connections to utility services are prohibited. All systems shall be restored to their original condition prior to satisfying final contractual payments.
9. HOT WORK: The Contractor shall submit for approval a written request to the Contracting Officer or authorized representative 5 days prior to any welding, oxyacetylene or plasma cutting work. Said request shall indicate welding procedures and fire prevention measures. All welding work performed during the project shall be carried out by qualified welders only. The copies of the welding certificates, issued by an approved agency, shall be kept in the construction inspector’s files.
10. VEHICULAR TRAFFIC, MACHINERY AND EQUIPMENT:
10.1 Traffic Control: All works which require vehicular or pedestrian traffic disruptions on the Base shall require an approved transit control plan. Said plan shall be approved at least 7 days prior to carrying out said disruption. Said plan shall include the date, duration, proposed alternative routes, signs, barriers, cones and/or flagmen. The Contractor shall establish alternate procedures should unforeseen circumstances take place. The responsibility of furnishing, erecting, maintaining and removing all signs, barriers, cones and flags shall be solely the Contractor’s. Once the work is completed, the Contractor shall remove the signaling elements such as barriers, cones and/or flags.
10.2 Access Routes: The Contractor shall submit a plan for the access routes which shall be approved by the Contracting Officer or authorized representative.
10.3 Trucks: Trucks loaded with loose material (air borne dust, construction debris or other objects that could fall from them), shall be duly covered. Said covers, such as tarps, shall be fastened over the load prior to accessing the adjacent roads.
11. PROGRESS SCHEDULE: (See solicitation/Contract FAR clause 52.236-15, Schedules for Construction Contracts, Apr 1984). The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval four copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.
11.1 Airfield Working Hours: The Contractor shall perform all work during airfield working hours unless a special authorization is issued by the Contracting Office representative to
01011 - 4 deviate from said work schedule. Airfield working hours shall be from 08:00 to sunset, from Monday to Sunday. Normally, the Contractor will not be given access to the airfield from 08:00 through 15:00, Monday through Friday, due to aircraft traffic.
11.2 Working Outside the Airfield Working Hours: If the Contractor wishes to work outside the airfield working hours, he shall submit an application to the Contracting Officer. The Contractor shall submit the request 5 duty days ahead of time as minimum.
12. MOBILITY PLAN: The Contractor shall submit a mobility plan to the Contracting Officer or authorized representative for approval. Said plan shall propose the location and surface of the work site, offices and material staging and storage areas. The Contractor shall submit the plan 5 duty days prior to commencing work. The Contractor shall include in the mobility plan the proposed system to supply the required utility services required at each site.
12.1 Construction Site Fencing: Construction sites, offices, latrines, material staging and storage areas shall be fenced in by means of a two meter high fence to include gates and locks, unless otherwise approved the Government of the United States. The type of fencing, height and color shall be specified in accordance with the Contracting Officer or authorized representative’s criteria. Fences shall be screened with green opaque screening material to prevent visibility inside the fenced area. Fencing shall be completely secured at top and bottom to prevent access.
Fences and screens shall be adequately staked and/or anchored to prevent blowing over during high wind conditions. The Contractor shall include in the Mobilization Plan photos, catalogs or samples of the screening material. The Contractor shall not install the fencing or screening materials until approval, in writing, has been granted from the Contracting Officer or authorized representative. The responsibility of providing, erecting, maintaining and removing the fencing shall be solely the Contractor’s. The Contractor shall replace or repair, within the following 24 hours or as determined by the Contracting Officer or authorized representative, all fence or screening sections which have been damaged or deteriorated. Once the works have been finalized, the Contractor shall remove the fencing.
12.2 Offices: Temporary prefabricated buildings required for administrative reasons (office space, conference room and break room) shall be in good conditions. Temporary prefabricated buildings requiring paint, repairs or are in bad conditions shall not be allowed at the site. Said temporary prefabricated buildings shall include on the outside a plaque, 0.5 x 0.5 meters maximum dimensions, indicating the name of the company and telephone number (s) of the person (s) designated as POC for the Contractor 24 hours a day. Once the works are finalized, the Contractor shall remove the temporary prefabricated buildings.
