- Repair Building 1840 Federal contract opportunity
- Solicitation number
- FA4626-15-R-0015
About this file
Updated questions with answers as of 3 Sept 2015
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4626-15-R-0015
Repair Building 1840 Submitted Questions – Answers As of 25 Aug 2015
1. I was looking into the proposal section of this project and had a question for you on section “3.2.3 FACTOR 2 – Offeror Experience/Management Plan”. How much does this sections come into awarding the project? If we don’t meet each of these sub-factors will our bid be rejected or are you using some sort of modifier?
There is no modifier used during the technical or past performance evaluation, offeror’s proposals MUST meet all specified requirements. Proposal must contain the information requested whether it is the prime or subcontractor who has the experience. If submitting on a subcontractor, that subcontractor must perform the work. If the proposal submitted (Prime or Subcontractor) does not meet the requirement, then the proposal is rated technically unacceptable and removed from further consideration for award.
2. SUBFACTOR 1: Do these projects have to be complete? It implies completed, but doesn’t specify. We only have completed 2 projects over $3.5 million in your specified time frame, but we are currently working on a $5.6 million here in town that could be number 3. We have done a number of larger projects just not in the specified time frame.
Projects that are "in progress" will count; the main catch is that they are at least 80 percent completed. Reference L-1-PPT; 4.0 Volume II Past Performance 4.3.
3. SUBFACTOR 2: Honestly we have zero of these projects. We have bid them in the past, but haven’t been the successful bidder. There also have not been many of these projects in Montana, and this will probably disqualify a couple Primes. On a side note as this project is largely subcontractor based wouldn’t it be more important if the subcontractor has this experience under Factor 1?
For Subfactor 2: It is important to submit the experience data on the company that will actually perform the work, be it prime or subcontractor.
4. Page 39 of 48, 3.0 Volume 1 – Technical Volume: For factors 1, 2, and subfactors, will affiliated company experience (parent company or sister company) experience be acceptable?
When reviewing experience being used for affiliated companies by a prime contractor submitting a proposal the main concern is "who" has the experience. If you plan on using those with the experience in the affiliated company to perform the work the experience is acceptable, however, if you are just using the affiliated company to show that the company "as a whole" has conducted work within the factor or sub-factor and have no plan to use those with the experience it is unacceptable. The main focus is that the actual company or individuals with the experience are being used to accomplish the requirement.
As of 27 Aug 2015
5. Blast door electric motors are called out to be replaced? Is this just the motor or all associated gears and actuators?
Only Motors are to be replaced
6. Will any new conduit be required to be painted to match existing wall covering?
No painting of conduit is required.
As of 31Aug 2015
7. Sheet E1.1, Detail 3. The pole being called out to use for new electrical already has 1 set of cut-outs on it. Is the intent to have two separate cross-arms and two separate cut-outs for new feed and existing feed?
All work will take place at the pole with the existing service entrance.
New work will take place at the pole where the existing service is fed.
--Install new riser on opposite side of the pole as the existing riser for the existing service to B-1840. Support the pole as necessary during excavation to install the sweep elbow that transitions from the underground to the riser.
--Install new crossarm/lightning arrestors/fused cut-outs assembly on opposite side of existing build.
--Install new crossarm on the opposite side of the existing pole for support of conductors and strain relief terminations.
--Make all connections from existing overhead distribution to cut-outs and service conductors to cut-outs.
--Remove existing jumpers, cut-outs, lightning arrestors, crossarms, and conductors. Cap existing riser.
AS of 3 Sept 2015
8. Are there any generals who have signed for disc that were not at pre-bid?
No
9. While addendum did address which pole to use for service, it did not address shutting down of line. This is a real safety issue and line should be de-energized for work and cut over.
Yes, line will be shut down to transfer service
10. Can you give depth of concrete at new electrical service underground line, new transformer vault, and line to new switchboard.
8" at new service underground line and new transformer vault. 6" at line to new switchboard.
11. On E1.1 note 2 tells use to use detail 7 for incoming line. This detail has 3- 4” conduits. Feeder schedule on E3.1 calls for 1-3”. Which is correct?
Neither is correct. Detail 7 on E1.1 and the feeder schedule on E3.1 should both show 2 - 4" conduits, 1 with conductors, 1 spare.
12. Training per 260500 3.5 A does not have to include the Electric Motors(267100) the Deluge Releasing System(28 31 00 1.8 A) and Interior Addressable Fire Alarm System(28 31 74 1.8 A) as they have their own training requirements, correct?
Training must be provided for all installed equipment.
13 260503 2.4 calls out Owner Furnished Equipment and Materials. If electrical items are supplied, will they be delivered to jobsite or must we pick up somewhere?
They would be delivered to the jobsite, if provided.
There is minimal, if any, government furnished equip/materials with this project.
14 Will 261200 3.5 11 be required?
Yes
15 260533 3.1 A. 4. Says that emt is allowed in dry indoor locations exposed. Existing conduit in bays looks all to be rmc. Is rmc required in bays or do we bid all with emt?
EMT is acceptable per the spec.
16 What is going to be required for shutting down the fire alarm system? To start we are going to need to shut down the fire alarm system in order to remove from areas we need to install the new work. In some areas the same holes thru the walls need to be reused. At the preconstruction meeting it was mentioned that it was known that the fire alarm system would need to be shut down for an extended period of time. Spec section 260563-2 – 3.3 note C says “contractor responsible to maintain and document 24 hour fire watch while fire system is down. Facilities never left unattended while fire system is down”. Are contractors going to be responsible for doing fire watch 24 hours a day while the fire alarm system is down? The contractor is not responsible for 24-hour fire watches in the facility.
This is the responsibility of the government.