Attachment 1 SABER SOW.docx
DOCX document 88 KB Posted
- Attached to
- SABER - Mountain Home AFB Federal contract opportunity
- Solicitation number
- FA4897-10-R-0005
About this file
Attachment 1 SABER SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 2.rtf | RTF text file | |
| SABER Questions and Answers.pdf | ||
| Pre-Bid Conference_Site Visit Minutes 072110.pdf | ||
| Attachment 6 Present and Past Performance Questionnaire.rtf | RTF text file | |
| Amendment 1.rtf | RTF text file | |
| Solicitation FA4897-10-R-0005.rtf | RTF text file | |
| Attachment 5 Wage Determination - Highway.docx | DOCX document | |
| Attachment 9 SABER Sample Project SOW.pdf | ||
| Attachment 3 Wage Determination - Residential.docx | DOCX document | |
| Attachment 4 Wage Determination - Heavy.docx | DOCX document | |
| Attachment 2 Wage Determination - Building.docx | DOCX document | |
| Attachment 8 Determination of Responsibility.docx | DOCX document | |
| Attachment 6 Present Past Questionnaire.docx | DOCX document | |
| Attachment 7 Certificate of Compliance.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
SIMPLIFIED ACQUISITION OF BASE ENGINEER REQUIREMENTS
(SABER)
MOUNTAIN HOME AFB, IDAHO
20 May 2010 Revision 9
Section 1 Summary of Work
| 1.1 Purpose |
| 1.2 Scope of Services |
| 1.3 Key Management Staff |
| 1.4 Technical Support Staff |
| 1.5 Contractor Use of Premises |
| 1.6 Government Furnished Services |
| 1.7 Phase In/Out |
Section 2 Coordination
| 2.1 Project Coordination |
| 2.2 Coordinating with Government Activities |
| 2.3 Utilities Coordination |
| 2.4 Existing Facilities/Job Site Verification |
| 2.5 Construction Schedules/Progress Reports |
| 2.6 Hours of Work |
Section 3 Special Procedures
| 3.1 Work On or Near Airfield |
| 3.2 Work in Munitions Storage Area |
Section 4 Delivery Order Proposal and Design Submittal
| 4.1 Ordering Procedures |
| 4.2 Delivery Order Proposal and Design Submittal |
Section 5 Temporary Construction Facilities and Controls
| 5.1 Safety |
| 5.2 Fire Prevention |
| 5.3 Severe Weather |
| 5.4 Barriers and Enclosures |
| 5.5 Security |
| 5.6 Temporary Controls |
Section 6 Equipment and Material
| 6.1 Equipment |
| 6.2 Material |
| 6.3 Salvage Material and Equipment |
Section 7 Delivery Order Closeout
| 7.1 Inspection Request |
| 7.2 Final Inspection |
| 7.3 Project Closeout |
Appendix 1 General Security Requirements
Appendix 2 Geospatial Information System Deliverables
Appendix 3 Environmental
SECTION 1
SUMMARY OF WORK
1.1 PURPOSE: The purpose of this Indefinite-Delivery, Indefinite-Quantity (IDIQ) contract is to provide construction services for civil and military projects in support of the United States Air Force at Mountain Home AFB, ID.
1.2 SCOPE OF SERVICES: The government will award construction projects by individual delivery orders on an as-needed basis. The contractor will furnish all personnel, equipment, tools, materials, supervision, and other items and services necessary to design, manage, and accomplish a broad range of maintenance, repair, alteration, and/or new construction work on various real property facilities. During the contract period, the Base Civil Engineer (BCE) will identify construction tasks and the Contracting Officer (CO) will issue delivery orders to the contractor to complete the work. The contractor will maintain an office on Mountain Home Air Force Base (MHAFB) in order to receive work requests and other related requirements to accomplish each delivery order. The work will include tasks in various trades, such as carpentry, pavement repair, roofing, asbestos abatement/removal, demolition, concrete masonry, welding, etc. Construction projects under this contract will generally range from $2,000 to $750,000. The work will be performed at Mountain Home Air Force Base, off-base Small Arms Range, Grasmere, Saylor Creek, Juniper Butte, associated Emitter Sites, Rattle Snake Radar Site, and other off-base facilities.
1.3 KEY MANAGEMENT STAFF
1.3.1 The contractor shall employ a sufficient number of qualified personnel to adequately oversee all work under this contract. When work is being performed, the assigned superintendent or an appointed alternate shall be available at any work site within 15 minutes of notification. All key management staff must be fluent in English.
1.3.2 A Project manager (PM) will be assigned to the site, dedicated to this contract, and have decision-making, obligation, negotiation, and signature authority pursuant to this contract. The Project manager must carry a cellular phone with a local number for immediate response to contract requirements. The PM will notify the Contracting Officer (CO) and CE SABER Project Inspector of any projected absence over 2 days and designate a qualified replacement.
1.3.3 Superintendent: The contractor will designate in writing, prior to execution of any delivery order, a superintendent responsible for the proper coordination and timeliness of the work and for the proper workmanship of all trades. The ability of the superintendent, based on his/her knowledge and experience, is essential to the proper execution of the work, as is his/her ability to communicate and direct the efforts of those performing the work.
