STATEMENT OF WORK
FY 14 APPLY REJUVINATING COATINGS TO RUNNING TRACK
WHITEMAN AFB, MO
Purpose: Contractor shall clean, supply materials, and labor to apply spray rejuvenating coatings, (Advanced Polymer Technologies (APT), on base running track to renew surfaces.
1. Contactor shall clean surfaces to receive rejuvenating coatings per manufactures compliance.
2. Contractor shall apply three (3) lifts of 1 – 3 MM rubber bound with latex binder (APT). Allow applicable cure times between coatings per manufacturer’s compliance.
3. Contractor shall install two (2) coat blue polyurethane structural spray (APT) .
4. Contractor shall apply layout and repainting of all track markings (lines and symbols) as in its current configuration.
5. Contractor shall remove any waste or refuse generated by the project from the confines of Whiteman
AFB.
6. Contractor shall provide clean-up of all areas of project.
7. Contractor shall use coatings produced by Advanced Polymer Technology (APT) to guarantee bonding to substrate of existing track surfaces or be able to produce and supply proof of compatibility from selected coating manufacturer.
8. Contractor shall provide warranty documentation for a minimum of three (3) years for materials and installation labor.
9. POC for project: Brian L. Munley, 509 CES/CEOE, 660 687-3204, brian.munley@us.af.mil
Revised SOW 14 Aug 2014 mailto:brian.munley@us.af.mil