MOUNTAIN CONSULTING SERVICES

9922 E Montgomery Drive; Suite 9 Spokane Valley, WA 99206 509-924-9236 509-924-2287

May 4, 2018

Mr. John Smith

Youth Programs

7 West Arnold Street

Fairchild AFB, WA 99011-9688

Project Number: 18-059.1

Mr. Smith, Mountain Consulting Services is pleased to provide the enclosed report for the limited asbestos containing materials survey conducted for the suspect interior building materials present within the Gym Area of Building 2310 (Youth Center) located on Fairchild AFB, Washington.

Mr. Todd A. Lewis, EPA-AHERA Building Inspector, certification: BIR20170915-07, expiration:

9-15-2018 conducted a limited field survey for this project on April 19th of 2018.

The following tested building materials were proven free of Asbestos Content:

Gray Concrete on Gym Wall Black Pad Under Gym Floor

Tan Rubber Pad

Off White Mastic with VCB

Black Vinyl Cove Base

Yellow/ Black Plastic Tile (Gym Floor)

The report must be kept on site during renovation activities for worker and regulatory review.

Thank you for choosing Mountain Consulting for these services. If you have any questions, or require any clarification concerning this report, please call me at (509) 924-9236. It was a pleasure working with you, and we look forward to working with you again in the future.

Sincerely, Mountain Consulting Services

Todd A. Lewis

AHERA Building Inspector tlewis@mountainconsultingllc.com mailto:tlewis@mountainconsultingllc.com

LIMITED ASBESTOS MATERIALS SURVEY

FOR THE INTERIOR BUILDING MATERIALS

PRESENT WITHIN THE GYM AREA

OF BUILDING 2310 (YOUTH CENTER) LOCATED ON

FAIRCHILD AFB, WASHINGTON

Prepared for:

Youth Programs

7 West Arnold Street

Fairchild AFB, WA 99011-9688

509-247-5601

Prepared by:

Mountain Consulting Services

9922 E Montgomery Drive, Suite 9

Spokane Valley, WA 99206

509-924-9236

May 4, 2018

MOUNTAIN CONSULTING SERVICES

May 4, 2018 Mountain Consulting Services

CONTENTS

1.0 INTRODUCTION

2.0 SCOPE OF WORK

3.0 ASSESSMENT SURVEY PARAMETERS

3.1 Homogeneous Areas

3.2 Bulk Sampling

3.3 Laboratory and Analytical Methods

4.0 RESULTS

4.1 Material Containing 1% or More Asbestos

4.2 Materials Assumed to Contain Asbestos

4.3 Materials with Asbestos Concentrations of Less than <1%

4.4 Non-ACM Materials

5.0 CONCLUSIONS AND RECOMMENDATIONS

5.1 Conclusions

5.2 Recommendations

6.0 LIMITING CONDITIONS AND CLOSURE

6.1 Limiting Conditions

6.2 Closure

APPENDICES

A Certification and Accreditation

B Bulk Asbestos Materials Analysis Report

C Bulk Sampling Locations Drawing

& Site Photographs

PROJECT NO: 18-059.1

L-ACM SURVEY

May 4, 2018 PAGE 1 Mountain Consulting Services

LIMITED ACM SURVEY; BUILDING MATERIALS; GYM AREA;

BUILDING 2310; YOUTH CENTER; FAFB, WA

1.0 INTRODUCTION

Mr. John Smith, of the Youth Programs of Fairchild AFB, contracted Mountain Consulting Services

(Mountain Consulting) to conduct limited asbestos containing materials survey for the suspect interior building materials present within the Gym area of Building 2310 (Youth Center) located on

Fairchild AFB, Washington.

Mr. Todd A. Lewis; EPA-accredited AHERA building inspector, certification: BIR20170915-07 expiration: 9/15/2018 conducted a limited field survey of the identified building materials on April

19th of 2018. [Refer to Appendix A for inspector certifications & laboratory accreditations].

SITE DESCRIPTION

The building included for this project is located within the north-central main building corridor area of Fairchild Air Force Base. The structure resides on the corner of Doolittle Avenue and Castle

Street. The suspect materials to be impacted for this project were identified by Mr. John Smith of the Youth Program.

For this survey project Building 2310 (Youth Center) will undergo select renovations work that will include the replacement of the Gym flooring and basketball hoops renovation work.

Fairchild AFB is located west of the City of Airway Heights, Washington in Spokane County. The

Air Force Base is bordered by Highway 2 to the north, Rambo Road to the east, Medical Lake Road to the south, and Graham Road to the west.