1.3.4 Quality control and safety management: The Contractor shall provide a Quality Control Manager (QCM) to provide quality control and safety management. The QCM shall perform a minimum of twice daily site visits to each active project site to ensure full compliance with all safety requirements, verification that the work and materials in place and stored on site are in accordance with the approved construction drawings, shop drawings, and material submittals. The QCM shall prepare daily field notes recording activities at each project site, prepare and coordinate material submittal sheets and shop drawing submittals, prepare quality control reports, attend all pre-final and final inspections, and schedule and coordinate testing procedures. Quality Control and Safety Management must be carried out by someone other than the Project manager or Site Superintendent.
1.4 TECHNICAL SUPPORT STAFF
1.4.1 The contractor shall provide adequate technical staff for the following functions: project planning/design, estimating, drafting/GIS and clerical. Skill level, experience, qualifications, and background for the personnel in these positions shall be as required to provide the government a complete, accurate, and quality project.
1.4.2 Professional Engineering Requirement: The contractor will, when required, retain an individual holding a professional engineer's license, and conform to the Architectural and Professional Engineering Registration and Certification laws of the State of Idaho. This individual(s) will have direct oversight of project design and planning activities and must be promptly available to provide engineering support and professional engineering certification when necessary. The requirement for a professional engineer will not be construed to imply that normal designs require professional engineering certification. However, the possibility exists that unforeseen events or unexpected site conditions require modifications to the completed design that will require proof of licensing (i.e., an Engineer's stamp) for modification. The government anticipates less than five percent (5%) of the designs will require this type of modification. However, when such conditions do occur, the contractor will provide said proof for the discipline appropriate to the modification. This requirement is not an additional cost under the contract and should be included in the coefficients.
1.5 CONTRACTOR USE OF PREMISES
1.5.1 Contractor On-Base Office: The contractor will maintain an office, staffed during normal work hours, on MHAFB solely for the purpose of meeting the terms of this SABER contract. Cost will be included in the contractor’s overhead and no additional payment will be made. The trailer will be provided by the contractor with the contractor responsible for connection to utilities. Space for the trailer will be assigned by 366th CES. Electricity is the only utility certain to be readily available. The office will maintain the ability to communicate by internet, land-line telephone, and fax.
1.5.1.1 The modular/mobile structure provided by the contractor, and used to meet this requirement, will be anchored in accordance with state regulations, skirted, and maintained in good repair.
1.5.1.2 A one-time move may be directed to government-supplied facilities solely at the contractor’s expense.
1.5.2 Contractor Storage Location
1.5.2.1 The contractor may be provided an area to stage materials, store equipment and tools, and maintain miscellaneous items. This area will be secured by the contractor, and any losses to the contained equipment/materials will not be the fault of the government.
1.5.2.2 The contractor area must maintain a neat and orderly appearance. The CO may instruct the Contractor to clean the storage area if it is deemed necessary. The Contractor shall respond within two (2) hours of being notified by the CO, and immediately clean the area. This cleanup is considered fulfillment of the basic contract and charges may not be applied back to the Government.
1.5.2.3 Post a notice of who to contact in case of emergency on all storage trailers and buildings.
1.5.2.4 Cover stored material and protect against physical and climatic damage or loss.
1.5.2.5 Do not leave equipment or materials on elevated locations without prior approval.
1.5.2.6 Store equipment removed in performance of work where directed by the CE SABER Project Inspector, and reinstall in work as required by drawings and specifications. Equipment temporarily removed shall be protected, cleaned and replaced equal to or better than its condition prior to starting work.
1.5.2.7 Do not store construction debris in the outside storage area or hold in this area for resale.
1.5.3 General Operation Requirements
1.5.3.1 Limit use of the premises to construction activities in areas indicated; allow for government occupancy and access.
1.5.3.2 Confine operations to areas within contract limits indicated. Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.
1.5.3.3 Keep driveways and entrances serving the premises clear and available to the government at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.
1.5.3.4 Sweep job site and haul routes daily (or more frequently as required to by the CO to mitigate possible Foreign Object Damage to aircraft engines) as required to remove all spillage, mud, and soil tracked from work site or dumpsite. Cover all loads subject to spillage such as earth fill, rubble, trash, materials taken to off base land fill, etc, during hauling to prevent spillage. Sweep spills immediately. Haul routes must be coordinated with the CE SABER Project Inspector to minimize impact to the base.
1.5.3.5 Perform the work so as not to interfere with the government’s operations.
1.5.3.6 Protect all government property within the work site, except for property required to be demolished. Protect property that is to be demolished until its scheduled demolition time. Protection shall include, but not be limited to, protection from construction generated dust, debris, water, freeze damage, and vibration.
1.5.3.7 Maintain and repair pavements, drives, or turf areas utilized during construction for access roads or storage areas, to the satisfaction of the CO. Cost associated with the above work shall be incidental to the contract. Where landscape rock areas are repaired or installed, provide commercial grade, spun weed barrier under rock to prevent weed growth. Make sure landscape rock is free from dirt and debris, and repair all wheel ruts, etc.
1.5.3.8 Lawn at Job Site: The contractor is responsible for maintaining lawns, landscaping, trees, shrubs, etc. within the work area. Any lawn areas damaged as a result of construction shall be repaired by installation of sod (rather than seeding). If possible, keep vehicles off grass areas. Protect areas under and around trees to prevent damage to tree roots. As appropriate, rope off or place barriers around any trees and shrubs to protect from construction damage. Ensure vehicles, construction materials, etc. are kept a safe distance from trees to ensure minimal damage from soil compaction.
