SPECIFICATIONS
FOR
DEMOLISH T-606 & CONSTRUCT
PARKING FOR T-611
MQNA 13-1001
Portfolio Optimization Office, 65th Civil Engineer Squadron
09 April 2018
USAFE
Lajes Field, Azores, Portugal
65th Civil Engineer
Squadron APO AE 09720
1383339088U Typewritten Text
REVISION I
MQNA 13-1001
Demolish T-606 & Construct Parking lot for T-611
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 73 03 SUPPLEMENTARY CONDITIONS FOR AZORES PROJECTS
special administrative requirements for projects located in the Azores
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
a description of work covered in this contract and is required for use in all projects
01 14 00 WORK RESTRICTIONS
work and site restrictions
01 30 00 ADMINISTRATIVE REQUIREMENTS
general administrative and procedural requirements for Contractor management and coordination
01 33 00 SUBMITTAL PROCEDURES
general procedures regarding submittals, data normally submitted for review to establish conformance with the design concept and contract documents
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
safety and occupational health requirements for the protection of Contractor and Government personnel, property, and resources
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
listing of organizations whose publications are referenced in other sections of the specifications.
01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION
Quality Control for small construction projects and repair or maintenance work. It may also be used for minor elements or small quantities of work in larger projects at the discretion of the Government
01 78 00 CLOSEOUT SUBMITTALS
closeout submittals including: revised project documents, warranty management, testing, adjusting and balancing, O & M manuals, and cleanup
01 78 23 OPERATION AND MAINTENANCE DATA
Operation and Maintenance (O&M) data packages, manuals and training
DIVISION 02 - EXISTING CONDITIONS
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
excavation, handling, and temporary storage of contaminated material
02 66 00 SELECT FILL AND TOPSOIL FOR LANDFILL COVER
PROJECT TABLE OF CONTENTS Page 1 select fill and topsoil layers for landfill cover systems. Select fill is the term used by USACE to describe soil layers placed directly on geosynthetic materials
02 82 13.00 10 ASBESTOS ABATEMENT
removal, encapsulation, enclosureencasement, or repair of friable and non-friable asbestos-containing material (ACM) which is encountered during the demolition, alteration, renovation, or maintenance of structures, substrates, equipment or portions thereof that contain asbestos; transportation, disposal, storage, containment of; and housekeeping activities on the site at which these activities are performed
02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
safety procedures and requirements for the demolition, removal, encapsulation, and disposal of asbestos containing materials (ACM)
02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD
for limiting occupational and environmental exposure to lead when removing/controlling lead-based paint or paint with lead (LBP/PWL)
DIVISION 03 - CONCRETE
03 30 00.00 10 CAST-IN-PLACE CONCRETE
cast-in-place concrete materials, mixing, and placement not exposed to a marine or high chloride environment.
DIVISION 04 - MASONRY
04 20 00 UNIT MASONRY
reinforced and nonreinforced masonry
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 JOINT SEALANTS
sealants for normal building construction
DIVISION 09 - FINISHES
09 06 00 SCHEDULES FOR FINISHES
color of exterior and interior materials and products
09 90 00 PAINTS AND COATINGS
painting of new and existing, interior and exterior substrates, including masonry, concrete, metal, wood and other miscellaneous materials
DIVISION 10 - SPECIALTIES
10 14 53 TRAFFIC SIGNAGE
PROJECT TABLE OF CONTENTS Page 2 traffic signs and sign posts
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
electrical general requirements, complete
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
common to all electrical sections
26 08 00 APPARATUS INSPECTION AND TESTING
electrical inspection and testing
26 20 00 INTERIOR DISTRIBUTION SYSTEM
procurement, installation, and testing of electrical wiring systems for construction projects
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
earthwork activities for buildings, utilities, roadways, railroads, and airfields
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.17 COLD MILLING OF BITUMINOUS PAVEMENTS
cold milling of bituminous pavement for airfields, roads, streets, parking areas, and other general applications
32 11 20 BASE COURSE FOR RIGID AND SUBBASES FOR FLEXIBLE PAVING
subbase, select-material subbase and rigid base courses for airfield pavements, roads and streets.
32 11 23 AGGREGATE AND/OR GRADED-CRUSHED AGGREGATE BASE COURSE
base course to be used directly under bituminous pavement courses
32 11 24 GRADED CRUSHED AGGREGATE BASE COURSE FOR FLEXIBLE PAVEMENT
graded crushed aggregate base course with a CBR 100 for use under flexible pavements and pervious pavement systems
32 12 13 BITUMINOUS TACK AND PRIME COATS
bituminous tack and prime coats for airfield pavements, roads, parking areas and general paving needs
32 12 16 HOT-MIX ASPHALT (HMA) FOR ROADS
hot-mix asphalt (HMA) courses (central-plant hot-mix) for roads
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
small portland cement concrete paving jobs such as roads, streets, sidewalks, and parking lots
32 17 23 PAVEMENT MARKINGS
pavement marking requirements for airfields, heliports, PROJECT TABLE OF CONTENTS Page 3 in hangars, roads and parking areas by means of paint, raised pavement markers (RPM), preformed tapes or plastics.