12.3 Latrines: Prefabricated temporary buildings required as latrines for personnel shall be in good conditions. The prefabricated temporary buildings requiring paint, repairs or are in bad conditions shall not be allowed on the work site. These facilities shall be kept in perfect using conditions and sanitized, shall be treated for insects and shall be emptied once a week and
01011 - 5 cleaned with a detergent suitable for sanitary use. The frequency of emptying and cleaning shall be adjusted according to needs. The facilities shall be located no less than 50 meters from the existing buildings on Base if they cannot be located near a sewage manhole. Once the works have been completed, the Contractor shall remove the temporary facilities and shall leave the area clean and sanitized.
12.4 Parking: The Contractor, their employees and subcontractors shall park all vehicles, including heavy machinery, equipment or vehicles, in areas where they do not pose an obstruction in the corresponding work site. All possible efforts must be made so that the vehicles are not parked in an area where they will be clearly visible from the outside.
12.5 Material Storage: Storage containers will be in good conditions. The storage of materials at the work site shall be at the Contractor’s own risk. The use of private security guards at the work site shall require Spanish Air Force Security Forces approval. The Contractor shall not use the work site to store material previously approved by the Contracting Officer or authorized representative. Once the works have finished, the Contractor shall remove the excess stored material.
12.6 Not used.
13. QUALITY CONTROL PLAN: The Contractor shall submit comprehensive Quality Control Plan 5 duty days prior to commencing work. The plan shall contain at minimum the following:
1. Names and Qualifications for any proposed Quality Control Manager or
Inspectors.
2. Develop an Organization Chart that identifies the Reporting Responsibility the
Quality Control Inspectors, Quality Control Manager and the Project Manager.
3. Inspection Procedures. This should include types and frequencies of inspections and procedures for failed or unsatisfactory inspections.
4. Inspection Reporting. Submit recommended forms for all types of planned inspections with the Quality Control Plan for approval.
5 Identify all necessary inspections and submit a schedule with the frequency of inspections.
6 Copies of all performed inspection reporting forms, including Specific (HVAC, Plumbing, framing, Electrical, HVAC etc.,) are to be submitted to the Contracting Officer within 24 hrs. after performing each inspection.
7. List of planned ‘Hold Inspection Points’ with the estimated dates from the construction schedule.
8. Request for Information (RFI) Submit the proposed RFI Form and RFI Log Form to be used. This will be used to submit and track any RFI’s during construction.
01011 - 6
9. Material Testing: Submit the name and qualifications for any Testing Agency or Laboratory planned for testing. All testing reports shall be submitted in a timely manner for review and approval. Should any test report fail, follow-on work is not to proceed until after the failure has been corrected. It is the responsibility of the QC Manager to ensure that all reports have been reviewed and the necessary action taken to resolve any failed testing.
10 A daily report of all actions performed during the contract period is required to be documented on a daily basis
a. The following should be included in the report, but is not all-inclusive.
1) The date of the inspection.
2) Comment on the weather conditions.
3) Inspection of equipment and materials and when received at the job-site.
4) Names of visitors to the site during the day.
5) Inspection of any deficiencies discovered during the day and corrective action taken.
6) Inspection and acceptance of subcontractor materials and workmanship.
7) Work being performed during the day and notation of inspection and acceptance.
8) Any field changes made by Civil Engineer inspector or deviations from original plans or specifications.
These daily reports are to be kept on the job-site and available for review at all times.
13.1 Acceptance of the Construction Quality Control (QC) Plan: Acceptance of the QC Plan is required prior to the start of construction. The Contracting Officer reserves the right to require changes in the QC Plan and operations as necessary, including removal of personnel, to ensure the specified quality of work.
13.2 The contractor is expected to know and adhere to the contract specifications and drawings. The Government inspector will conduct regular inspections to confirm compliance with the drawings & specifications.
13.3 Tests to be performed by the contractor are to be in accordance with the specifications and will be evaluated by the government inspector.
13.4 Maintenance of records required by the contract and specifications are the responsibility of the contractor.
01011 - 7
13.5 Final inspection and acceptance will be conducted jointly with the inspector and a representative from the contracting office. All punch list items must be completed before final acceptance of the project.
14. WORK DAY:
14.1 Normal Work Hours: The Contractor shall perform all work during normal working hours unless a special authorization is issued by the Contracting Office representative to deviate from said work schedule. Normal working hours shall be from 0800 to 1700, from Monday to Friday, with the exception of holidays.
