Request_for_Information__FA5270-14-R-0023.pdf

PDF 65 KB Posted

Attached to
Replace Boiler Room Doors and Door Frames Federal contract opportunity
Solicitation number
FA5270-14-R-0023
Issued by
Department of the Air Force Pacific Air Forces

About this file

Reference to Offerors

View the file

Other files for this federal contract opportunity

Other files attached to Replace Boiler Room Doors and Door Frames, newest first.
File Type Posted
Amendment_0001_to_FA5270-14-R-0023 _SF30.pdf PDF
SF1442_-_FA5270-14-R-0023-0002.pdf PDF
Amendment_0002_to_FA5270-14-R-0023-0002 _SF30.pdf PDF
Amendment_FA5270-14-R-0023.doc DOC document
Boiler_Room_1409_Drawings_.pdf PDF
Boiler_Room.pdf PDF
Format_For_Submission_Experience_(3).pdf PDF
NYJS_144212_BOILER_PLANT_DOORS_Statement_of_Work.docx DOCX document
Boiler_Room_1073_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

PACIFIC AIR FORCES

24 Apr 2014

MEMORANDUM FOR INTERESTED PARTIES

FROM: 18th CONS/LGCC Unit 5199

APO AP 96368-5199

SUBJECT: Request for Information (RFI) for Replace Boiler Plant Doors and Frames, Bldg. 873, 857, 1073 and 1409 on Camp Kinser /Solicitation Number: FA5270-14-R-0023

Project Numbers: LXEZ 13-1048 Title: Repair Building 870, Kadena AB, Okinawa, Japan

1. We have received questions from a contractor and responses are as follows for your information:

Question

No.

Reference

Question Government Response

1 Statement of Work (SOW), section 4.1. .

Some of signs on the doors are missing. Would the government provide the accurate QTY which is missing?

Does the government provide the signs? or, does contractor have to provide the signs?

If contractor does, would the government provide the specification for the signs?

The resultant contractor will remove and re-install existing signage on doors.

Refer to Revised statement of work dated 21 Apr 14, section 4.1.1 and 2.

2 SF 1442 It is required to provide abatement and dispose cost for asbestos and LBP;

however, without the result of the sampling, we can't estimate.

In other words, we can't provide the accurate information.

Would the government provide the QTY for abatement and disposal for two items, asbestos and LBP?

Quantity of each abatement and disposal of asbestos and lead base paint is established at line item 0002 and 0003.

Refer to Amendment 0002 to FA5270-

14-R-0023, SF30.

2. Point of contact is Kei Yamanoha at 098-961-1933 or by email at kei.yamanoha@us.af.mil

GUS SPENCER, TSgt Contracting Officer

Reference:
Question:
Government Response:
1:
Statement of Work SOW section 41:
The resultant contractor will remove and reinstall existing signage on doors Refer to Revised statement of work dated 21 Apr 14 section 411 and 2:
2:
SF 1442:
Quantity of each abatement and disposal of asbestos and lead base paint is established at line item 0002 and 0003 Refer to Amendment 0002 to FA5270 14R0023 SF30: