Q and A's for Solicitation FA426-09-R-0021.docx

DOCX document 12 KB Posted

Attached to
RECOVERY-- NZAS051038 - Repair Substation Breakers Federal contract opportunity
Solicitation number
FA4626-09-R-0021
Issued by
Department of the Air Force Global Strike Command

About this file

The attached are some questions and answers received by some contractors.

View the file

Other files for this federal contract opportunity

Other files attached to RECOVERY-- NZAS051038 - Repair Substation Breakers, newest first.
File Type Posted
Switchgear Measurements.pdf PDF
Additional Questions and Answers.docx DOCX document
Questions and Answers(2)_ 23 Jul 09.docx DOCX document
Q A's from the site visit.zip ZIP file
Wage Det_MT1_Atch 5_Revised.docx DOCX document
Amendment 0002.doc DOC document
09-R-0021 - Drawings - Amended.zip ZIP file
Amendment 0001.doc DOC document
SCHEDULE OF DRAWINGS_Atch 3.docx DOCX document
Drawings_Atch 4.zip ZIP file
Specifications_Atch 1.zip ZIP file
Solicitation - FA4626-09-R-0021.doc DOC document
Wage Det_MT1_Atch 5.docx DOCX document
Past Performance Survey_Atch 6.docx DOCX document
Submittal Schedule_Atch 2.xlsx XLSX spreadsheet
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers for Solicitation FA426-09-R-0021, Repair Substation Breakers

Q: Specific sheet note #3 indicates items shown with light line weights are existing, however, all lines appear to be the same density.

A: The line weights on the original drawings did not print correctly. An amended set of drawings, sheets 1 thru 27 have been prepared and will be posted via an amendment. This should clarify the line weights.

Q: In specification section 16435 Medium Voltage Switchgear, 2.1 Manufacturer, lists GE PowerVac switchgear, or equal. Please confirm that Square D/Schneider Electric will be an accepted substitute.

A: Square D/Schneider Electric is an acceptable manufacturer; however, it is up to the contractor to ensure that the product specified meets or exceeds the requirements of the specifications, i.e. “equal to the product specified”.

Q: It appears that this proposal is for two lineups of 15 kV switchgear interconnected via non-seg busway. These lineups are fed from two transformers that have no specifications.

A: Correct that the proposal is for two lineups interconnected via busway through a tie switch. The proposal shows no specifications for the transformers because they are existing to remain.

Q: The site plan E1.1 Specific Remodel Notes #1 indicates “New Building” to see E2.1 the electrical floor plan that shows partial equipment shown on the one-line on E3.1.

A: The site plan E1.1 indicates that there are two new rows of switchgear. The note refers to E2.1 to show the individual sections of the line-ups.

Q: Is the house part of the scope of this proposal? There are no housing specifications.

A: Yes, the house is part of the scope of work for the proposal. There are structural drawings for the building as well as specifications for the building materials in the proposal.

Q: There are existing conduit and entry points. Does our gear have to match the dimensions, conduit entry points and elevations shown on the front elevations E5.0 and E5.1?

A: The conduit entry points must be maintained otherwise new feeders would have to be installed and installation of new feeders is beyond the scope of this proposal.

Q: The RFP FA4626-09-R-0021 page 3 of 43 indicates nameplate information that is not listed on the one-lines. It is difficult for me to determine what I need to provide a quote on.

A: I believe the confusion is with the NSN that this number is generated by Contracting’s Procurement System. This is not name-plate data. The intent is to provide and install equipment per the drawings and specifications. This can be addressed further at the site visit.