2.0 SCOPE OF WORK

The scope of work was designed to meet the requirements for asbestos inspection and due diligence notification in the Occupational Safety and Health Administration (OSHA) Asbestos Standard (29

CFR 1926.1101), the National Emission Standards for Hazardous Air Pollutants (NESHAP; 40 CFR

61), and applicable portions of the Asbestos Hazardous Emergency Response Act (AHERA) and regulations in 40 CFR 763.

The survey was conducted through visual evaluation, classification and analysis of suspected asbestos-containing materials (ACMs) used in the construction or remodeling of the surveyed interior area of the building. The survey included the following tasks:

Visual survey and assessment of the location and condition of suspected materials.

Collection and analysis of bulk samples from suspected asbestos containing materials.

Preparation of a report summarizing the identification and assessment of any asbestos containing materials and material found not to contain asbestos.

May 4, 2018 PAGE 2 Mountain Consulting Services

3.0 ASSESSMENT SURVEY PARAMETERS

3.1 HOMOGENEOUS MATERIALS

Homogeneous materials are those considered to be consistent throughout an area based on color, texture, and construction era. For the purpose of this survey, homogeneous materials were delineated using the construction era, material composition, and material location as the primary considerations. Material appearance, texture, size, color, and analytical results may support assumptions about each material’s homogeneity.

3.2 BULK SAMPLING

Suspected ACMs were collected according to guidelines in 40 CFR 763.85 and were sampled to determine the type and percentage of asbestos by volume. At least Two (2) Samples were collected from each selected miscellaneous material type; at least Three (3) Samples from each thermal system insulation (TSI) materials; and suspect surfacing materials were sampled according to the AHERA

“3/5/7 rule” for spray or trowel applied materials.

For other types of suspect materials, or materials assumed to be non-ACM, regulations require the on-site AHERA building inspector to determine the appropriate number of samples. The quantity of material present, manufacturer’s labels, appearance, construction or renovation era, and inspector’s expertise were used to determine the number of samples.

A homogeneous material is considered to be a Regulated ACM if one or more sample results produce greater than 1% asbestos. The EPA recommends that at least three samples be analyzed by polarized-light microscopy (PLM) for the following types of materials in order to prevent false negative results (less then <1% asbestos):

Materials that contain low concentrations of asbestos fibers (less than 10%);

Materials with asbestos fibers tightly bound in a matrix;

Materials with milled asbestos fibers (fine fibers);

Materials with hand-mixed asbestos fibers; and

Materials with a combination of these characteristics.

All bulk samples must have results below 1% asbestos before the material may be classified in accordance with AHERA rule as not being Regulated ACM. If asbestos is detected in the material at less than <1%, WISHA worker health and safety due diligence regulations still apply.

3.3 LABORATORY AND ANALYTICAL METHODS

BULK ASBESTOS MATERIALS

Mountain Consulting collected and submitted for analysis Ten (10) bulk asbestos material samples collected from Five (5) different homogeneous suspect miscellaneous building materials targeted for testing.

May 4, 2018 PAGE 3 Mountain Consulting Services

The asbestos samples were submitted for analysis to Mountain Laboratories of Spokane Valley, Washington using proper chain of custody procedures. During analysis, one (1) submitted sample was sub-divided, resulting in a total of eleven (11) samples analyzed for this project.

The samples were submitted for analysis to Mountain Laboratories of Spokane Valley, Washington using chain of custody procedures. Mountain Laboratories participates in the national voluntary laboratory accreditation program (NAVLAP) and is a NAVLAP accredited asbestos testing laboratory, NAVLAP code: 101890-0.

All samples were analyzed to determine asbestos type and content using PLM with dispersion staining in accordance with the following methods:

EPA EPA 623/R-93/116, “Method for the Determination of Asbestos in Bulk Building

Materials” (July 1993).

EPA “Interim Method for the Determination of Asbestos in Bulk Insulation Samples”

(40 CFR Part 763, Subpart F, Appendix A; May 27, 1982).

ASTM Draft “Standard Method of Testing for Asbestos Containing Materials by Polarized

Light Microscopy” (ASTM Committee D22.05; January 14, 1988).

4.0 RESULTS

This section describes the results of bulk testing for the suspect asbestos materials include with this project. [Refer to the bulk sample analysis report located in Appendix B for asbestos materials testing results; and, Appendix C for the analysis report associated with lead coatings testing results].

