B2123_Schedule_of_Material_Submittals.xls
XLS spreadsheet 35 KB Posted
- Attached to
- B2123 Roof Repair
- Solicitation number
- FA4855-13-R-0033
About this file
Attachment 2 AF66 Schedule of Material Submittals
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF66
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT TITLE | SOLICITATION / CONTRACT NO. | |||||||||||||||||||||
| CZQZ13-1126 | Emergency Roof Repair B2123 | FA4855- | ||||||||||||||||||||||
| TO BE COMPLETED BY THE PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | NUMBER OF COPIES REQUIRED | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |||||||||||||
| CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MFG'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | OTHER | ||||||||||||
| APPROVED | DIS- APPROVED | |||||||||||||||||||||||
| 1 | Project Progress Report (AF3065) | 3 | Biweekly | |||||||||||||||||||||
| 2 | Accident Prevention Plan | 3 | NTP + 10 days | |||||||||||||||||||||
| 3 | Activity Hazard Analysis | NTP + 10 days | ||||||||||||||||||||||
| 4 | Roofing Licenses and Certificates | 3 | NTP + 10 days | |||||||||||||||||||||
| 5 | Environmental Protection Plan | 3 | 3 | NTP + 10 days | ||||||||||||||||||||
| 6 | Material Safety Data Sheets | 3 | NTP + 10 days | |||||||||||||||||||||
| 7 | Construction Quality Control Plan | 3 | NTP + 10 days | |||||||||||||||||||||
| 8 | Sealants | NTP + 10 days | ||||||||||||||||||||||
| 9 | Welding Procedures Qualifications, Quality control and Specifications | 3 | NTP + 10 days | |||||||||||||||||||||
| 10 | Roofing, Detail Drawings, Material Samples, Installation Instructions, Maintenance Instructions, Certificate | 3 | 3 | 3 | 3 | 3 | 3 | 3 | 3 | NTP + 10 days | ||||||||||||||
| 11 | Steel Coatings, Materials, Fixture list, Product Data, Samples, Certificates | 3 | 3 | NTP + 10 days | ||||||||||||||||||||
| 12 | Lghtning Protection Materials, Equipment and Fixtures, Eq list, Shop Drwgs, Prod Data, Test Reports, Certs | 3 | 3 | 3 | NTP + 10 days | |||||||||||||||||||
| 13 | Close Out Submittals, As-Blt Dwgs, Warranty | 3 | 3 | Final + 10 days |
&L&"Times New Roman,Regular"&8Schedule of Material Submittals, Feb 05 (SAF/AQCP)&R&"Times New Roman,Regular"&8&P of &N