QA's_-_Base_Recycle_Center.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Repair Base Recycle Center, Bldg. 6035 Federal contract opportunity
- Solicitation number
- FA481919RA022
About this file
**Please disregard the Q&A document that was posted on 9-16-19 since it was the incorrect document**
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QA's_-_6000_Area.xlsx | XLSX spreadsheet | |
| (Revised)_Additional_Questions_&_Answers_-_Base_Recycle_Center.pdf | ||
| Additional_Questions_&_Answers_-_Base_Recycle_Center.pdf | ||
| B6035_Drawings.pdf | ||
| QA's_-_Base_Recycle_Center.xlsx | XLSX spreadsheet | |
| Site_Visit_Attendee_List.pdf | ||
| Attachment_02_Appendix_A_Scope_of_Work.pdf | ||
| Attachment_04_Wage_Determination_4_Jan_19.pdf | ||
| Solicitation_-_FA481919RA022.pdf | ||
| Attachment_09_General_Financial_Information.pdf | ||
| Attachment_05_AF_Form_66.xls | XLS spreadsheet | |
| Attachment_07_AF_3064.pdf | ||
| Attachment_06_AF_Form_3000.pdf | ||
| Attachment_10_Insurance_Requirements.pdf | ||
| Attachment_01_SOW.pdf | ||
| Attachment_03_Appendix_B_Photos.pdf | ||
| Attachment_08_AF3065.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PPIF
| Pre Proposal Inquiry Form | Solicitation No: FA481919RA022 |
| Contracting Officer Name: Mrs. Melissa Sanders | Project Title: Repair Base Recycle Center |
| Contract Administrator Name: A1C Alyssa McSwain | Proposal Due Date: 9/19/19 |
| Review: 9/6/19 | |
| Email: 325CONS.Construction@us.af.mil |
| Question No. | Reference (Sect/Para/Page) | Question | |
| 1 | Site Visit Inquiry | Please provide the permitting agency and contact information for the project. | This information will be discussed at the Preconstruction conference prior to work beginning. |
| 2 | Site Visit Inquiry | Does the project duration of 280 days from NTP include the architect design phase? | The 280 days includes the design phase. |
| 3 | Site Visit Inquiry | What locations are available for construction generated garbage and debris dumping; is this on the base or must it be hauled off base? | Review Section 1.1 GENERAL REQUIREMENTS, Item P- Cleanup; 4.11.2.5 Hazardous Waste, Item P Covered Chutes; 5.9 GENERATED REFUSE. |
| 4 | Site Visit Inquiry | Will additional consideration be given to the General Contractor for project award if the proposed Architect is a Women-Owned Small Business (WOSB)? | No |
| 5 | Site Visit Inquiry | Often bids that are above the Simplified Acquisition Threshold and that require Performance and Payment bonds also required a bid bond. It appears this project does not require a bid bond. Please indicate if this is correct or if we should provide a bid bond? | No bid bonds required. |
| 6 | Site Visit Inquiry | What year was the original building designed and constructed? | 9/25/09 |
| 7 | Site Visit Inquiry | What was the applicable building code when the original building code was designed? | 2007 |
| 8 | Site Visit Inquiry | Will the occupancy of this building increase or change? | No |
| 9 | Site Visit Inquiry | Appendix A Scope of Work, Section 2.0 Summary of Work, par. 2.0 Architectural, 2.3 states ”Replace all doors on all sides of the building to comply with AT/FP requirements and in coordination with structural requirements. Will this facility have to comply with any other or all of UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings? | No |
| 10 | Site Visit Inquiry | Bullet item “K” list several exterior improvements such as parking lot improvements, pavement marking, sidewalks, entry way pavements, perimeter fencing etc. which are not found in the Appendix A Scope of work. Which Scope of work will take precedence or fully define the work required? | No, items with no scope are not included in this project. |
| 11 | Site Visit Inquiry | Please confirm it is the intent of the specifications to require the contractor to have a person onsite full time from the time Construction begins until the work is substantially complete. | Only when project contractor or sub-contractor is onsite or work is being performed for this project. |
| 12 | Site Visit Inquiry | "We are trying to gather information to bid out 3 12x12 roll up doors, our engineer needs information for the earthquake requirement, they need occupancy category, and site class. Could you please provide me with the information or point me in the right direction?" | Contractor would need to determine earthquake requirements and state why they are not needed. Occupancy 3 to 5 persons periodically throughout the day. Site class information not available at this time. |