Questions_and_Answers.docx
DOCX document 14 KB Posted
- Attached to
- BLDG 1440 ROOF MAFB, MT Federal contract opportunity
- Solicitation number
- FA4626-15-R-0009
About this file
Q A's- more to follow
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Additional_Q.docx | DOCX document | |
| q a's.docx | DOCX document | |
| Conformed_copy_of_1440_Roof_Repair.pdf | ||
| Amendment_2_Changes.pdf | ||
| Questions_and_Answers.docx | DOCX document | |
| Past_Performance_clarification.docx | DOCX document | |
| AMENDED_-_075323__-_ethylene-propylene-diene-monomer_(epdm)_roofing.pdf | ||
| Amendment_01.pdf | ||
| Pg-43.pdf | ||
| Pg-44.pdf | ||
| Pg-42.pdf | ||
| Meeting_mins_Roof_1440.pdf | ||
| Attach_5-WDOL.pdf | ||
| Attach_1-SPECS.pdf | ||
| Attach_7-_Past_Performance_Questionnaire.pdf | ||
| Attach_4-Schedule_of_Drawings_-_Bid_Doc_1440.pdf | ||
| Attach_6-_Base_Entry_Policy_Letter.pdf | ||
| Attach_2_-_Submittal_Schedule-Repair_Roof_Bldg_1440.pdf | ||
| FA4626-15-R-0009.pdf | ||
| Attach_3_-_Drawings.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
1. On the Roof Mechanical/Electrical Demolition Plan under the electrical work notes #7 it states “ disconnect and remove all lightning protection down conductors.” According to the elevation demolition drawings provided it notes that the existing wall panels are to remain. Please confirm that this is correct and they indeed want the existing exposed down leads removed. If they want the existing lightning protection system down leads removed who is removing this material? Would your customer like us to provide a pricing for the removal of the existing down leads along with the existing system on the roof or is a separate party removing this material?
2. With this being an existing building and I’m assuming the existing landscape around the building is complete with concrete/asphalt etc. Would they like us to tie in to the existing grounding from the old system or would they like us to include provisions to install a new grounding system ( ground ring, ground rods etc.).
Answer: No new lightning protection work is required for this project. Existing lightning protection system will be removed to the extent possible without removing the existing wall panels (in accordance with the demolition notes
3. Can the roofing be substituted with Duralap PVC roofing. This was used on the recent roof project Bldg. 500
Answer: No. The project has to be constructed, as designed, with an EPDM membrane.
4. Can the roof construction be phased into one section at a time?
Answer: Yes, up to the offeror.
5. Does the entire fence need to be constructed as shown in the plans?
Answer: No, fencing can be phased in coordination with the construction.