1.5.3.9 Utility installations for crossing streets, sidewalks, curbs, or gutters: All utility crossings of streets, sidewalks, curbs, or gutters shall be by trenchless boring unless specified otherwise. When pavement road cuts are permitted, only half of the road will be closed at any time. The road closures shall be coordinated in advance and the road re-opened as soon as possible to traffic. Final asphalt patching shall be complete within seven (7) days of initial cutting, weather permitting.
1.5.3.10 Contractor Identification Signs: The contractor may erect a sign at the contractor’s furnished office. The sign(s) shall be in compliance with base requirements and color scheme and approved by the BCE before being erected.
1.6 GOVERNMENT FURNISHED SERVICES.
1.6.1 Utility Service: The government will make all reasonably required amounts of utilities available to the contractor from existing outlets and supplies at the contractor’s on-base office as well as job sites. The contractor is responsible for installing temporary service outlets. The contractor will carefully conserve any utilities furnished under this contract. The contractor is solely responsible for provision of telephone and internet service.
1.6.2 The government will furnish the contractor water from a fire hydrant or water fill stand designated by CE SABER Project Inspector. The contractor will operate hydrants with an appropriate hydrant wrench
1.6.3 Emergency Medical Treatment
1.6.3.1 The USAF Hospital, Mountain Home AFB, ID, will provide emergency medical treatment to employees of the contractor for injuries incurred while working at Mountain Home AFB, ID. The contractor will reimburse the USAF Hospital, Mountain Home AFB, for treatment provided at the current reimbursement rate for non-beneficiaries. The contractor will also provide the USAF Hospital, Mountain Home AFB, the name of a physician and/or hospital to which the injured personnel can be transferred for further treatment and care after receiving initial emergency treatment at Mountain Home AFB, ID.
1.6.3.2 Follow-on care, after the initial emergency care, will not be provided.
1.6.4 Refuse Collection: The government will provide refuse collection services from bulk containers located at or near the contractor’s office area. The contractor is responsible for disposing of construction debris and contractor-generated refuse at construction sites safely and properly in accordance Appendix 3. No construction debris will be placed in the government owned dumpsters.
1.7 PHASE IN/OUT.
1.7.1 Contract Phase-in: The contractor will commence any mobilization and familiarization activities prior to actual work on individual delivery orders. The first 14 calendar days following the award of the contract will be designated a start-up period, after which the contractor will have all equipment and personnel in place to fully execute the requirements of this contract. The contractor will be allowed the first 14 calendar days (unless otherwise noted) of the start-up period to mobilize without being asked to perform under this contract. The contractor will have a fully operational field office with all required facilities, staff, and capabilities within 21 calendar days after award.
1.7.2 Completion of Contract: At the conclusion of this contract, the contractor shall be required to vacate the areas provided including, but not limited to: office area, storage area, and individual work sites. The contractor shall return the area to its original condition within 14 calendar days of being notified by the CO, or the conclusion of this contract, whichever comes first.
END OF SECTION
SECTION 2
COORDINATION
2.1 PROJECT COORDINATION.
2.1.1 General. The contractor shall coordinate all work schedules with the CO and with the base CE SABER Project Inspector prior to the start of work. The contractor shall participate in weekly progress meetings with the CO and the SABER staff. Attendance at these meetings may include the contractor’s corporate management representative(s) at the CO’s discretion. Before initiating any work under an individual delivery order, the contractor shall confer with the CO or designated representative(s) and agree on:
2.1.1.1 A sequence of procedures
2.1.1.2 A means of access to premises and buildings
2.1.1.3 Space for storage of materials and equipment
2.1.1.4 Delivery of materials and use of approaches
2.1.1.5 Use of corridors, stairways, elevators, and similar means of egress
2.1.1.6 Communications
2.1.1.7 The locations of partitions and barriers
2.1.1.8 Eating spaces and rest rooms for contractor’s employees
2.1.1.9 Any other incidentals to the project
2.1.2 Interruption of Work: If it becomes necessary to interrupt work activities in buildings and/or other areas for construction purposes (except as otherwise described in the delivery order), the contractor shall request permission, in writing, from the CO ten (10) workdays in advance, if possible.
2.1.3 Construction: Prior to start of any construction under this contract, the contractor shall coordinate start and completion dates in writing with the CO ten (10) workdays prior to the scheduled start date.
2.1.4 Temporary Construction: Any contractor-installed temporary construction intended to prevent interruption of normal work activity or loss of utility services must be coordinated with the CE SABER Project Inspector.
2.2 COORDINATING WITH GOVERNMENT ACTIVITIES.
2.2.1 Adhere to the requirements of each user organization established during the course of negotiations. However, any infringement on the normal working conditions (i.e. closing a hallway) must be coordinated through the CE SABER Project Inspector at least 24 hours in advance. Contractor will be advised of special requirements (i.e. noise/odor limitation) before negotiations.
2.2.2 If it becomes necessary to interrupt the using agencies’ work activities in buildings and/or areas for construction purposes, permission to do so must be requested in writing to the CO five (5) working days in advance. Written requests for street closings shall be submitted for approval fourteen calendar days prior to closing the street.
2.2.3 Work requiring utility outages (electrical, water, gas, comm., etc) which will close down or limit normal activities in the building will be coordinated through the CE SABER Project Inspector. Requests for utility outages shall be submitted in writing to the CE SABER Project Inspector for approval 14 calendar days in advance. Utilities will not generally be turned on and off by the contractor; the contractor will be responsible for coordinating through the CE SABER Project Inspector for scheduling Base Civil Engineering personnel for this purpose.
2.2.4 All work in secure areas shall be under escort by Government personnel. Security Forces may require a local agency check of all personnel involved in the accomplishment of the work prior to commencement of work. When notified of this requirement, the contractor should allow approximately 30 days for this check. The contractor must comply with established procedures in place at time of performance.
2.2.5 Work in Military Family Housing units will require scheduling and notification at least 7 days in advance.
2.2.6 Use of equipment such as cranes exceeding the height of surrounding facilities requires advance coordination with the CE SABER Project Inspector.
2.3 UTILITIES COORDINATION.
2.3.1 Utility Outages: Perform the work under this contract with a minimum of outage time for all utilities and road closures. Schedule any work that requires road or utility outages (electrical, water, gas, communication, etc.), which will close down or limit normal activities in the building, construction area, or other affected areas (as determined by the CO) at a time other than regular work periods of the organization occupying the facility. Submit requests for approved utility outages or road closures fourteen (14) working days prior to commencing work. The contractor must receive approval in writing from the CO before interrupting utilities. Written approval must be present on the job site during outages. Once work begins on an approved outage, work must continue without interruption until the contractor restores utility services to the affected line(s) and/or facility.
2.3.2 Excavating around or locating existing utilities: Identify and locate all valve or utility shut-off locations for use in the event of accidental damage prior to the start of work. To preclude accidental damage, the contractor shall locate the exact location of all known utilities (i.e., communication, natural gas, fuel supply, etc.) by hand digging prior to any excavation with power equipment. The contractor shall note any utilities discovered during excavations that are missing or incorrect on the contract drawings and on the as-built drawings.
2.4 EXISTING FACILITIES/JOB SITE VERIFICATION: Record drawings showing existing facilities and underground utilities are available to the contractor through the CE SABER Project Inspector. The contractor is responsible to verify all dimensions and actual conditions, except underground utilities, when developing individual delivery order proposals. Failure to verify the dimensions and locations will be at the contractor’s risk and shall not relieve the contractor from accomplishing the work required by the contract at the price awarded by the government.
2.5 CONSTRUCTION SCHEDULES AND PROGRESS REPORTS
2.5.1 Submit a construction schedule for all projects exceeding 60 days within 5 days of Notice to Proceed (NTP). Construction schedules will be submitted on an AF Form 3064, Contract Progress Schedule. Work elements listed on the AF Form 3064, Contract Progress Schedule will be listed in Construction Specification Institute (CSI) Master Format. When a project consists of multiple facilities, and/or is divided into phased construction within a single delivery, these instances shall be considered as delivery order phases. Provide for approval to the CO a separate AF Form 3064 for each phase and its apportioned project percentage. In addition, the contractor shall include cumulative AF Form 3064 summarizing all phases of the task order to equal 100%.
2.5.2 Submit a weekly progress report for all projects requiring an AF Form 3064. Progress reports will be submitted on an AF Form 3065, Contract Progress Report. Work elements listed on the AF Form 3065, Contract Progress Report will match the approved AF Form 3064, Contract Progress Schedule for the applicable task order.
2.5.3 The contract progress schedule will be set up to include a combination of work elements with a separate line item for UNIT ACCEPTANCE. UNIT ACCEPTANCE will be given a range of at least 10 percent. Unit acceptance will include clean up and correction of all punch list items.
2.6 HOURS OF WORK: Hours of work will ordinarily be from 6:00 AM to 5:30 PM, Monday through Friday. Access to work sites may be restricted to these hours and days. Work that requires inspection during accomplishment or that prevents inspection of previous work after accomplishment normally will not be allowed during other than the normal work hours specified above. Work during other than normal hours must be coordinated in advance with the SABER Inspector. These hours may be varied by the contractor when approved by the CO to meet weather and temperature conditions and operational requirements.
SECTION 3
SPECIAL PROCEDURES
3.1 WORKING ON OR NEAR AIRFIELD
3.1.1 Airfield: The contractor is responsible for all coordination necessary for any and all flightline/controlled/restricted area construction access. Contact Base Operations for construction restrictions involving the flightline, taxiway, and runway areas and comply with established procedures in place at the time of performance. Special care may be required to control foreign objects and dust near the airfield.
3.1.1.1 Delays to access can be expected due to the military mission and military exercises.
3.1.1.2 Cleanliness of Work Area: Maintain the cleanliness of taxiway, runway, apron pavements and hangar areas at all times to prevent foreign object damage (FOD). Ensure all stockpiles and materials required to be left at the worksite anywhere on the airfield is secured and, if necessary, covered to avoid potential FOD. Any debris caused by contractor activity in airfield areas requires immediate containment. Mud, dust, & dirt on airfield pavement deposited by contractor activity require immediate sweeping.
3.2. WORK IN NON-NUCLEAR MUNITIONS STORAGE AREA (NMSA).
3.2.1. Work to be accomplished under this contract may involve work located within the base security area of Mountain Home AFB. Any work within these areas will have the strictest security requirements.
3.2.2 The contractor will be required to comply with established procedures in place at the time of performance
3.2.3 Delays to access can be expected due to the military mission and military exercises.
SECTION 4
DELIVERY ORDER PROPOSAL AND DESIGN SUBMITTAL
4.1 ORDERING PROCEDURES
4.1.1 Delivery Order Response Requirements
4.1.1.1 As the need exists for performance under the terms of this contract, the CO will notify the contractor of an existing performance requirement and request a price from the contractor for each delivery order (DO). The Government will provide the contractor a Request for Proposal (RFP) with a Statement of Work (SOW) describing the work to be performed, which may include special instructions and conditions, a material submittal register (AF Form 66), and if applicable, thirty-five percent (35%) design drawings to be completed by the contractor.
4.1.1.2 The contractor shall respond to a site visit request within three (3) working days by visiting the proposed work site in the company of the contract administrator, the CE SABER Project Inspector, and a representative of the using agency. The purpose of this site visit will be to establish clear understanding between the contractor and Government as to what work will be required in the DO. On-site changes may be made to the SOW or drawings at this time if the contractor or the Government identifies items of work that have been left out which need to be accomplished as part of the delivery order. Any revisions to the SOW by either party will be provided to the contractor. The contract administrator will issue the RFP to the contractor after the site visit. Completed proposals are due to the contract administrator within 10 working days of the issued RFP.
4.1.1.3 Quick Response Requirements: If the requirement is determined to be a quick response requirement by the CO, the contractor shall submit a delivery order proposal to fulfill the requirement within a maximum of five (5) workdays from receipt of the RFP.
4.1.2 Separate Requirement for Project Design/Estimating
4.1.2.1 The government may issue a delivery order for project design, without obligating the government to the construction of the project. The government’s intent for this is to obtain a design and estimate for projects that are being considered for SABER construction. It is not the government’s intent to have the contractor provide design and estimating service for projects with no serious intent to construct the project under the SABER contract. Project design fee will be as stated in Section B, for the appropriate magnitude. The project magnitude will be stated in each government request for project design/estimate. The contractor shall immediately notify the Contracting Officer (CO) if the project estimate will differ from the government’s determination of magnitude. The contracting officer will take action to ensure the project stays within the magnitude or ensure the contractor/government is equitably compensated for the change in magnitude.
| Micro magnitude |
| $50,000 or less |
| Low magnitude |
| $50,001-$150,000 |
| Medium magnitude |
| $150,001-$500,000 |
| High magnitude |
| $500,001 or more |
4.1.2.2 The government is not obligated to issue the contractor a delivery order for the construction of the project described in a completed design/estimate.
4.1.2.3 Upon government acceptance of a contractor’s design with estimate, the contractor may invoice for the design. If, within one year after acceptance of and payment for a design, the government elects to have the contractor construct the project, the total project price will be adjusted downward in an amount equal to that already invoiced and paid for under the design. If, after the period of one year after acceptance of and payment for a design, the government elects to have the contractor construct the project, the redesign cost will be 25% of the original design amount.
4.1.2.4 If the government and the contractor cannot come to an agreement on a particular project to be priced under the project design/estimating process, negotiations shall either be terminated without cost to the government or the contracting officer shall unilaterally direct the tasks with compensation to the contractor for efforts in its projects/design estimating process.
4.1.3. End of Year Projects (Provisional)
4.1.3.1 Preparation of Proposals: In addition to administration of on-going projects, the Contractor will have sufficient resources and capacity to deliver multiple proposals, within a compressed time period, for provisional projects issued at the End of Year (EOY).
4.1.3.2 Award: Award of provisional projects will be contingent upon the availability of funding and prioritization.
4.1.3.3 Upon receipt of the contractor’s proposal, the government will review the proposal for completeness. The CO and the contractor will then enter into negotiations (as necessary) to add, change, or delete line items to reach a final negotiated amount and period of performance.
4.1.4 Right to Negotiate: The Government reserves the right to enter into negotiations with the Contractor for purpose of obtaining a guaranteed price for one or more submitted EOY proposals. Negotiation by the Contracting Officer may be executed before availability of funding is determined. Said actions will NOT constitute intent to award. All costs incurred by the Contractor as a result of proposal preparation and subsequent negotiations will be borne solely by said same, whether project is or is not awarded.
4.1.5 After completion of negotiations, and prior to issue of a delivery order, the contractor shall provide a corrected copy of the proposal and an updated statement of work reflecting any changes made at negotiations. Changes to the corrected proposal will reflect all changes made during negotiations, and will be used as the final project estimate. Indicate on front page “Final Negotiated Estimate”. Copies will be given to the CO and CE SABER office.
4.1.6 Delivery orders may then be issued by the CO. Each delivery order will include the following information:
4.1.6.1 Base Civil Engineering Project Number and Title
4.1.6.2 Contract Number and Delivery Order Number
4.1.6.3 Statement of Work and Drawings
4.1.6.4 Delivery Order Price
4.1.6.5 Delivery Order Performance Period
4.1.6.6 Delivery Order Award Date
4.1.6.7 Accounting and Appropriation Data
4.1.6.8 Government-Furnished Material
4.1.7 Estimated Quantities: The delivery order may reflect estimated quantity line items. For these items, submit a daily total of quantities used on the days the contractor uses the item. These submittals may be delivery tickets, weigh bills, worksheets, etc., to meet the specific requirement. Provide these submittals to the CE SABER Project Inspector, who will validate and forward them to the CO.
4.1.8 Notice to Proceed: A Notice to Proceed will be issued for each awarded delivery order. The performance period will begin upon receipt of the NTP. In rare instances, on those projects deemed emergencies, the government may issue an oral NTP prior to the issuance of the written delivery order. In that case, the Notice to Proceed will be the date the contractor receives verbal confirmation from the CO. NTPs will not be issued prior to receipt of bond documents (when required).
4.2 DELIVERY ORDER PROPOSAL AND DESIGN SUBMITTAL: Every proposal must be supported by necessary documentation to indicate that adequate engineering and planning to accomplish the requirement have been done so as to minimize any delays in the construction process. Examples of documentation that might reasonably be expected would include sketches, construction drawings, calculations, catalog cuts, specifications, architectural renderings, detailed scope of work, etc.
4.2.1 Statement of Work (SOW): Every delivery order proposal must include a written description of the design. Organize the SOW in a logical format and include a detailed description of each of the major tasks in the delivery order.
4.2.2 Shop Drawings: Drawings submitted by the contractor, subcontractor, and any lower tier subcontractor, must show in detail the proposed fabrication and assembly of structural elements and/or the installation (i.e. form fit, and attachment details) of materials or equipment. The government will not require designs in excess of a conventional design developed to a 35% stage. Drawings must have sufficient detail to enable both the contractor and the government to accomplish independent estimates. For the purpose of this requirement, the term drawings includes actual shop drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the contractor to explain in detail specific portions of the work required by the contract.
SECTION 5
TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
5.1 SAFETY.
5.1.1 The contractor is required to comply with OSHA standards applicable to any work performed.
5.1.1.1 Control access to sites under contractor control and ensure that any individual on-site exercises appropriate safety procedures including wear of personal protective equipment.
5.1.2 The contractor assumes full responsibility and liability for compliance with the applicable rules and regulations for the health and safety of personnel during the execution of work, and shall hold the government harmless for any action on the contractor’s part or that of its employees or subcontractors, which results in illness, injury, or death.
5.1.3 Immediately report any mishap resulting in personal injury or property damage and fully cooperate in any associated investigation.
5.2 FIRE PREVENTION
5.2 Comply with all applicable National Fire Prevention Association standards associated with contract performance as well as published Mountain Home AFB procedures.
5.2.2 Restore automatic fire sprinkler and detection systems upon completion of work. When protected facilities are unoccupied and detection/suppression systems are out of service, post a fire guard unless other arrangements have been made.
5.3 SEVERE WEATHER: Be prepared at all times for severe weather and take action to protect people, materials, facilities, and equipment affected by contract activities.
5.4 BARRIERS AND ENCLOSURES: The contractor may be required to erect and remove temporary barricades or fencing to safeguard the construction site and protect individuals adjacent to the area of work as identified in the DO. Any devices interfering with pedestrian or vehicle traffic will be coordinated with the CE SABER Project Inspector.
5.4.1 Site Plan: Prepare and submit to the CO, a site plan indicating the proposed location and dimensions of any area to be fenced and used by the contractor, the number of trailers to be used, avenues of ingress/egress to the fenced area, and details of the fence installation. Any areas that may have to be graveled to prevent the tracking of mud shall also be identified. The contractor shall also indicate if the use of a supplemental or other staging area is desired.
5.4.2 Indoor Barricades: Furnish, install, and maintain adequate barricades and warning signs to isolate the construction area from other occupied building areas, and to block direct access to open floor areas, areas with tripping hazards, and/or areas with overhead construction hazards.
5.4.3 Outdoor Barricades: Furnish, install, and maintain adequate barricades, warning signs, and flares to isolate outdoor construction areas. Identify and barricade all open trenches and excavations at the end of each day.
5.4.4 Fences may be required to isolate the construction site.
5.4.5 Temporary traffic control shall be conducted in accordance with the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD)
5.5 SECURITY
5.5.1 Comply with all security regulations imposed by the installation commander and/or the agency occupying the space where the contractor will perform the work.
5.5.2 To prevent outside intrusion, at the end of each day, close up each and every exterior wall and roof opening resulting from work in buildings. Closures shall remain in place when the contractor is not actively working on the site. This requirement may be waived by the CO.
5.6 TEMPORARY CONTROLS
5.6.1 Perform normal housekeeping functions inside and outside facilities as outlined in base regulations and as directed by the CO. Such functions include sweeping, mopping, dusting, disposal of accumulated waste materials and rubbish, and other operations necessary to present a neat appearance at all times. Remove rubbish and waste materials daily and place in approved containers outside the building. Limits of construction will be defined during site visits and the contractor will be responsible for grounds maintenance within the defined area. Mud, dirt, and debris spilled on roads and parking lots will be cleaned at the end of each day, and flight line surfaces will be cleaned immediately.
5.6.2 Excavations. Backfill all excavations immediately when possible, and always within one week of completion of work.
5.6.2.1 Temporarily repair road cuts to assure a smooth transition until accomplishing final repairs.
5.6.2.2 The contractor shall complete final grading within one week of the completion of work involving disturbance to grounds/back filling. Complete final landscaping within three (3) weeks of the beginning of a planting season to all areas available for such work.