14.2 Work Outside Normal Hours: If the Contractor wishes to work outside the normal hours of operation, Saturdays, Sundays, or holidays, he shall submit an application to the Contracting Officer. The Contractor shall submit the request 5 duty days ahead of time as minimum.
15. CONSERVATION AND MAINTENANCE:
15.1 Conservation and Maintenance of the Existing Facilities: The contractor shall conserve and protect all existing facilities at the work site or adjacent to it which shall not to be removed or affected by the work required under this contract. The Contractor shall restore, at no additional cost to the Government of the United States of America, the facility affected during the execution of works to its original condition, before final acceptance of the project.
15.2 Conservation and Maintenance of the Existing Vegetation: The Contractor shall conserve and protect the existing vegetation (trees, shrubs, grass) on or adjacent to the work site, which shall not to be removed and which do not interfere with the work required under this contract. The contractor shall only remove trees or shrubs when specifically indicated in the drawings and specifications and shall avoid damaging the rest of vegetation. If any limbs or branches of trees are broken during contract performance due to the careless operation of equipment or the carelessness of the workmen, the contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound. The contractor shall cut the grass or vegetation in the work site so that it does not exceed 10 cm in height. The Contractor shall restore, at no additional cost to the Government of the United States of America to their original state all areas disturbed during construction to their original condition before final acceptance of works under this project.
16. CLEANING AND MAINTENANCE:
16.1 Housekeeping and Site Cleanup: The Contractor shall dispose of accumulated debris, waste materials and rubbish and shall keep the site in order. All rubbish and waste
01011 - 8 materials shall be removed daily and shall be placed in contractor furnished containers and shall be removed on a daily basis to an authorized dump off-Base as the project progresses.
Contractors shall ensure all light weight debris at the construction site is properly secured in waste receptacles so that it does not blow to another area or onto the airfield. Once the works are finished, the Contractor shall remove the containers.
16.2 Cleaning and Maintenance of Access Routes: The Contractor shall be solely responsible for any material dumped/spilled by trucks, vehicles and machinery or equipment on the access routes. Said material shall be immediately removed by the Contractor. The Contractor shall be responsible for assuring that all access routes shall be kept clean and clear at all times.
No amount of debris whatsoever will be tolerated on the access routes
16.3 Waste and Construction Debris: The Contractor, once the project has been completed, shall submit a report to the Chief of Construction Management with the estimated amounts or waste and construction debris managed during the execution of the project.
17. HAZARDOUS MATERIAL: Before transporting any type of hazardous material, the Contractor shall contact the Chief of Construction Management to coordinate handling and storage. The Contractor shall be responsible for complying with all applicable environmental rules and regulations concerning handling, transportation and storage of materials and/or dangerous waste.
18. NOISE CONTROL: The Contractor shall comply with all applicable municipal and state regulations and all bylaws and norms pertaining to noise control, applicable on or off Base.
19. SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION: (See Solicitation/Contract FAR clause 52.236-21, Specifications and Drawings for Construction, Feb 1997).
19.1 Maintenance and Updating of As-Built Drawings and Specifications: The Contractor shall keep two sets of specifications and prints, regular size, on the site which shall show neatly and clearly marked in red all approved & not approved variations between the actual construction and the contract documents. The As-Built drawings shall be kept up-to-date at the work site at all times during the contract.
19.2 Availability and Review of As-Built Drawings: As-Builts shall be available for inspection by the Contracting Officer or his authorized representative. Upon completion of work, a complete set of As-Built drawings shall be submitted to the Contracting Officer for final review. A hard copy of the As-Built drawings will be submitted marked in red and signed by project inspection. The Contracting Officer shall provide comments and/or approval within the following two weeks from the submittal.
01011 - 9
19.3 Submittal of As-Builts: After final review and once the As-Built drawings have been approved, the Contractor shall have two weeks to submit a complete set of As-Builts and a CD with Updated AutoCAD files, Version 2010, of said drawings. The name of the drawing files on the CD shall correspond to the drawing numbers of the hard copies. The CD shall be labeled as follows:
- Project Name and Number.
- Date.
- Contract Number.
- Contractor Name.
20. CONTRACTOR GENERAL GUIDELINES FOR AS-BUILT SPATIAL DATA
COLLECTION & SUBMITTAL:
20.1 The contractor is responsible for accurately collecting all spatial data* features as-built and as-installed. The required positional accuracy is +/- 2 cm.
20.2 The contractor is responsible for delivering the spatial data in a scalable vector format such as DXF, AutoCAD DWG, ESRI shapefile or ESRI Geodatabase.
20.3 The contractor shall identify the classification, type, size, location, ID number, and any other necessary attributes, as specified by the Government, for all features.
20.4 The contractor is responsible for delivering the spatial data in a logical layering system according to the current version of Spatial Data Standard for Facilities Infrastructure and Environment (SDSFIE). The layers and associated definitions are listed in Appendix A.
SDSFIE Feature Summary Listing.
20.5 The contractor is responsible for delivering the spatial data in the Universal Transverse Mercator (UTM) coordinate system Zone 30 North, World Geodetic System 1984 (WGS84) datum.
20.6 The contractor will coordinate with the installation GeoBase Office to determine the current version being used for all software, data and data standards. The Government will provide the contractor with data and information concerning all necessary and pertinent functions and principal features of the identified project including the installation's latest digital planimetric data.
20.7 Deliverables include, but are not limited to:
• Site plans.
• Topographic surveys or studies.
01011 - 10
• Boundary or Cadastral surveys.
• Utility (water, sewer, power, storm, etc.) designs, plans, surveys and studies.
• Pavement, Grading, or Excavation plans.
• Soil/Geology studies or surveys.
• Environmental assessments, surveys, studies, or plans.
• Historical or Archaeological surveys, studies, or plans.
All data deliverables shall include a schedule and shall be in a digital (electronic information) format and shall be delivered on CD-ROM or DVD-ROM. The media must have an external label listing the contractor's contact information, a short description of the contents, and a sequence number if there are multiple volumes.
20.7.1 A transmittal sheet in both hardcopy and digital format (a *.dbf, *.xls, or ASCII comma-delimited format) must accompany the media containing the information included on the external labels, total number of volumes being delivered, and a list of file names and file descriptions on each volume. The transmittal sheet must also include instructions for reading, restoring, or transferring the files from the media, and certification that all delivery media is free of known computer viruses - including the name(s) of the virus scanning software and the date the virus scan was performed.
20.7.2 The following procedures must be performed before CADD data is placed on the delivery media:
1. Include all files, both graphic and non-graphic, required for the project.
Ensure all files are in the same directory, and that references to those files do not include device or directory specifications.
2. Ensure all reference (external reference) files are attached and without device or directory (path) specifications.
3. Remove all extraneous graphics and text outside the project border area, and set the active parameters to a standard setting (or the setting contained in the seed or prototype file).
4. Include any standards sheets (abbreviations, symbols libraries, font libraries, color tables, pen tables, plot configuration files, user command files, etc.) necessary for a complete project.
20.7.3 The following procedures must be performed before GIS data is placed on the delivery media:
01011 - 11
1. Shapefile data shall include, as a minimum, the following files: the *.shp, the *.shx, the *.dbf, the *.prj and the *.xml or other metadata file.
2. Geodatabase data shall be returned in a Personal Geodatabase format compatible with the version of ArcGIS presently used by the GeoBase Office. All concomitant tables, domains, metadata, etc. shall be included in the Geodatabase.
3. Any ArcGIS Map Documents (i.e. *.mxd files) delivered shall be accompanied by all referenced data files, both spatial and tabular; and any associated images or other objects in the layout.
*Spatial data, also known as geospatial data or geographic information, means any data with a direct or indirect reference to a specific location or geographical area.
21 SITE INVESTIGATION AND CONDITIONS AFFECTING WORK: The Contractor acknowledges that it has taken steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to… see Solicitation/Contract FAR clause 52.236-3, Site Investigation and Conditions Affecting the Work, Apr 1984.
22. PERMITS AND RESPONSIBILITIES: The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occurs as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the entire work, except for any completed unit of work which may have been accepted under the contract. (See Solicitation/Contract FAR clause 52.236-7, Permits and responsibilities, Nov 1991)
23. CONTRACTOR AND SUBCONTRACTOR PERSONNEL:
23.1 Superintendent: The Contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor. The superintendent must be able to effectively answer technical questions related to the project and effectively manage the work.
23.2 English Speaking Representative:
23.2.1 At all times during the execution of any work, the Contractor shall have a representative present on site capable of explaining the work operations and receiving
01011 - 12 instructions in English. The Contracting Officer or authorized representative shall have the right to determine, without appeal of such decision, whether the proposed representative has the linguistic capability or not, in which case, said representative shall be replaced immediately by another previously approved by the Contracting Officer or his authorized representative.
23.3 Personnel Listing: The Contractor shall submit a list of key personnel and subcontractor personnel to include position, personal addresses and phone number for emergency contact purposes. As changes occur and additional information becomes available, the Contractor shall correct the information contained in the previously submitted lists.
23.4 Personnel Transit On-Base: Personnel working on the Base shall keep to the work site and shall transit using the approved access routes. The personnel shall keep off restricted areas unless the pertinent authorization is issued.
24. PUBLIC RELEASE OF INFORMATION: The public release of information o photographs concerning any aspect of the materials or services related to this bid, purchase order or other documents resulting thereof without prior written approval from the Contracting Officer.
25. SAFETY PROGRAM:
25.1 Safety Plan: Prior to commencement of work, the Contractor shall submit a Safety Plan to the Contracting Officer in writing. The safety plan shall be subject to approval by the Contracting Officer or his authorized representative. The work site Safety Plan shall identify safety and health risks of the workers and shall propose the necessary preventive measures for each unavoidable risk in order to protect the physical integrity of the workers and minimize material damage to the facility. Fire prevention measures shall be indicated for those works which involve a fire risk. The Contractor shall provide fire extinguishers for hazardous works in which fire or a fire risk is involved. Avoidable risks shall be eliminated. Preventive measures shall be preferably collective in nature. Those risks for which, technically, collective preventive measures do not apply shall allow the use of Personal Protection Equipment. The Contractor shall list the contents of the First Aid Kit in the Safety Plan.
25.2 Standard Regulations: The contractor shall execute the Safety Plan in accordance with the corresponding State, Autonomous Community, Province and Municipal legislation. The program shall include, but not be limited to, the following:
- “Occupational Safety and Health as of 1970, Public Law 91-596, 91 Congress, S.2193, 29 December 1970.
- "Public Law Amendment 91-596, 101-552, 3101, 5 November 1990.
- “Ley 31/95, 8 November, Risk Prevention”.
01011 - 13
Royal Decree 1316/1989, 27 October, relative to protection for workers exposed to noise risks during the execution of work.
Royal Decree 363/1995, 10 March, Regulation for notification of new substances and classification, container and labeling of hazardous substances.
Royal Decree 485/97 14 April, on work site warning signs.
Royal Decree 486/97, 14 April, work sites.
Royal Decree 487/97, 14 April, handling heavy loads.
Royal Decree 488/97, 14 April, screens.
Royal Decree 664/97, 12 May, biological agents.
Royal Decree 665/97, 12 May, cancerous agents.
Royal Decree 773/97, 30 May, Individual Protective Equipment.
Royal Decree 1215/97, 18 July, work equipment.
Royal Decree 1627/97, 24 October, Occupational Safety and Health regulations regarding construction works.
Royal Decree 1942/1997, 5 November, Regulation on the installation of protection against fires.
Royal Decree 396/2006, 31 March, regulation relative to working with Risk of
Asbestos.
25.3 Base Regulations: The Contractor, his employees and subcontractors shall become familiar with and comply with all Base rules and regulations including fire, traffic and security regulations.
25.4 Excavations and Hazardous Areas: Excavations and all areas considered hazardous by the Government of the United States of America shall be protected by suitable barriers, lights and beacons (flags, cones, boards). Warning lights (portable lamps IP-44 minimum) or safety signal lights shall be installed by the Contractor. The Contractor shall pay for any damage resulting from his own negligence. The responsibility of supplying, erecting, maintaining and removing all barriers, lights, beacons, warning lights and safety lights shall be solely the
01011 - 14
Contractor’s. Once the works have finalized, the Contractor shall remove all signaling elements such as barriers, lights and beacons.
25.5 Burning and Explosives: Burning practices and use of explosives without prior written authorization from the Government of the Unites States of America is prohibited.