4.1 MATERIAL CONTAINING 1% OR MORE ASBESTOS

ACMs are materials proven to contain at least 1% asbestos or greater. AHERA and NESHAP regulations distinguish between friable and non-friable forms of ACM. A friable material is defined as one that can be “crumbled, pulverized, or reduced to powder by hand pressure when dry.”

Friability is an indication of a material’s ability to release asbestos fibers into the air. Regulated

ACMs are defined by NESHAP as all friable ACM and non-friable ACM that may be disturbed by renovation or demolition.

All sampled suspect interior building materials included for asbestos content testing for this project were proven to be ACM-Free; Refer to Section 4.4 for a list of materials tested.

4.2 MATERIALS ASSUMED TO CONTAIN ASBESTOS

No suspect materials were assumed to contain asbestos during this survey activity.

May 4, 2018 PAGE 4 Mountain Consulting Services

4.3 MATERIALS WITH ASBESTOS CONCENTRATIONS OF LESS THAN <1%

No analyzed materials were proven to contain less than 1 percent (<1%) asbestos during this survey activity.

4.4 NON-ACM MATERIALS

Microscopic examination of samples collected from the following suspect building materials in support of the Building 2310, did not detect the presence of asbestos minerals (ACM-Free):

Gray Concrete on the Gym Walls (samples 01 & 02)

Black Pad under the Plastic Tiles of the Gym (samples 03 & 04)

Tan Rubber Pad on the Concrete Slab Foundation (samples 05 & 06)

Black Vinyl Cove Base with White Mastic in Gym (samples 07 & 08)

Yellow Plastic Tile for the Gym Floor (samples 09 & 10)

Black Layer Associated with the Yellow Plastic Tile on Gym Floor (sub-sample 10A)

5.0 CONCLUSIONS AND RECOMMENDATIONS

Our findings are based strictly on information obtained from our site observations and from sample analysis during survey activities. Consistent with our knowledge and understanding of environmental regulations, particularly as they apply to the potential liabilities associated with asbestos-containing building materials, we present the following conclusions and recommendations.

5.1 CONCLUSIONS

The tested and analyzed building materials proven to be free of asbestos require no further action in regards to asbestos regulations. These materials may be impacted without any specialized personnel training and disposed of in a landfill that accepts standard construction debris.

5.2 RECOMMENDATIONS

If any materials not identified in this survey are uncovered during renovation or demolition, they must be assumed to contain regulated amounts of asbestos until sampling and analysis prove otherwise. ACM must be handled in accordance with OSHA, NESHAP, and local regulations.

The Spokane Regional Clean Air Agency (SRCAA), the local building department and the local fire department should be contacted regarding possible permit requirements.

May 4, 2018 PAGE 5 Mountain Consulting Services

6.0 LIMITING CONDITIONS AND CLOSURE

6.1 LIMITING CONDITIONS

We have exercised reasonable efforts to accomplish the tasks for this project using current professional standards of the industry. To the extent that the services require subjective judgment, there can be no assurance that definitive or desired results have been obtained or that they will be usable. Although based on scientific principles, to the extent that results depend on subjective judgment, they are subject to human error.

The suspect building materials to be impacted during the scheduled renovation project were identified by the Youth Program representative.

Only the specific materials within the building areas identified in this report are covered by the conclusions presented.

6.2 CLOSURE

The results, conclusions, and recommendations in this report were prepared following our inspection of suspected ACM at the subject property. Methods used by Mountain Consulting for this study are consistent with the standard of care and professionalism normally exercised by consultants in environmental science and engineering. The Client acknowledges that Mountain Consulting has been retained for the sole purpose of assisting the Client to identify ACM, if any, associated with the subject structure.

It is agreed that Mountain Consulting has assumed responsibility only for performing this inspection, limited to the identified areas and presenting this report and conclusions to the Client.

The Client acknowledges that Mountain Consulting is not acting as an “agent” for the Client, or any other user or entity, for work associated with any asbestos-containing materials.

This report was prepared for the exclusive use of the Youth Program of Fairchild Air Force Base, Washington and/or representatives thereof. It may only be reproduced in full and with written approval of Mountain Consulting and is not warranted if any portion of it is separated from the original complete document.

May 4, 2018 PAGE 6 Mountain Consulting Services

STATEMENT OF PROFESSIONALISM

Mountain Consulting Services hereby certifies that the limited asbestos containing materials survey conducted for the suspect interior building materials present within the Gym area of Building

2310 located on Fairchild AFB, Washington, was conducted under modified protocols of 40 CFR

763.85. All policies and procedures described in 40 CFR 763 have been followed. All work and statements contained herein are certified true and correct to the best of Mountain Consulting’s ability.

