Questions and Answers for FA5000-11-R-0025
1. In regard to price proposal preparation, does the contractor need to transfer pricing information from the Price Exhibit to the related Contract Line Item Number (CLIN) 0001, 1001, 2001, 3001 and 4001 for Storage, Security, Processing of Cars and if so what portion of the pricing is used to calculate the specific price on line item? Can the CLIN be marked “See Price Exhibit” in the Net Amt field of proposal?
No transfer of pricing information is required from the Price Exhibit to the CLIN Net Amt fields for CLINs 0001, 1001, 2001, 3001 and 4001. Please complete the Price Exhibit fully and return as part of proposal submission. Annotate the Net Amt field as “See Price Exhibit” on CLINs 0001, 1001, 2001, 3001 and 4001.
2. In regard to price proposal preparation, does the contractor need to transfer pricing information from the Price Exhibit to the related Contract Line Item Number (CLIN) 0002, 1002, 2002, 3002 and 4002 for Peak In-Processing and if so what portion of the pricing is used to calculate the specific price on line item? Can the CLIN be marked “See Price Exhibit” in the Net Amt field of proposal?
No transfer of pricing information is required from the Price Exhibit to the CLIN Net Amt fields for CLINs 0002, 1002, 2002, 3002 and 4002. Please complete the Price Exhibit fully and return as part of proposal submission. Annotate the Net Amt field as “See Price Exhibit” on CLINs 0002, 1002, 2002, 3002 and 4002.
3. In regard to price proposal preparation, does the contractor need to transfer pricing information from the Price Exhibit to the related Contract Line Item Number (CLIN) 0003, 1003, 2003, 3003 and 4003 for Peak Out-Processing and if so what portion of the pricing is used to calculate the specific price on line item? Can the CLIN be marked “See Price Exhibit” in the Net Amt field of proposal?
No transfer of pricing information is required from the Price Exhibit to the CLIN Net Amt fields for CLINs 0003, 1003, 2003, 3003 and 4003. Please complete the Price Exhibit fully and return as part of proposal submission. Annotate the Net Amt field as “See Price Exhibit” on CLINs 0003, 1003, 2003, 3003 and 4003.
4. As a further clarification to price proposal submission please note the following:
CLINs 0004, 1004, 2004, 3004, and 4004 for Temporary Fence Material and Install – please complete the Price Exhibit fully and then complete unit price (quantity is 12 and unit of issue is Months) and extended net amount price directly on the CLIN structure.
CLIN 0005 for Permanent Fence Material and Install, please complete the Price Exhibit fully and then complete unit price (quantity is 1 and unit of issue is Lump Sum) and extended net amount price directly on the CLIN structure.
Other files
| File | Type | Posted |
|---|---|---|
| Answers and Questions | — | |
| FA5000-11-F-0025-0001.doc | DOC document | |
| POV PWS-Updated 25 July 2011.docx | DOCX document | |
| Answers to questions.docx | DOCX document | |
| POV PWS.docx | DOCX document | |
| Price Exhibit.xlsx | XLSX spreadsheet | |
| PP Questionare FY 12 POV Storage Contract - JBER.doc | DOC document | |
| Solicitation FA5000-11-R-0025.doc | DOC document | |
| WD 05-2017 REV 15 06-13-11.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .