This memorandum provides clarification questions and answers for solicitation number FA449720R0017 to replace automated temperature controls at Building B116. The contractor shall upgrade HVAC control system panels and components supporting air handling units, duct heaters, heating hot water, chilled water, power monitoring, unit heaters, and cabinet unit heaters. Improvements aim to increase DDC system functionality, reliability, and serviceability for this critical facility. Testing and balancing of air and water is not required, as control and VAV replacements should be equivalent. The contractor must ensure proper system operation during commissioning.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Automated Temperature Controls B116, newest first.
File Type Posted
Solicitation Amendment FA449720R00170001 SF 30.pdf PDF
B116 QA_Responses 20200524.pdf PDF
Atch 1 - SOW - Repair B116 Replace HVAC Controls.pdf PDF
Atch 5 - DAFB Standard Specifications.pdf PDF
Solicitation - FA449720R0017.pdf PDF
Atch 4 - DAFB Local Design Guide (9 Apr 18).pdf PDF
Atch 3 - Wage Determination Building 20200103.pdf PDF
Atch 7 - Brand Name Trane SC JA 20200512.pdf PDF
Atch 2 - Bid Schedule - B116 Rpl Auto Temp Ctrls.xls XLS spreadsheet
Atch 6 - Operational Climatic Data.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

436th Contracting

Squadron (AMC) 639 Atlantic Street

Dover AFB, Delaware 19902-5639

11 June 2020

MEMORANDUM FOR ALL OFFERORS

FROM: 436 CONS/PKA

639 Atlantic St Dover AFB, DE 19902

SUBJECT: FA449720R0017, Project No. 1076655, Replace Automated Temperature Controls B116, Questions and Answers Clarification

The following is a list of clarification questions posed by prospective contractors and the corresponding answers.

Q1. With the replacement of the VAVs and controls throughout the building, will testing and balancing of the air and water be required for the HVAC system?

A1. The SOW does not call for TAB. The controls and VAVs should be a 1 for 1 swap. The SOW requires the contractor to ensure proper operations during commissioning.

DEPARTMENT OF THE AIR FORCE