Submittal Schedule_Atch 2.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
RECOVERY-- NZAS051038 - Repair Substation Breakers Federal contract opportunity
Solicitation number
FA4626-09-R-0021
Issued by
Department of the Air Force Global Strike Command

About this file

Attachment 2 - Submittal Schedule

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY-- NZAS051038 - Repair Substation Breakers, newest first.
File Type Posted
Switchgear Measurements.pdf PDF
Additional Questions and Answers.docx DOCX document
Questions and Answers(2)_ 23 Jul 09.docx DOCX document
Q A's from the site visit.zip ZIP file
Wage Det_MT1_Atch 5_Revised.docx DOCX document
Amendment 0002.doc DOC document
09-R-0021 - Drawings - Amended.zip ZIP file
Amendment 0001.doc DOC document
Q and A's for Solicitation FA426-09-R-0021.docx DOCX document
Solicitation - FA4626-09-R-0021.doc DOC document
Wage Det_MT1_Atch 5.docx DOCX document
SCHEDULE OF DRAWINGS_Atch 3.docx DOCX document
Drawings_Atch 4.zip ZIP file
Specifications_Atch 1.zip ZIP file
Past Performance Survey_Atch 6.docx DOCX document
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIALS SUBMITTALSProject NumberProject Title:Solicitation/Contract No.
NZAS 05-1038Replace Substation BreakersFA4626-09-R-0021
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR
Number of Copies Required
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSNOTIFICATIONOTHERREQUIRED SUBMISSION DATE (BY CONTRACTOR)DATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDIS- APPROVED
1As Built Field Data 01000 3.54PTFA
2Operating and Maintenance Instructions 01000 3.74PTFA
3Contractor Furnished Equipment List 01000 3.84PTFA
4Shop Drawings 01000 3.9 as Required by Technical Specifications4PS
5Start of Work Notification 01000 3.101PTSW
6Notice of Final Inspection 01000 3.111PTFI
7Construction Near Utility Systems 01000 3.121PTSW
8Utility Outage Notices 01000 3.131PTO
9Submittals 01000 3.144PSS
10Quality Control Plan 01000 3.174PTSW
11Quality Control Records 01000 3.17.Q1EWD
121354 Checklist (Property Inventory Checklist) 01000 3.184PTFI
13Nuclear Densometers 01000 3.20.A4PTSW
14Asbestos Free Facility 01000 3.35.B4PTSW
15Identification of Employees 01001 1.1. A.4PTSW
16Environmental Protection 01360 Attachment - Waste Management Plan4ANTP
17Environmental Protection 01360 Attachment - Recovered Materials Written Determination Form4ANTP
18Environmental Protection 01360 Attachment - Recycled Material Use Form4ANTP
19Submittals 01732 1.5 Literature & Schedule of Demolition Activities4PTSW
20Earthwork 02300 1.4.A. Warning Tape4**10d PTSW
21Earthwork 02300 1.4.B. Material Test Report4**15d ANTP
22Chain Link Fences 02821 1.4.A. through D.444444**15d ANTP
23Cast-in-Place Concrete 03300, 1.3.B. Product Data & Instructions4444**15d ANTP
24Cast-in-Place Concrete 03300, 1.3.C. Product Samples1**15d ANTP
25Cast-in-Place Concrete 03300, 1.3.D. Mix Design4**21d PTSW
26Cast-in-Place Concrete 03300, 1.3.E. Test Results4**36 hours AWC
27Structural Steel 05120, 1.3.444**15d ANTP
28Cold Formed Metal Framing 05400, 1.3.A.444**15d ANTP
29Preformed Metal Siding and Roofing 07400, 1.344444444**15d ANTP
30Joint Sealants 07920, 1.344444444**15d ANTP
31Steel Doors and Frames, 08110, 1.2.A.44444*15d ANTP
32Overhead Coiling Doors, 08361, 1.5444444*15d ANTP
33Finish Hardware 08710, 1.44444*15d ANTP
34Painting 09900, 1.44444*15d ANTP
35Operation and Maintenace Manuals 15000, 1.18.B O&M's for all equipment2PTFP
36Fans 15820, 2.1 Shop Drawings44444**15d ANTP
37Ductwork and Accessories 15841, 1.6 Equipment Submittals444444**15d ANTP
38Basic Electrical Requirements 16050, 1.4.D. Seismic Restraint (Calculations at Government's Option)44444**15d ANTP
39Basic Electrical Requirements 16050, 3.2.K. Contractor Qualifications44**10d ANTP
40Raceways 16110, 2.444**15d ANTP
41Conductors (Under 600 Volts) 16120, 1.24**15d ANTP
42Conductors (Over 600 Volts) 16124, 1.244444**15d ANTP
43Boxes 16130, 1.34**15d ANTP
44Panelboards - 16160, 1.34444**15d ANTP
45Protective Relays 16295, 1.64444**15d ANTP
46Busways16340, 1.3.444444**15d ANTP
47Medium Voltage Switchgear 16345, 1.6.444444**15d ANTP
48Medium Voltage Switchgear 16345, 12 Extra Materials (spare fuses)1**15d ANTP
49Medium Voltage Load Interrupter Switchgear 16350, 1.5.444444**15d ANTP
50Medium Voltage Regulators 16355, 1.2.A - C.44444**15d ANTP
51Medium Voltage Regulators 16355, 1.2.D. Pentahead Sockets2**PTFA
5248 VDC Battery System 16360, 1.344444**15d ANTP
53Lighting Fixtures - 16500, 1.1.C & D.44**15d ANTP
Schedule of Abbreviations:
AWC= After Work CompletedEWD= Each work day AF Form 3000 not requiredPTFP=Prior to Final Payment
PTSW= Prior to Starting WorkPTFA= Prior to Final AcceptancePTCW=Prior to Completing Work
AFA= After Final AcceptanceBMF=Before Material DeliveryAFI=After Final Inspection
PTO= Prior to OutageSN=Advance NotificationPT=Prior To
PTNT= Prior to Notice to ProceedSRO=After Each OccurrencePSSPer Submittal Schedule
ANTP= After Notice to ProceedPTFI=Prior to Final Inspection
&"Times New Roman,Regular"&12Attachment 2&"Times New Roman,Regular"&12Replace Substation Breakers
NZAS 05-1038&"Times New Roman,Regular"&12FA4626-xx-R-xxxx

&"Times New Roman,Regular"&12AF Form 66 02:

&F-&D &"Times New Roman,Regular"&12 SS-&P

REQUIRED TECHNICAL SUBMITTALS