26. ASBESTOS: The use of asbestos containing materials is prohibited.
27. CELL PHONE AND RADIO TRANSMITTER RESTRICTIONS: Under no circumstances shall radio transmitters or cell phones be used without prior approval from the Government of the United States of America.
28. WEATHER PROTECTION: The Contractor shall take the necessary precautions to protect the work site, facilities, equipment and materials from weather, to include those furnished by the Government or Government Property. It shall be the Contractor’s responsibility to be aware of weather forecasts and to take the necessary protective measures. Prior to commencing any work, the Contractor shall have at the site the material (tarpaulins, etc.) or necessary equipment to protect the site, facilities, equipment and materials exposed to rain, wind, or other natural events. Required tarpaulins shall not be light plastic, the thickness shall be enough as to assure that the weight of accumulated water does not exceed the resistance of the tarpaulin, thus tearing it. The Contractor shall be responsible for damage caused due to lack of protection against the weather.
29. MATERIAL AND/OR EQUIPMENT SUBMITTALS:
29.1 Submittals Required: The Contractor shall submit the documentation or samples indicated in the Form “Schedule of Material Submittals” for each material or equipment.
29.2 Submittal Procedure: The Contractor shall attach AF Form 3000 “Material Approval Submittal” to the documentation or sample of material or equipment submitted. The Contractor shall fill in all the necessary fields of AF Form 3000. The Contractor shall turn in AF Form 3000 and the documentation or sample of the material or equipment to the Contracting Officer within the time frame indicated in the document “Schedule of Material Submittals” for approval prior to commencement of any type of work. The Contracting Officer shall return the AF Form 3000 indicating if said submittal has been approved or not. If the Contracting Officer has not approved the submittal, the Contractor shall provide a new submittal.
29.3 AF Form 3000: The Contractor shall create said form.
30. MATERIALS AND/OR EQUIPMENT:
30.1 Material and/or Equipment Purchase Order: Once the Contractor has received
01011 - 15 approval from the Contracting Officer for the submittal, the Contractor shall proceed with the purchase order for the approved equipment or material.
30.2 Delay in the Delivery of Materials and/or Equipment: Delays in the delivery of materials and/or equipment shall not justify an extension in the performance period of the contract.
31. COMMENCEMENT OF WORK: Once all the required materials and/or equipment are available for use, the Contractor shall proceed to commence the works. If the Contractor wishes to commence works without all materials and/or equipment on site, he shall request authorization from the Contracting Officer.
02960 - 1
SECTION 02960
GROOVING FOR AIRFIELD PAVEMENTS
PART 1 - GENERAL
1.1 GROOVING OF AN ACTIVE RUNWAY:
1.1.1 Emergency Landings and Takeoff: Emergencies shall take precedence over all Contractor operations. Upon notification from the Control Tower of emergency landing or imminent takeoff, all operations shall be stopped immediately and all personnel and equipment evacuated to an area not utilized for aircraft traffic which is at least 60 m measured perpendicular to and away from the near edge of the runway. Equipment shall be able to clear the work area within 15 minutes.
1.1.1.1 Work Interruptions due to Aircraft Traffic: The Contractor shall be paid for work interruptions due to aircraft traffic. The minimum payment for each interruption will be one hour. If the interruption is more than one hour, the payment for the interruption will be proportional to the unit cost per hour of interruption.
1.2 REFERENCES: The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
UNIFIED FACILITIES CRITERIA (UFC)
UFC 3-260-02 (30 Jun 2001), Pavement Design for Airfields.
UNIFIED FACILITIES GUIDE SPECIFICATIONS (UFGS)
UFGS 32 01 26.71 (Aug 2008), Grooving for Airfield Pavements.
1.3 SYSTEM DESCRIPTION:
1.3.1 Grooving Machine: Provide a grooving machine that is power driven, self-propelled, specifically designed and manufactured for pavement grooving, and has a self contained and integrated continuous slurry vacuum system as the primary method for removing waste slurry.
The grooving machine shall be equipped with diamond-saw cutting blades, and capable of making at least 457 mm in width of multiple parallel grooves in one pass of the machine.
Thickness of the cutting blades shall be capable of making the required width and depth of grooves in one pass of the machine. The cutting head shall not contain a mixture of new and
02960 - 2 worn blades or blades of unequal wear or diameter. Match the blade type and configuration with the hardness of the existing airfield pavement. The wheels on the grooving machine shall be of a design that will not scar or spall the pavement. Provide the machine with devices to control depth of groove and alignment within the specified tolerances.