5.6.3 Access Roads: At the end of each day, inspect for and clear all mud, dirt, debris, foreign objects, or spills of any kind from the contractor’s operation (including subcontractors and suppliers) on streets and parking lots used as access to the work or staging areas. Ensure all taxiways, runways, parking aprons, and hard surfaces in or around the airfield used to access the work or staging areas remain clean at all times.
SECTION 6
EQUIPMENT AND MATERIAL
6.1 EQUIPMENT: Provide equipment and qualified operators, maintain it in a safe, serviceable condition, and use it only for its intended purpose. The CO reserves the right to inspect any on-base equipment and reject such equipment if considered unsafe, in poor operating condition, or inappropriate for work. The contractor must notify the CO of any contractor equipment broken down on any base road. Every effort should be made to move inoperable equipment to the nearest parking lot before leaving it.
6.2 MATERIAL
6.2.1 Government Furnished Materials (GFM) will not be furnished to the contractor as a general rule; however, the government reserves the right to provide GFM and/or Government Furnished Equipment (GFE) to be used on any delivery order. In such cases, these materials will be documented and excluded from the price of the delivery order.
6.2.1.1 The contractor, with its own personnel, shall transport all GFE/GFM, if any, described on the delivery order from the government storage area to the work site.
6.2.1.2 The contractor is responsible for the loss or damage to GFM.
6.2.1.3 Follow the instructions of the CO regarding the disposition of all Government-furnished property not consumed in performance of a delivery order.
6.2.2 Real Property Installed Equipment (RPIE): The government will not use this contract solely to satisfy equipment requirements (such as dishwashers, ranges, swimming pool accessories, etc.). However, delivery orders may include incidental requirements for equipment that are reasonable components of a construction project.
6.2.3 Store equipment removed in performance of work where directed by the CE SABER Project Inspector, and re-use in work as required by drawings and specifications. Equipment temporarily removed shall be protected, cleaned and replaced equal to or better than its condition prior to starting work.
6.3 Salvage Material and Equipment: Salvage items to be retained by the government will be identified on each delivery order, as applicable.
6.3.1 Provide equipment and personnel as required for loading, transportation to delivery point, off loading and positioning at final location.
6.3.2 Items not identified for demolition or government reuse will become the property of the Contractor and removed from Government property.
END OF SECTION
SECTION 7
DELIVERY ORDER CLOSEOUT
7.1 INSPECTION REQUEST
7.1.1 Notification: The Contractor may request a pre-final inspection for the purpose of having the Government assist in identifying discrepancies or punch-list items prior to the final inspection. Any discrepancies identified at the pre-final inspection must be completed before the final inspection.
7.1.2 When the Contractor is ready for final inspection, the Contractor shall submit
7.1.2.1 As-built drawings, with CAD disk, if applicable
7.1.2.2 Quality control (QC) report signed by the QCM listing any discrepancies
7.1.2.3 DD Form 1354 (Transfer and Acceptance of DoD Real Property), new construction
7.1.2.4 Facility Data Worksheet, renovation work
7.1.2.5 Keys and key schedule
7.1.2.6 O&M manuals
7.1.2.7 Warranties
7.1.2.8 Written request for final inspection to the CO
7.1.3 Final inspections must be requested a minimum of 48 hours prior to the desired date. The Contractor must schedule final inspection in sufficient time to allow for final clean-up and acceptance NO LATER THAN the specified contract completion date.
7.2 FINAL INSPECTION
7.2.1 The final inspection will be conducted with the contract administrator, QCM, Superintendent, and SABER PM. If, during a final inspection, it is obvious that the job site is not ready for final inspection, the inspection will be terminated and rescheduled after a minimum of 24 hours. If the final inspection was scheduled and terminated by the contractor, the contractor may be assessed Liquidated Damages in accordance with the basic contract.
7.2.2 The contractor must ensure the job site is thoroughly cleaned prior to inspection. Remove any leftover gypsum board, dust, smudges, spackle/glue splatter, or paint spatter from the site after construction. Ensure all tile is wiped down and free of dirt and debris, clean glass, and vacuum carpeting.
7.3 PROJECT CLOSEOUT
7.3.1 The government requires the following information (as applicable) for record and operation purposes. The following must be submitted within ten days of the final inspection.
7.3.1.1 Final Invoice
7.3.1.2 Release of Claims
7.3.1.3 Final Certified Payrolls
7.3.2 As-Built Drawings: Maintain one set of drawings at the work site and record all changes and any hidden or subsurface data discovered during construction. Provide a marked up red-line copy with all changes that transpired during performance of the delivery order to the CO prior to the final inspection. Submit completed record drawings and survey information in accordance with Appendix 2.
7.3.3 Keys and Keying Schedule. Provide all keys to finish hardware as indicated on the finish hardware schedule or sections of work.
