FA4809-10-R-0004 SJAFB NC Atch 1 Appendix B - Section 01560.doc

DOC document 85 KB Posted

Attached to
Multiple Award Construction Contract (MACC)
Solicitation number
FA480910R0004
Issued by

About this file

Atch 1 Appendix B to SOW

View the file

Other files

File Type Posted
NOTICE.docx DOCX document
FA4809-10-R-0004 SJAFB NC Atch 5 Atch 2 Blank 3052.xls XLS spreadsheet
Questions and answers 21 Oct 10.docx DOCX document
G-1 COVERSHEET.dwt —
Bldg 3803 1st Floor.ppt PPT presentation
Survey.dwt —
Telecommunications.dwt —
3803rooff.dwg DWG drawing
Tsaec.mln —
A2.DWG DWG drawing
A1.DWG DWG drawing
E3PLAN.DWG DWG drawing
2NDFLOOR.DWG DWG drawing
934002prop2.dwg DWG drawing
Drawer4_20100716_0004.PDF PDF
Drawer4_20100716_0012.PDF PDF
Drawer4_20100716_0017.PDF PDF
Drawer4_20100716_0018.PDF PDF
Drawer4_20100716_0027.PDF PDF
Drawer4_20100716_0001.PDF PDF
Drawer4_20100716_0010.PDF PDF
Drawer4_20100716_0028.PDF PDF
934002demo2.dwg DWG drawing
Drawer4_20100716_0007.PDF PDF
Atch 5.1 pg 10 25-06-02_11.pdf PDF
FA4809-10-R-0004 SJAFB NC Atch 2.7 Wage Det - NC100009 —
Atch 5.1 pg 26 VKAG 84-1076 D-1.pdf PDF
Atch 5.1 pg 43 VKAG 84-1076 E-8.pdf PDF
Atch 5.1 pg 68 VKAG 86-1006 T-1.pdf PDF
Atch 5.1 pg 84 VKAG 96-1104 A-3.PDF PDF
Atch 5.1 pg 32 VKAG 84-1076 E-1.pdf PDF
Atch 5.1 pg 28 VKAG 84-1076 D-4.pdf PDF
Atch 5.1 pg 62 VKAG 86-1006 E-1.pdf PDF
Atch 5.1 pg 34 VKAG 84-1076 E-2.pdf PDF
Atch 5.1 pg 64 VKAG 86-1006 E-3.pdf PDF
Atch 5.1 pg 51 VKAG 84-1076 P-5.pdf PDF
FA4809-10-R-0004 SJAFB NC Appendix F - AF Form 66.xls XLS spreadsheet
FA4809-10-R-0004 SJAFB NC Atch 5.1 pg 2 25-06-02_3.pdf PDF
Atch 5.1 pg 36 VKAG 84-1076 E-3.pdf PDF
Atch 5.1 pg 61 VKAG 86-1006 A-6.pdf PDF
Atch 5.1 pg 7 25-06-02_8.pdf PDF
Atch 5.1 pg 75 VKAG 93-4002 E-4.pdf PDF
Atch 5.1 pg 87 VKAG 96-1104 A-5 AS-BUILT.PDF PDF
Atch 5.1 pg 90 VKAG 96-1104 COVER.PDF PDF
Atch 5.1 pg 78 VKAG 94-4001 C-1.pdf PDF
Atch 5.1 pg 41 VKAG 84-1076 E-6R.pdf PDF
Atch 5.1 pg 63 VKAG 86-1006 E-2.pdf PDF
Atch 5.1 pg 93 25-06-02_14.pdf PDF
Atch 5.1 pg 85 VKAG 96-1104 A-4.PDF PDF
FA4809-10-R-0004 SJAFB NC Atch 3 - Determination of Contractor Responsibility.doc DOC document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4809-10-R-0004

Attachment 1

SECTION 01560

ENVIRONMENTAL PROTECTION

1.

DEFINITIONS:

1.1 Oil: Any kind of oil in any form, including, but not limited to: fats, oils, or greases of animal, fish, or marine mammal origin; vegetable oils, including oils from seeds, nuts, fruits, or kernels; and, other oils and greases, including petroleum, fuel oil, sludge, synthetic oils, mineral oils, oil refuse, or oil mixed with wastes other than dredged spoil.

