Questions_and_Answers_Updated.pdf
PDF 393 KB Posted
- Attached to
- MAFR Temporary Bunkhouse Federal contract opportunity
- Solicitation number
- FA485518R0026
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4855-18-R-0026-0003_Extend_Closing.pdf | ||
| UPDATED_SOO_MAFR_TFB.pdf | ||
| FA4855-18-R-0026-0002.pdf | ||
| QUESTIONS_AND_ANSWERS.pdf | ||
| Statement_of_Objectives-_MAFR_TFB.pdf | ||
| FA4855-18-R-0026-0001_Bunkhouse.pdf | ||
| FA4855-18-R-0026_Bunkhouse.pdf | ||
| PP_Questionnaire.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS **UPDATE 1**:
TEMPORARY FIRE BUNKHOUSE
24 JUL 2018
(PICTURES OF SITE BELOW Q&A)
1. What is the the distance to the nearest water tie-in location, as well as the existing pipe size.
a. The connections will be within 75' of where the units will be located.
2. **UPDATED** How far to the nearest electrical supply and what is the available phasing, amps and voltage, or will we need to supply a new service through the local utility?
a. It is planned to be about 250' from the location of the Temporary Bunkhouse. Main line is 12470 Volt, 3 Phase line. The power request is for a 103 kW transformer with 120/240V single phase coming out of transformer.
3. Is there any soils report available for the proposed site?
a. I would have to do some digging for an actual report, however I can say that it is loose sand.
4. I have spoken with our site contractor and he was requesting photographs of the site. This will allow him to at least assemble an minimally knowledgeable proposal for the sitework, facilities.
a. Three pictures below.