SUMMARY OF CHANGES:

Questions and Answers

1. The user discussed them removing the foldaway bleachers and that the limits of the flooring demo and put back would stop flush with the front face of where the fold away bleachers currently sit. Please clarify if we are to price any removal or replacement section for the bleacher pocket sections?

A: Negative. The bleachers will be a part of a separate requirement. Flooring will be flush with the wall.

2. The existing gym area has 4” black rubber cove base. Will the existing base be left in place? Or removed and replaced with new?

A: The 4” black rubber cove base will be removed and replaced new.

3. It was discussed that the existing substrate gym floor rubberized epoxy (tan in color) would be left in place and we are only responsible to remove the un-adhered black rubber matting and gym flooring system and then apply the new flooring system on top of the old existing rubberized epoxy (tan in color).

A: The removal would be complete upon removing the rubberized layer. There is no need to take out the dry pack.

4. Are we bidding direct to you?

A: Per the solicitation instructions, please submit bids to “RFQ due date/time: 24 July 2020/ 1:00 P.M. PT. Please make sure all quotes remain valid through 30 Sep 2020.

Email to: Colton McDonald at colton.mcdonald@us.af.mil and Ms. Heather Rogers at heather.rogers.9@us.af.mil.”

5. Is / will there be a project GC?

A: The Company submitting the quote will be responsible for all material and work performed.

6. When can we receive 100% CD’s?

A: Please refer to Attachment A B2310 YC Sports Court Dimensions.

7. Is there a confirmed spec?

A: Please refer to the SOW for the minimum characteristics.

8. Will this project require dedicated Supervision and QC? If so can the Superintendent also be the QC or must they be two separate individuals?

A: This is a commodity with install. No QC or Superintendent required, although an onsite foreman will be expected to manage day to day activities.

9. Will the project require a bid guarantee to be provided with the proposal?

A: Bids shall indicate pricing is good until 30 September 2020.

10. Will the project require a payment and performance bond from the awarded General Contractor?

A: No bonds are required. Payment will be rendered after completion and Government Acceptance of the project.

11. Has an Asbestos Survey been completed on the flooring material requiring demolition?

A: Yes there has been an Asbestos Survey. Please see Attachment C.

11a If so, please provide a copy for review.

A: See Attachment C.

11b. If not, will one be required and if asbestos is encountered after award, this will be considered a differing site condition.

A: See Attachment C.

12. Is the rubber underlayment below the floor grid attached with adhesive or just layed in place?

A: The rubber underlay is set in place. There is no adhesive applied.

13. From the pictures provided, there appears to be a dry pack floor leveler under the rubberized underlayment. Would this also be removed or does removal stop once the rubberized underlayment has been removed?

A: The removal would be complete upon removing the rubberized layer. There is no need to take out the dry pack.

14. Does the project duration of 60 calendar days from NTP include the time to procure materials? It is assumed not, and the 60 calendar days is for construction only once material has been approved, ordered, and arrived.

A: There will not be Notice to proceed (NTP) issued. The period of performance to order materials, demolish, install new flooring and full completion is 60 days from After Date of Contract (ADC).

15. Is there is an incumbent contractor currently performing these services, if similar services have been performed in the past, or if this is a new requirement.

A: There is not an incumbent contractor currently performing these services. This is a new requirement and a stand-alone requirement.

16. If this is a follow-on requirement, could you please provide the previous contract or task order number?

A: There is not a follow-on requirement. This is a stand-alone requirement.

17. Is the Government able to accept offers from Small Businesses under NAICS code 339920, Sporting and Athletic Goods Manufacturing, standard employee size 750?

A: The solicitation specifies NAICS 238330. A potential vendor can always add the NAICS 238330 if they provide such services.

18. Is a vector or high resolution image file of the center court logo available?

A: See attachment D.

19. What size (height and width) should the center court logo be?

A: Approximately 24 feet wide and approximately 24 feet tall. The height will be determined by the width if the ratio of the logo is maintained.

20. What color does the Government prefer for the game lines?

A: We would like the basketball court lines to be blue (same color as the big “YP” in the logo), volleyball court white, and hopscotch and four square red.

21. Does the Government request vented cove base be installed at the edges where the new hardwood meets the walls?

A: See response two.

22. Does the Government require a bond guarantee?

A: No. Please see answer #10.

23. Is it acceptable for the period of performance to exceed 60 days?

A: No. The period of performance is set at 60 days.

24. Is the Davis-Bacon wage requirement applicable?

A: No, as this is a commodity with installation, not a construction project.

Added the following clause(s):

STANDARD COMMERCIAL WARRANTY

The Contractor shall extend to the Government the full coverage of any standard commercial warranty normally offered in a similar commercial sale, provided such warranty is available at no additional cost to the Government. Acceptance of the standard commercial warranty does not waive the Government’s rights under the “Inspection” clause nor does it limit the Government’s rights with regard to other terms and conditions of this contract. In the event of a conflict, the terms and conditions of the contract shall take precedence over the standard commercial warranty. The standard commercial warranty period shall begin upon final acceptance of the applicable material and/or services listed in the Schedule. The Contractor shall provide a copy of its standard commercial warranty (if applicable) with its offer. The warranty covers a period of months. (Offeror is to insert number)

(End of Clause)