Q A_-_FA4877-16-Q-0477_Sunshade_Removal_ _Install.pdf

PDF 46 KB Posted

Attached to
Sunshade Removal & Install Federal contract opportunity
Solicitation number
FA4877-16-Q-0477
Issued by
Department of the Air Force Air Combat Command

About this file

Q A

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4877‐16‐Q‐0477 Sunshade Removal & Install Questions and Answers

Q1. What is the width of the parking spot line that will be removed? What is the width of the tow line that will be removed? What is the width of the new parking spot lines and new tow line?

A1. All the lines are approximately 6 inches and the two tow lines come directly out of our hangar and to the current sunshade.

Q2. Site layout slide #3 states that there are two tow lines at 75' each that need to be removed arethese lines depicted on any of the 4 site layout slides? If so could you highlight where these 75' tow lines are located?

A2. I do not see the originals marked but they are replaced by the two diagonal lines that go into the hangar off the centerline.

NOTE: The dimensions of the current sunshade are 167’‐1 1/2” X 50’‐0” X 32”‐6’.