Inspector: __________________________________ Date: May 4, 2018

Todd A. Lewis

AHERA Building Inspector

Certification: BIR20170915-07

Expiration: September 15, 2018

APPENDIX A

CERTIFICATION AND ACCREDITATION

APPENDIX B

BULK ASBESTOS MATERIALS

ANALYSIS REPORT

9922 East Montgomery Suite 13 NVLAP LAB CODE 101890-0

(509) 922-1365 ● Fax (509) 922-1380

Polarized Light Microscopy, NVLAP Accreditation

May 3, 2018

Mountain Consulting Services, LLC Project: FAFB Building 2310

Todd Lewis Project #: 18-059.1

9922 E. Montgomery Avenue, Suite 9

Dear Mr. Lewis, The enclosed report details results for the analysis of the bulk sample(s) submitted to Mountain

Laboratories on April 19, 2018. Sample analysis was performed to determine asbestos type and content using Polarized Light Microscopy, supplemented by Dispersion Staining (PLM/DS).

This report includes a summary of the analytical results and chain of custody. Analytical results are only reflective of the samples, which were tested and presented in this report. Mountain Laboratories limits warranty to proper analysis methods and takes no responsibility for sample procurement.

It has been our pleasure providing you with these analytical services. If you have any questions regarding this report, please do not hesitate to call us at (509) 922-1365.

Sincerely, Heidi L. McCarthy

Laboratory Manager

Mountain Laboratories

Mountain Laboratories NW, Inc.

Enclosure: 1023.14233.14342

MOUNTAIN LABORATORIES

BULK SAMPLE ANALYSIS FOR ASBESTOS

Test Method: EPA-600/R-93/116: Interim Method for the Determination of Asbestos in Bulk Building Materials. Customer #: 1023

Laboratory No. B18-14233 B18-14234 B18-14235

Sample ID No. 18-059.1-01 18-059.1-02 18-059.1-03

Sample Description Concrete Concrete Pad

Sample Treatment Teased/Crushed

Heated

Teased/Crushed

Heated Teased/Heated

Homogeneous No No Yes

Layered Yes Yes No

Fibrous No No No

Sample Color Black/Gray Black/Gray Black/Green/Brown

Yellow/Orange

Asbestos Present No No No

Asbestos Type and

Percentage

1. Chrysotile

2. Amosite

3. Crocidolite

4. Other

Concrete N.D.

Black Layer N.D.

Concrete N.D.

N.D.

Total % Asbestos None None None

Other Fibrous Material

In Sample

Non-Fibrous Material:

Concrete:

Other 100%

Black Layer:

Quartz 65%

Other 35%

Concrete:

Quartz 65%

Other 35%

Date Analyzed: May 3, 2018 Analyzed By: Lisa Meade

Mountain Laboratories, Mountain Laboratories NW, Inc. limits warranty to proper analysis methods only and takes no responsibility for sample procurement. Mountain Laboratories, Mountain

Laboratories NW, Inc., 9922 E. Montgomery Suite #13, Spokane Washington 99206 (509) 922-1365 - Fax (509) 922-1380. PLM has been known to miss asbestos in a small percentage of samples. Thus negative or <1% PLM results should be tested with either SEM or TEM. Customer is responsible for sample separation. This report may only be reproduced in full with written approval by Mountain Laboratories. Soil/Dust samples are not covered under NVLAP Accreditation.

Sample results must not be used by the customer to claim product certification, approval, or endorsement by NVLAP, NIST, or any agency of the Federal Government.

Test Method: EPA-600/R-93/116: Interim Method for the Determination of Asbestos in Bulk Building Materials. Customer #: 1023

Laboratory No. B18-14236 B18-14237 B18-14238

Sample ID No. 18-059.1-04 18-059.1-05 18-059.1-06

Sample Description Pad Rubber Pad Rubber Pad

Sample Treatment Teased/Heated Teased/Heated Teased/Heated

Homogeneous Yes Yes Yes

Layered No No No

Fibrous No No No

Sample Color Black/Green/Brown

Yellow/Orange Tan Tan

Asbestos Present No No No

Asbestos Type and

Percentage

1. Chrysotile

2. Amosite

3. Crocidolite

4. Other

N.D. N.D. N.D.