7.3.3.1 Comply with base design standards for compatibility of locksets, latch sets, deadlocks and cores.
7.3.3.2 Cores will be furnished by the contractor and combinated and installed by the base locksmith.
7.3.4 Operation and Maintenance Manuals/Data: Furnish two (2) copies of operation and maintenance manuals for any installed products containing complete instructions for operation, inspection, testing and maintenance of the system, including part breakdown diagrams. If applicable, the manuals shall also contain complete wiring schematics and diagrams. Provide the CO all paperwork that was shipped with or attached to the product or material including:
7.3.4.1 Installation or maintenance instructions for the product or material
7.3.4.2 Part number listing
7.3.4.3 Care and/or cleaning instructions
7.3.4.4 Removing and replacing information
7.3.4.5 Warranty information
7.3.4.6 Operator manuals
7.3.5 Facilities Data Worksheet:. Submit a Facility Data Worksheet for all major equipment items. List all equipment furnished and installed during new construction, maintenance, repair/renovation, etc., of any items that increase the capacity or extend the service provided by those items repaired/replaced. This list will include, but is not limited to, each piece of equipment that has a serial number.
7.3.6 DD Form 1354 (Transfer and Acceptance of DoD Real Property): Submit a completed DD Form 1354 for all new construction.
7.3.7 One year warranty. Provide a comprehensive, one-year warranty covering all materials, equipment, and workmanship, to be honored by the contractor.
7.3.7.1 This requirement is primary, and in addition to any warranties provided by manufacturers and installers.
7.3.7.2 Provide a single, 24-hour warranty point of contact for all work.
7.3.7.3 The CO will determine the category of the call. Respond to warranty issues within the following times.
· Routine Calls. Respond within three (3) calendar days after notification by the CO, and not later than one (1) calendar day on the second and subsequent attempts to correct a deficient item. The work must be completed within seven (7) days of receiving materials.
· Urgent Calls. Respond within 24 hours of notification and complete corrective action within three (3) days of receiving materials.
· Emergency Calls. Respond within two (2) hours of notification and complete corrective action within 24 hours of receiving materials.
APPENDIX 1: GENERAL SECURITY REQUIREMENTS
1. General
1.1. Scope: These standards apply to all new construction, demolition, rehabilitation, alteration, modification, repair, and maintenance contracts for existing facilities.
1.2. General Requirements: Compliance with Laws: The contractor shall comply, and ensure that all subcontractor(s) comply, with all applicable Federal, State, and Local laws, regulations, ordinances and standards related to safety and security matters at Mountain Home Air Force Base.
1.3. Listing of Employees: Maintain a current listing of employees and provide a list of the key personnel within 30 days of contract award, to the CO. The list shall include employee's name, social security number, and date of investigation if contract work involves unescorted entry to Air Force restricted or other sensitive areas designated by the Installation Commander. The list shall be validated and signed by the contractor representative with the authority to bind the contractor, and provided to the Contracting Officer prior to the contract start date. Updated listings shall be provided when an employee's status or information changes.
1.4. Reporting Requirements: The contractor shall comply with Air Force Instruction (AFI) 71-101, Volume-1, Criminal Investigations, and Volume-2, Protective Service Matters, requirements. Contractor personnel shall report to the QAP any information or circumstances of which they are aware that may pose a threat to the security of DOD personnel, contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment and as required thereafter.
1.5. Security
1.5.1. Personnel Security: Contractor personnel requiring unescorted entry to restricted or other sensitive areas designated by the Installation Commander shall comply with AFI 31-101, The Air Force Installation Security Program, and AFI 31-501, Personnel Security Program Management, requirements.
1.6. Traffic Laws: The Contractor and its employees shall comply with base traffic regulations in accordance with the provisions of AFI 31-204.
1.7. Base Exercises Upon implementation of a base exercise, the contractor will be required to present a Mountain Home AFB contractor’s badge indicating they are exempt. When determined to be in the best interest of the government, the 366 SFS will release the contractor to continue its work.
1.8 Telephone System Security Monitoring: All communications with DOD organizations are subject to communications security (COMSEC) review. Contractor personnel will be aware that telecommunications networks are continually subject to intercept by unfriendly intelligence organizations. The DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, civilian contractor personnel are advised that any time they place a call to, or receive a call from, military organization, they are subject to COMSEC procedures. The contractor will assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees dealing with official DOD information.
1.9 Key Control: The contractor must establish and implement methods to ensure safeguarding of all keys issued to the contractor. Keys may not be duplicated without authorization. The contractor may only allow access to authorized individuals. Lost keys will be reported to the Contracting Officer and any re-keying required to maintain security may be billed to the contractor.
APPENDIX 2: GIS DELIVERABLES
GEOSPATIAL INFORMATION SYSTEM (GIS) DELIVERABLES FOR
DESIGN & CONSTRUCTION PLANS
The contractor shall provide deliverables in the following format:
All locational base map (point, line, and polygon feature(s)) data collected shall be delivered in ESRI ArcGIS 9.x digital format along with the original source files. The geospatial files shall have an external spatial reference (.prj) file attached specifying the parameters of the coordinate system used (as provided by the government). All topologically correct geospatial data shall overlay on the installations latest orthorectified imagery provided by the government, using the same coordinate and projection system of the imagery (UTM 11 north WGS84, using the EGM96 geoid model ). All accuracy errors shall be reported to the contract program manager.
All Architectural/Engineering data (building components, plans, designs, etc.) shall be in a digital (electronic information) format AutoCAD 2005 or higher.
· All graphic and non-graphic data will be collected in the format defined by the Spatial Data Standards Facilities, Infrastructure, and…