Text version
F2A3E15103A001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment to solicitation, FA4659-15-R-0008 Demo RAPCON B635 and B657, is to incorporate answ ers to questions, and to extend the proposal due date from 6 July 2015 to 10 July 2015.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 01-Jul-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA4659-15-R-0008
X 9B. DATED (SEE ITEM 11)
03-Jun-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
01-Jul-2015
CODE
319 CONTRACTING FLIGHT
575 TUSKEGEE AIRMEN BLVD
GRAND FORKS AFB ND 58205 6436
FA4659 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA4659-15-R-0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
SOLICITATION/CONTRACT FORM
The required response date/time has changed from 06-Jul-2015 02:30 PM to 10-Jul-2015 02:30 PM.
The following have been added by full text:
QUESTIONS AND ANSWERS
JFSD201509 Demo RAPCON 635 2nd Fire Station 637 FA4659-15-R-0008 Questions:
1. I did not see a Hazardous Materials Survey attached to this solicitation. Is there a survey for these buildings? If no survey has been performed, will one be required to be performed by the contractor and included in the proposal?
And if any hazardous materials identified, how will these conditions (lead, asbestos, etc.) be addressed?
See Specification Section024100 paragraph 3.1.1.
2. Regarding B657 – there appears to be an underground storage tank behind the building. Is this to be demolished with the structure? If so, is the tank to be considered clean? Is the depth known?
See Drawing 6 of 11. The tank is not identified for demolition and therefore is not part of this project.
3. Regarding B635 – Are the generator and fuel tank to be demolished as a portion of this demo? Same as above, if so what is the condition of the fuel tank?
See Specifications 01000 paragraph 2.1.1. “…remove associated utilities from these sites”; therefore, the contractor removes the generator and the fuel tank. This is a 1,000 gallon diesel fuel tank, approximately 6-feet x 12-feet x 4-feet, self-contained, above ground tank, with no evidence of leakage. High probability that the tank contains diesel fuel.
4. Regarding B635 – There is a hydrant between the building and parking lot, is this to be demolished?
See drawing 7. Do not demolish water line and hydrant as noted on drawings.
5. Regarding B635 – Are the light poles in the parking lot to be demolished?
See drawing 7. Contractor is to demolish electrical and associated light poles.
6. Regarding B635 – Are any of the trees or landscaping to be protected in the area immediately surrounding the building?
No, these trees and shrubs are so close to the facility that it is not feasible to attempt to protect them during the demolition.
7. Secondary Fire Station Building 657, can we install a temp fence along the flight line, to limit the access to the flight line. We would remove section of the current fence, this allow easy access to the building. Would limit the amount of line badges required and escorts required. Ease of access would help in lower the cost of this removal action.
No, the flightline fence shall not be compromised.
8. This question only applies to Radar Approach Control (RAPCON) facility, building 635. Assuming, that the building was constructed similar to other facilities own by USAF at other installations. This material is suspect
ACM. All outer walls have been cover by an interior wall the potential of having ACM due to contact transfer.
Asbestos Fireproofing - Asbestos-containing Spray-on or Slab (Tremolite) Fireproofing in buildings, this material was historically used in these types of buildings. We assume this coating is present on all four outer walls. Our question can we assume everything inside the building is ACM and dispose of the material as ACM; in lue of a
FA4659-15-R-0008
survey and very substantial remediation project. We believe the disposal of material will the more economical option for the GFAFB. We have contacted NDDOH and they have agree with our approach due present of the coatings. If GFAFB can provide asbestos survey on this building excluding this material. We believe this is the best option.
This question is addressed in the Statement of Work paragraphs 2.1.7., 4.3., and 13.6.5. of Section 01000 and the entirety of Section 01001.
(End of Summary of Changes)