This document is a solicitation amendment for replacing automated temperature controls at Building 116 on Dover Air Force Base. The contractor shall provide all labor, materials, tools and equipment to upgrade the facility HVAC control system panels and components supporting air handling units, duct heaters, heating and chilled water systems, power monitoring systems, unit heaters and cabinet unit heaters. Improvements are intended to increase the HVAC direct digital control system functionality, reliability and serviceability for this mission-critical facility. The amendment changes the evaluation factors to use the Lowest Price Technically Acceptable process and modifies the experience subfactor by removing the summary of technical qualifications requirement. Offerors must submit responses by June 5, 2020 to the Department of the Air Force Air Mobility Command for consideration.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B116 QA_Responses Part 2 20200611.pdf | ||
| B116 QA_Responses 20200524.pdf | ||
| Atch 5 - DAFB Standard Specifications.pdf | ||
| Solicitation - FA449720R0017.pdf | ||
| Atch 4 - DAFB Local Design Guide (9 Apr 18).pdf | ||
| Atch 3 - Wage Determination Building 20200103.pdf | ||
| Atch 2 - Bid Schedule - B116 Rpl Auto Temp Ctrls.xls | XLS spreadsheet | |
| Atch 6 - Operational Climatic Data.pdf | ||
| Atch 7 - Brand Name Trane SC JA 20200512.pdf | ||
| Atch 1 - SOW - Repair B116 Replace HVAC Controls.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section B - Supplies or Services & Prices or Costs
The following CLIN(s) / SLIN(s) were modified:
0001 - Includes all Design and Construction work required to replace B116 HVAC controls and VAV terminal units IAW SOW.
INFORMATION FROM TO
CIN 00000000000005193550
Section M - Evaluation Factors for Award
Miscellaneous text in this section has been modified to:
1. This is a competitive selection in which competing offerors will be evaluated using the Lowest Price Technically Acceptable (LPTA) evaluation process. The Government expects to award one firm-fixed price requirements contract as a result of this solicitation. The Government will make an award to the responsible (in accordance with [IAW] the Federal Acquisition Regulation [FAR]) contractor whose offer conforms to the solicitation and is determined to be the best value to the Government considering price and technical factors.
The solicitation requirements include all stated terms, conditions, representations, certifications, and other information required by 52.215-1 of this solicitation.
Factor I - Price The Government will evaluate offers based on prices proposed and technical factors required by the solicitation.
The offeror's proposal will be evaluated for price reasonableness. The lowest priced proposal will be considered and reviewed for technical acceptability. If the proposal is not technically acceptable, the next lowest proposal will be reviewed for technical acceptability until the Government has determined a proposal to be technically acceptable. Reasonableness: The existence of adequate price competition is expected to support a determination of reasonableness. If adequate price competition is not obtained or if price reasonableness cannot be determined other techniques will be used.
Factor II - Technical The following ratings will be used in rating technical capability:
Acceptable: Proposed meets the requirements of the solicitation Unacceptable: Proposed does not meet the requirements of the solicitation
Beginning with the lowest price proposal, technical acceptability will be evaluated. If the lowest priced proposal is determined to be technically acceptable, that offer will represent the best value to the Government and the evaluation process will stop. If the lowest priced proposal is determined to be technically unacceptable, the Government will proceed to the next lowest offer and evaluate technical acceptability. This evaluation process will continue until a proposal is determined to be technically acceptable. The following technical subfactors will be evaluated. If all of the following subfactors are not submitted, the proposal shall be determined non-responsive and removed from consideration. The contractor at a minimum shall meet the following technical requirements identified below in accordance with the Statement of Work:
Subfactor 1 - Work Plan: The offeror must provide a basic work plan that demonstrates a realistic approach to the accomplishment of the work. This plan cannot exceed four pages and must address the following:
FA449720R00170001
a. Timeline identifying critical path for project construction completion within the contract performance period.
b. Performance statement identifying the plan of action and scope as it relates to the requirements and limitations described in the statement of work.
Subfactor 2 - Experience: The offeror must submit a description of its capability to complete a project of this size and scope. This description cannot exceed two pages and must address the following:
a. History of the offeror's construction experience, with emphasis on projects of similar scope and scale to the requirements in the Statement of Work. Provide point of contact information for each project listed.
Subfactor 3 - Quality Control: The offeror must submit a narrative description of its quality control procedures.
This narrative cannot exceed two pages and must address the following:
A description of internal review procedures that facilitate quality standards and the identification of individuals responsible for ensuring quality control. All Unified Facilities Guide Specification (UFGS) specified contractor quality control requirements must be satisfied.
FA449720R00170001
| IDCode: |
| Page: 1 |
| Pages: 3 |
| AmendNo: 0001 |
| EffDate: 6/5/2020 |
| ReqNo: F1Q3FQ0031A002 |
| ProjNo: 1076655 |
| IssCode: FA4497 |
| AdmCode: |
| IssuedBy: FA4497 436 CONS LGC |
639 ATLANTIC ST BLDG 639
CP 302 677 5068
DOVER AFB, DE 19902-5639
United States Brittney Santiago, Email: brittney.santiago@us.af.mil Telephone: 3026775210
| AdminBy: |
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: FA449720R0017 |
| SolDate: 5/13/2020 |
| AwardChg: |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: See Section G |
| ChgeOrd: |
| ChgeOrder: |
| Modify: |
| SuppAgre: |
| SuppAuth: |
| ModOthr: |
| OthrSpec: |
| NoReq: 1 |
| Require: |
| Copies: |
| Descript: The purpose of this amendment is: 1. Change Section M- Evaluation Factors for Award, Technical Subfactor 2, Experience to the following: Delete Subfactor 2b: Summary of the offeror's technical qualifications or certifications associated with the requirements outlined in the Statement of Work. |
| ContNameTitle: |
| CoNameTitle: Contracting Officer |
Email: juan.roman.1@us.af.mil Telephone: 3026775233
| ContDate: |
| CODate: |