1.2 Hazardous Material (HAZMAT): Includes all items (including medical supply items, but excluding drugs in their finished form and pharmaceuticals in individually-issued items) covered under Emergency Planning & Community Right-To-Know Act (or other host nation, federal, state, or local) tracking requirement, the OSHA HAZCOM Standard, and all Class I and Class II Ozone Depleting Substances.

2.

ENVIRONMENTAL PROTECTION REQUIREMENTS: Provide and maintain during the life of the contract, environmental protection as defined herein. Provide environmental protection measures as required to control pollution that develops during normal construction practice. Provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Comply with all federal, state, and local regulations pertaining to environmental requirements. Develop proposals for an environmental protection plan for the project and, prior to the commencement of the work, meet with the Contracting Officer and discuss the proposed environmental protection plan. The meeting shall develop mutual understanding relative to details of environmental protection, including measures for protecting natural resources, required reports, and measures to be taken should the Contractor fail to provide adequate protection in a timely manner. Perform a preconstruction survey of the project site and take photographs as necessary to enhance the survey.

3.

ENVIRONMENTAL MANAGEMENT SYSTEM – Seymour Johnson AFB has an Environmental Management System in place. The Contractor shall support and comply with the Environmental Management System operational and administrative requirements. The contractor and all associated employees shall maintain an awareness of potential environmental impacts associated with the duties they are performing. Actions must be taken to minimize those environmental impacts during any service, design and/or construction activity. The Contractor and all appropriate personnel shall complete Environmental Management System awareness training and ensure all employees working on SJAFB are knowledgeable of EMS policies and procedures. An Executive Summary of Seymour Johnson’s EMS shall be provided to the contractor. EMS awareness training is available to contract personnel at the following Air Force sponsored training site: http://esohtn.com. The contractor shall provide written certification of training completion to the Contracting Officer within 30 days of contract start up.

4.

PROTECTION OF NATURAL RESOURCES: The natural resources within the project boundaries and outside the limits of permanent work performed under this contract shall be preserved in their existing condition or restored to an equivalent or improved condition upon completion of the work.

4.1 Land Resources: Except in areas indicated to be cleared, do not remove, cut, deface, injure, or destroy trees or shrubs without special permission from the Contracting Officer. Do not fasten or attach ropes, cables, or guys to any existing trees for anchorages unless specifically authorized. Where such special emergency use is authorized, the Contractor shall be responsible for any resultant damage.

4.1.1 Protection: Protect existing trees which are to remain and which may be injured, bruised, defaced, or other wise damaged by construction operations.

4.1.2 Repair or Restoration: Repair or restore to their original condition all trees or other landscape features scarred or damaged by the equipment or operations. Obtain approval of the repair or restoration from the Contracting Officer prior to its initiation.

4.1.3 Temporary Construction: Obliterate all signs of temporary construction facilities such as haul roads, work areas, structures, foundations of temporary structures, stockpiles of excess or waste materials, and all other vestiges of construction. Temporary roads, materials, and all other vestiges of construction. Temporary roads, parking areas, and similar temporary use areas shall be graded in conformance with surrounding areas, tilled, and seeded. Include topsoil of nutriment during the seeding operation as necessary to reestablish a suitable stand of grass. The seeding operation shall be as specified in Section 02485.

4.2 Fish and Wildlife Resources: During the performance of the work take such steps as required to prevent interference or disturbance to fish and wildlife. Do not alter water flows or otherwise significantly disturb native habitat adjacent to the project area which are critical to fish and wildlife except as may be indicated or specified.

5.

EROSION AND SEDIMENT CONTROL MEASURES: If the work associated with this project disturbs more than one acre of land, the contractor shall follow all requirements set forth in North Carolina General Statute 143-215.1, Permit No. NCG010000. This includes but is not limited to the design/application of an erosion and sedimentation control plan, paying the associated fee, the proper control of the Certificate of Approval (granted by NCDENR), implementation of the plan, and all the inspection type requirements during the actual construction period along with the proper documentation. These required documents shall be provided and/or made available to appropriate government personnel upon request. At least one copy of each NOI, NPDES Permit, SWPPP PLAN, Certificate of Approval, and Certificate of Termination Document shall be given to the 4 CES/CEV Office.

