Q&A.docx
DOCX document 14 KB Posted
- Attached to
- High Bay Lighting Federal contract opportunity
- Solicitation number
- FA4626-17-R-0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions_updated.docx | DOCX document | |
| New_Drawing_PDFs.zip | ZIP file | |
| Questions.docx | DOCX document | |
| SOW_High_Bay_Lighting_FY17.docx | DOCX document | |
| 01_00_00_General_Requirements_High_Bay.doc | DOC document | |
| Amendment_003.docx | DOCX document | |
| Photos.zip | ZIP file | |
| FA462617R0003U0002.pdf | ||
| Site_Visit.pdf | ||
| FA462617R0003U0001.pdf | ||
| 01_00_00_General_Requirements_High_Bay.doc | DOC document | |
| Q&A.docx | DOCX document | |
| Attach_2_Submittal_Schedule_High_Bay_Lighting.xls | XLS spreadsheet | |
| Attach_4_Drawings.zip | ZIP file | |
| Attach_7_Special_Contract_Requirements.docx | DOCX document | |
| Attach_3_Schedule_of_Drawings.doc | DOC document | |
| Attch_9_Subcontractor_Consent.doc | DOC document | |
| Attach_6_Installation_Perimeter_Access.pdf | ||
| Attch_8_Past_Performance_Questionaire.docx | DOCX document | |
| Attach_5_Wage_Determination.docx | DOCX document | |
| Attach_1_Specifications.zip | ZIP file | |
| FA462617R0003.docx | DOCX document |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Response to Questions FA4626-17-R-0003 High Bay Lighting
Q: Can you please clarify the date of the Site Visit? There are 2 different dates mentioned in the Solicitation, both April 18th at 10:00 am, and April 19th (pages 30 and 31).
A: The correct site visit date is 18 April at 10:00 am.
Q: I did not see the solicitation due date? Is it available yet? What do we need to do to visit the site? We plan to submit an "equal" for the metal halide fixtures. Do you need to pre-approve the equal? Is so what would you like us to provide. I see that there is no "Energy Efficient Requirement in section 3.23 required. Can you clarify how this relates to UFC specifications for the project?
A: 4 May 2017 is the due date. Yes it is available. If you do not have current contractor base passes, you will need to send us company information to be able to process you on base. Company information will include the company name, name of the individual, Social Security number, city and state, date of birth, and Driver License number. No a pre-approval for the equal is not needed. It can be submitted as a submittal after award. No UFC specifications are referenced in this project. The specified light fixture types were chosen based on initial cost, anticipated life span and ease of replacement, in addition to improved energy efficiency.
File details come from the government source that posted it. Updated .