Total % Asbestos None None None

Non-Fibrous Material: Other 100% Other 100% Other 100%

Mountain Laboratories, Mountain Laboratories NW, Inc. limits warranty to proper analysis methods only and takes no responsibility for sample procurement. Mountain Laboratories, Mountain

Laboratories NW, Inc., 9922 E. Montgomery Suite #13, Spokane Washington 99206 (509) 922-1365 - Fax (509) 922-1380. PLM has been known to miss asbestos in a small percentage of samples. Thus negative or <1% PLM results should be tested with either SEM or TEM. Customer is responsible for sample separation. This report may only be reproduced in full with written

Sample results must not be used by the customer to claim product certification, approval, or endorsement by NVLAP, NIST, or any agency of the Federal Government.

Test Method: EPA-600/R-93/116: Interim Method for the Determination of Asbestos in Bulk Building Materials. Customer #: 1023

Laboratory No. B18-14239 B18-14240 B18-14241

Sample ID No. 18-059.1-07 18-059.1-08 18-059.1-09

Sample Description VCB w/ADH VCB w/ADH Plastic Tile

Sample Treatment Teased/Heated Teased/Heated Teased/Heated

Homogeneous No No No

Layered Yes Yes Yes

Fibrous No No No

Sample Color Black/Off White Black/Off White Yellow/Black

Asbestos Present No No No

Asbestos Type and

Percentage

1. Chrysotile

2. Amosite

3. Crocidolite

Cove Base N.D.

Off White Mastic N.D.

Cove Base N.D.

Off White Mastic N.D.

Yellow Layer N.D.

Total % Asbestos None None None

Cove Base:

Binder/Filler 30%

Vinyl 70%

Off White Mastic:

Cove Base:

Binder/Filler 30%

Vinyl 70%

Off White Mastic:

Yellow Layer:

Mountain Laboratories, Mountain Laboratories NW, Inc. limits warranty to proper analysis methods only and takes no responsibility for sample procurement. Mountain Laboratories, Mountain

Laboratories NW, Inc., 9922 E. Montgomery Suite #13, Spokane Washington 99206 (509) 922-1365 - Fax (509) 922-1380. PLM has been known to miss asbestos in a small percentage of samples. Thus negative or <1% PLM results should be tested with either SEM or TEM. Customer is responsible for sample separation. This report may only be reproduced in full with written

Sample results must not be used by the customer to claim product certification, approval, or endorsement by NVLAP, NIST, or any agency of the Federal Government.

Test Method: EPA-600/R-93/116: Interim Method for the Determination of Asbestos in Bulk Building Materials. Customer #: 1023

Laboratory No. B18-14242 B18-16209

Sample ID No. 18-059.1-10 18-059.1-10-A

Sample Description Plastic Tile

Sub Sample of

18-059.1-10

Black Layer

Sample Treatment Teased/Heated Teased/Heated

Homogeneous No Yes

Layered Yes No

Fibrous No No

Sample Color Yellow/Gray/Clear Black

Asbestos Present No No

Asbestos Type and

Percentage

1. Chrysotile

2. Amosite

3. Crocidolite

Yellow Layer N.D.

Clear Mastic N.D.

N.D.

Total % Asbestos None None

Yellow Layer:

Binder/Filler 30%

Vinyl 69%

Other <1%

Clear Mastic:

Mountain Laboratories, Mountain Laboratories NW, Inc. limits warranty to proper analysis methods only and takes no responsibility for sample procurement. Mountain Laboratories, Mountain

Laboratories NW, Inc., 9922 E. Montgomery Suite #13, Spokane Washington 99206 (509) 922-1365 - Fax (509) 922-1380. PLM has been known to miss asbestos in a small percentage of samples. Thus negative or <1% PLM results should be tested with either SEM or TEM. Customer is responsible for sample separation. This report may only be reproduced in full with written

Sample results must not be used by the customer to claim product certification, approval, or endorsement by NVLAP, NIST, or any agency of the Federal Government.

APPENDIX C

SAMPLING LOCATIONS DRAWING

& SITE PHOTOGRAPHS

THE GYM AREA OF BUILDING 2310 LOCATED

ON FAIRCHILD AIR FORCE BASE IN AIRWAY

HEIGHTS, WASHINGTON

THE GRAY CONCRETE OF THE GYM AREA OF

BUILDING 2310 LOCATED ON FAIRCHILD AIR

FORCE BASE IN AIRWAY HEIGHTS,

WASHINGTON

18-059.1 FAFB 2310-LACM Report
Todd's Certs 2018
18-059.1 FAFB 2310-LACM Report
Lab Results
18-059.1 FAFB 2310-LACM Report
CAD Drawing
Photos