5.1 If the work associated with this project disturbs less than one acre of land, the contractor shall provide properly and adequately designed/implemented erosion and sedimentation control practices as to not contribute pollution to the base’s regulated storm water discharges. This includes but is not limited to protection of storm drains, ditches, or other waters of the State from sedimentation runoff; and controlling disposal of discarded building materials, concrete truck washout, chemicals, litter, and sanitary wastes at the construction sites that may cause adverse impacts to water quality.

5.1.1 Burn-off: Burn-off of ground cover is not permitted.

6.

CONTROL AND DISPOSAL OF SOLID, CHEMICAL, AND SANITARY WASTES: Pick up solid wastes and place in containers which are emptied by the contractor on a regular schedule. The preparation, cooking, and disposing of food are strictly prohibited on the project site. Conduct handling and disposal of wastes to prevent contamination of the site and other areas. On completion, leave areas clean and natural looking. Obliterate signs of temporary construction and activities incidental to construction of the permanent work in place.

6.1 Removal from Government Property: Remove rubbish and debris from Government property and dispose of it in compliance with federal, state, and local requirements.

6.2 Chemical Waste: Store chemical waste in corrosion resistant containers labeled to identify type of waste, date filled, and contractor name. Remove containers from the project site, and dispose of chemical waste in accordance with federal, state, and local regulations. Chemical waste has the potential to become hazardous waste. The contractor shall conduct sample analysis sufficient to determine if the waste is a hazardous waste as defined in 40 CFR Part 261. Any waste meeting the definition of hazardous shall be accumulated and manifested in accordance with federal, state, and local regulations and coordinated with the 4 CES/CEV office. The contractor shall notify the Contracting Officer immediately in the event of any chemical waste spill.

6.3 Petroleum Products: Conduct fueling and lubricating of equipment and motor vehicles in a manner that affords the maximum protection against spills and evaporation. Dispose of lubricants to be discarded and excess oil in accordance with approved procedures meeting federal, state, and local regulations.

7.

DUST CONTROL: Keep dust down at all times, including non-working hours, weekends, and holidays. Sprinkle or treat, with dust suppressors, the soil at the site, haul roads, and other areas disturbed by operations. No dry power brooming is permitted. Instead use vacuuming, wet mopping, wet sweeping, or wet power brooming. Air Blowing is permitted only for cleaning non-particulate debris, such as steel reinforcing bars. No sandblasting is permitted unless dust there from is confined. Only wet cutting of concrete blocks, concrete, and asphalt is permitted. No unnecessary shaking of bags is permitted where bagged cement, concrete mortar and plaster is used.

8.

SOLID WASTE DIVERSION AND RECYCLING

All solid waste generated as a result of project activities are the responsibility of the Contractor. The Contractor shall provide necessary dumpsters, roll-offs, containers, etc. for proper storage, removal, and ultimate disposal the solid waste. The Contractor shall not use base dumpsters, roll-offs, or containers for the disposal of solid waste. Solid waste debris, including construction & demolition debris shall be recycled and/or diverted away from landfill disposal to the extent practical for the project.

A. Construction debris that cannot be recycled: Demolition and/or construction materials that cannot be reused, recycled, or otherwise diverted must be segregated from other solid waste and disposed at an approved C&D landfill. The Wayne County C&D landfill is adjacent to the Municipal Solid Waste Landfill. The Contractor shall maintain records of construction debris diverted and disposed.

B. Recyclables: The contractor shall remove recyclables from the solid waste stream to the extent practicable. Disposing of recyclables in a municipal solid waste landfill (MSWLF) is not acceptable and may constitute violation of the contract. Local county ordinance prohibits the disposal of solid waste with greater than 10% recyclables. In the event the county sites the Contractor for excessive recyclables within a load, the Contractor is solely responsible for fines and/or increased tipping fees. Recyclables shall be taken to off-base facilities for recycling with all profit from those materials being those of the Contractor. The Contractor shall maintain records (by weight) of all materials recycled and disposed.

Use of demolition debris (rubble) as fill material is considered recycling. The contractor shall report reuse of such material in the monthly Solid Waste Diversion report (see format below).