1.3.2 Water Supply: If transportation of the water by surface laid pipe is permitted, routing of the pipe shall be shown on a drawing to be submitted for Contracting Officer's approval by the Contractor. The available water source location is identified on the drawings.
Water for the grooving operation shall be provided by the Contractor.
1.4 SUBMITTALS: Royal Decree 1630/1992 (modified by Royal Decree 1328/1995), which dictates the dispositions for free circulation of constructional purpose products, shall be complied with in application of Directive 89/106/CEE. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted:
Submittal Description Product Data
Equipment [G]
List of proposed equipment to be used in performance of construction work, including descriptive data and safety precautions required for the equipment operation.
Procedures [G]
Grooving sequence and method of placing guide lines to control grooving operation.
1.5 ENVIRONMENTAL REQUIREMENTS: Grooving operations will not be permitted when freezing conditions prevent the immediate removal of debris and/or drainage of water from the grooved area. Discharge and disposal of waste slurry shall be the Contractor's responsibility. Waste slurry discharge pits may be constructed along side the pavement to be grooved, as directed by the Contracting Officer. Provide and maintain temporary storm drainage, pollution control, and erosion control features at each discharge pit in accordance with base environmental regulations. After the waste slurry has been dewatered, the hardened slurry shall be excavated and disposed off base in accordance with the base waste disposal requirements. All discharge pit areas shall be regraded and restored to original condition.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
02960 - 3
3.1 PREPARATION:
3.1.1 Existing Pavements: Bumps, depressed areas, bad or faulted joints, and badly cracked and/or spalled areas in the pavement shall not be grooved until such areas are adequately repaired or replaced. If the existing pavement is not suitable because of its strength, the grooving shall not be executed.
3.1.2 New Pavements: Permit new Portland cement concrete pavements to cure for a minimum of 28 days before grooving.
3.2 GROOVING:
3.2.1 Procedures: Grooving should be terminated within 1.5 of the pavement edge to allow adequate space for operation of the grooving equipment. Cut grooves in the Portland cement areas as indicated on the drawings. Begin the grooving at one side of the usable runway and continue for the full width of the area. Take all reasonable precautions to prevent damage to or roughening of the pavement between grooves. Spalling along or tearing or raveling of the groove edges shall not be allowed. The grooves shall be 6 mm, plus 2 mm, minus 0 mm wide by 6 mm, plus or minus 2 mm deep and 38 mm, plus 0 mm, minus 3 mm center to center spacing.
The groove length shall be from one edge of the runway to the other edge of the runway plus or minus 75 mm long and normal to the longitudinal axis of the centerline of the runway. The transverse alignment of the grooves shall not vary more than 75 mm plus or minus on a 23 m length of grooving. Do not groove within 150 mm plus or minus 75 mm of the runway centerline. Do not groove within 150 mm of transverse joints or working cracks, through compression seals, in-runway lighting fixtures or similar items.
3.2.2 Clean-Up: Clean-up shall be continuous. Flush debris produced by the equipment to the edge of the grooved area or pick it up before it dries and hardens. The dust coating remaining shall be flushed to the edge of the area if the resultant accumulation is not detrimental to the vegetation or storm drainage system. Accomplish all flushing operations in a manner to prevent erosion on the shoulders, damage to vegetation, or plugging of storm drainage.
3.2.3 Repair of Damaged Pavement: Repair at the Contractor's expense, as specified in Section 02961, any damage, which in the opinion of the Contracting Officer will be detrimental to aircraft operations and/or pavement performance, occurring to the pavement as a result of the grooving operations.
3.3 CONTRACTOR QUALITY CONTROL:
3.3.1 Test Section: Groove a test section in an area of the pavement outside of the trafficked area, as approved by the Contracting Officer. The area shall be 60.96 m long by two
02960 - 4 lanes wide. Demonstrate the setup and alignment process, the grooving operation, and the waste slurry disposal.
3.3.2 Inspections: At the beginning of each work shift, furnish a full complement of grooving blades with each saw that are capable of cutting grooves of the specified width, depth, and spacing. If during the work, a single grooving blade on a machine becomes incapable of cutting a groove, continue work for the remainder of the work shift.