Attachment__2_SOW.pdf
PDF 100 KB Posted
- Attached to
- Resurface Base Running Track
- Solicitation number
- FA4625-14-R-0010
About this file
Statement of Work
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
RESURFACE RUNNING TRACK
WHITEMAN AFB, MO
Purpose: Contractor shall clean, supply materials, and labor to apply spray rejuvenating coatings, on base seven (7) lane running track to renew surfaces.
1. Contactor shall clean surfaces to receive rejuvenating coatings per manufactures compliance.
2. Contractor shall apply three (3) lifts of 1 – 3 MM rubber bound with latex binder. Allow applicable cure times between coatings per manufacturer’s compliance.
3. Contractor shall install one (1) coat blue polyurethane structural spray.
4. Contractor shall apply layout and repainting of all track markings (lines and symbols) as in its current configuration.
5. Contractor shall cordon area to ensure new surface is allowed to cure without interference
6. Contractor shall remove any waste or refuse generated by the project from the confines of
Whiteman AFB.
7. Contractor shall provide clean-up of all areas of project.
8. Contractor shall use coatings produced by Advanced Polymer Technology (APT) or equal to guarantee bonding to substrate of existing track surfaces or be able to produce and supply proof of compatibility from selected coating manufacturer.
9. Contractor shall provide warranty documentation for a minimum of one (1) year for materials and installation labor.
10. POC for project: Brian L. Munley, 509 CES/CEOE, 660 687-3204, brian.munley@us.af.mil mailto:brian.munley@us.af.mil
File details come from the government source that posted it. Updated .