The contractor will report, monthly, no later than the last day of the following month, the total weight of solid waste and construction/demolition waste he disposed, and percentage diverted through recycling. The report will be made in two copies. The following format will be used:

Solid Waste Report Project #:

Contract #:

Facility #:

Contractor :

Contractor Point of Contact:

Contractor Phone #:

4 CES QAE:

Report Period: dd/mm/yyyy to dd/mm/yyyy

LBS
RECEIVING FACILITY

A. Total Amount of Solid Waste Taken to Municipal Solid Waste Landfill

B. Total Amount of C&D Debris Taken to C&D Landfill For Disposal

C. Total Amount of Recyclables Retained for Consumption by Contractor

D. Total Amount of Recyclables Taken to Wayne County Recycling Center

1. Cardboard

2. Scrap Metal

3. Other

E. Total Amount of C&D/Recyclables Taken/Sold to Other Recycling Points or

Reused On-Site

1. Cardboard

2. Scrap Metal

3. Other

4. Fill Material

F. Total Solid Waste Generated (A+B+C+D+E) (includes all material generated from the project)

G. % Diverted from Municipal Solid Waste Landfill ((C+D+E)/F) *100

This report must be submitted to the 4 CES project QAE monthly.

QAE: 1 copy; CEV 1 copy as distributed by QAE

9.

HAZARDOUS MaterialS/HAZARDOUS WASTES. The Contractor shall obtain approval from the Hazardous Material Management Program (HMMP) team prior to purchasing, handling, using, and storing any chemicals, solvents, lubricants, and other products for this contract that require an MSDS. The Contractor shall identify these materials on a Contractor Hazardous Material Authorization, Inventory, & Usage Form (AF Form 3952 – Contractor Equivalent). The Contractor shall provide this inventory list and one copy of the MSDS for each item to HAZMART for review and HMMP approval prior to any chemicals being brought onto Seymour Johnson AFB.

This Inventory & Usage Form will also be used by the Contractor to report hazardous material usage. At project completion, the contractor shall submit a final report (AF Form 3952 – Contractor Equivalent) to the Contracting Officer detailing overall project hazardous material usage.

For projects extending over 6 months in duration, the inventory (AF Form 3952 – Contractor Equivalent) shall be used to provide monthly usage reports to the Contracting Officer and a final report at project completion. The Contractor shall maintain one copy of the MSDS for each hazardous material line item used within the work center.

Contractor Hazardous Material Authorization, Inventory, and Usage Form (AF Form 3952 – Contractor Equivalent)

1. Prime Contractor/Organization:
2. PriMe Cont/POC

3. Phone

4. Fax

5. Date

2.
6. Prime CONT EMAIL
7. CONTRACT NUMBER
8. EXPECTED START DATE

9. EXPECTED END DATE

10. CONTRACTOR SIGNATURE

11. WORKPLACE/BLDG

12. SUB-CONTRACTOR

13. DELIVERY ORDER

14. CONTRACT ADMINISTRATOR

15. CONTRACTING ADMINISTRATOR SIGNATURE

16. PHONE

17. FAX

18. DATE

19. Government QAE/OPR

20. SIGNATURE

21. PHONE

22. FAX

23. DATE

24. PROJECT/TASK DESCRIPTION

25. Usage Reporting Schedule

FORMCHECKBOX

Contract Term FORMCHECKBOX Monthly ______________(month reported)

Product Name/Part Number
Manufacturer
Storage Location While On-base2
Physical Form (S,L,G)
Amount & Unit of Issue3
Container Type
Max Amount Onsite at any Time 4
Anticipated Amount Used for Project
Actual Amount Used During

Period5 Intended Use

FOOTNOTES: 1. This form is used for initial notification of hazardous materials intended for use on associated project and to report subsequent actual usage. Include all materials, which contain an EHS, TRI, CERCLA hazardous substance, toxic chemical, generates a hazardous waste after use, and/or requires a Material Safety Data Sheet.
2. Will temporary storage be established or kept in vehicles and taken off-base daily.

3. Identify amount in container & the units item is measured in, i.e. gallon, ounces, lbs, etc.

4. Identify maximum amount present (stored and used) at any one time on SJAFB.

5. Report actual quantities used. Quantities should reflect the reporting schedule identified in line 25.

END OF SECTION 01560