Statement of Work (SOW)

REMOVE GYM FLOORING AND INSTALL NEW ONE

BLDG 2310, SCHOOL AGE PROGRAM AND YOUTH SPORTS FACILITY FAIRCHILD

AFB, WA

23 June 2020

1. DESCRIPTION OF SERVICES: Contractor shall provide all labor, materials, and tools necessary to remove and dispose of the existing floor, and install a new, water resistant floor with associated door thresholds and/or transitions at the Youth Center Gymnasium located at Building 2310, 200 West Castle St., Fairchild AFB, WA.

2. SCOPE OF WORK: The contractor shall complete all work, which includes furnishing all supervision, labor, material, equipment, and service, unless specified herein, required under this contract and per 2018 Base Design Standards (BDS). All work shall be performed in accordance with all Federal, State, local laws and regulations, manufacturer’s recommendations and this SOW.

- The Contractor shall provide a gym floor with the minimum following characteristics:

• Approximately 61 feet by 96 feet (Government-furnished information is not guaranteed to represent actual conditions, therefor contractors are responsible for field verification during pre-proposal site visit)

• Solid Maple Hardwood

• Sanded, cleaned, and sealed appropriately

• Game Lines: (1) Basketball court, (1) Volleyball Court, (1) Four Square Court,

(1) Hopscotch Court

• Logo (Blue/Grey) picture provided below

• Below Logo: (13) Letters - Youth Programs - (in red) (16) Letters - Air Force

Services - (in grey)

• Fit court to adjust to 6 doors and remove, replace, or provide with associated thresholds and/or transitions

3. GOVERNMENT FURNISHED PROPERTY AND SERVICES: The government will provide access to utilities as needed.

4. GENERAL INFORMATION

4.1 HOURS OF OPERATION: Hours of operation are 0600-1800 Monday through Friday, excluding Federal Holidays and any other designated down day. Work can be done at other than the normal hours of operation with the written approval of the Contracting Officer. The contractor shall coordinate in advance all hours of work and any service interruptions with Civil Engineering points of contact.

January 1 New Year’s Day

3rd Monday in January Martin Luther King, Jr. Day 3rd Monday in February President’s Day Last Monday in May Memorial Day July 4 Independence Day 1st Monday in September Labor Day 2nd Monday in October Columbus Day November 11 Veterans Day 4th Thursday in November Thanksgiving Day December 25 Christmas

FA462020QA332

Attachment 1 SOW

4.2. SECURITY REQUIREMENTS: All personnel employed by the Contractor in the performance of this contract, or any representative of the Contractor entering the government installation, shall abide by all Fairchild Air Force Base security regulations.

4.3. CONTINUATION OF MISSION ESSENTIAL FUNCTIONS: IAW DoDI 1100.22 (Policy and Procedures for Determining Workforce Mix), and any applicable Air Force implementation, unless otherwise directed by an authorized Government representative, it is determined that installation services provided under this contract are not mission essential for performance during a crisis.

5. PERFORMANCE PERIOD: Project shall not exceed 60 days after contract award.

6. ATTACHMENTS:

A. B2310 Youth Center Sports Court Dimensions B. 2018 FAFB Base Design Standards

Logo:

Four Square:

Hopscotch:

Floor Layers:

23 June 2020