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
storm drainage piping systems using concrete, clay, steel, ductile iron, aluminum, polyvinyl chloride (PVC), polyethylene (PE), polypropylene (PP) pipe and steel reinforced polyethylene (SRPE) pipe
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
underground electrical work
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 73 03
SUPPLEMENTARY CONDITIONS FOR AZORES PROJECTS
08/08 special administrative requirements for projects located in the Azores
PART 1 GENERAL
1.1 SUBMITTALS
1.2 PHYSICAL DATA
1.3 LEGAL HOLIDAYS
1.4 CONDUCT OF CONTRACTOR PERSONNEL
1.5 EMPLOYEE RECRUITING (PORTUGUESE NATIONALS)
1.6 INVESTIGATION OF DAMAGE OR INJURY
1.7 PROCESSING OF CONTRACTOR'S PERSONNEL AND PROPERTY
1.8 RADIO FREQUENCIES FOR MOBILE AND PORTABLE RADIOS
1.9 SPECIAL REQUIREMENTS FOR OUTDOOR SIGNS
1.10 WRITTEN CORRESPONDENCE
1.11 PORTUGUESE EQUIVALENT
1.12 SOURCE REQUIREMENTS CLAUSE (01 MAY 86)
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
DOCUMENT 00 73 03 Page 1
DOCUMENT 00 73 03
SUPPLEMENTARY CONDITIONS FOR AZORES PROJECTS
08/08
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval.Submit the following in accordance with Section 01 33 00 and shall be sent via AF Form 3000. The schedule of submittals shall be done using AF Form 66, Schedule of Materials submittals.
1.2 PHYSICAL DATA
Data referred to below is furnished for the Contractor's information.
However, it is expressly understood that the Government will not be responsible for interpretation or conclusion drawn therefrom by the Contractor.
a. The physical conditions indicated on the drawings and in the specifications are the result of site investigations.
b. Geographic Conditions
(1) The Azores are comprised of a group of nine small islands, politically an integral part of Portugal, lying in the North Atlantic, about 2,300 miles east of New York and about 980 miles west of Lisbon, Portugal. The islands have a total area of 1,581 square miles with a total population of about 360,000. The economic mainstays of the Azores are fishing and agriculture.
There is no heavy industry, and facilities for repairing machinery are limited. Most tools, implements, and farm utensils are handmade.
(2) The climate is mild and the humidity high. Average annual temperature is 63 degrees F. Diuranal fluctuation in temperature is approximately 10 degrees. Highest recorded temperature, 80 degrees F, lowest recorded temperature, 40 degrees F. The yearly average rainfall is 44.80 inches; the monthly average rainfall and probability of rain is as follows:
Month Average (in.) Probability
January 6.00 65 percent
February 5.40 64 percent
March 5.00 61 percent
DOCUMENT 00 73 03 Page 2
Month Average (in.) Probability
April 3.10 43 percent
May 1.80 39 percent
June 1.80 33 percent
July 7.70 29 percent
August 1.80 35 percent
September 3.20 40 percent
October 5.20 55 percent
November 5.10 57 percent
December 5.30 58 percent
High winds occur from December through March. Average winds during this period are 11.6 knots. The recorded high winds are: November 90 knots, December 72 knots, January 90 knots, February 128 knots, March 106 knots, April 89 knots.
1 Terceira Island measures roughly 11 by 18 miles, almost entirely bordered by high cliffs. The terrain is hilly and dominated by volcanic ranges, including two extinct craters. The airfield is located on the northeast side of the island. The total population of Terceira Island is approximately 80,000. The city of Angra do Heroismo, capitol of the district, has a population of about 30,000; and the nearest town to the airfield, Praia da Vitoria, has a population of about 11,000.
c. Transportation Facilities for Lajes Field. Lajes Field is defined as the U.S. Forces Azores operational area on Terceira Island.
1 Railroads: There are no railroads on the island.
2 Highways and Roads: The majority of the roads are paved. A asphalt highway links Praia da Vitoria and Angra do Heroismo. The use or construction of haul roads and bridges shall be subject to prior approval of the Contracting Officer.
3 Ports: The island has two ports capable of handling deep draft ocean freighters, Praia da Vitoria and Angra do Heroismo. There are no regularly scheduled commercial vessels arriving or departing Terceira Island.
4 Air: Lajes Field is served by the commercial two Portuguese airline s TAP & SATA.
1.3 LEGAL HOLIDAYS
For information purpose, the base acknowledges the following United States and Portuguese holidays:
DOCUMENT 00 73 03 Page 3
*New Year's Day 01 January
Mardi Gras Variable
Good Friday Variable
Day of Liberty 25 April
Day of the Worker 01 May
Holy Spirit Monday Variable
Corpus Christi Variable
Day of Portugal 10 June
Praia da Vitoria Day 11 August
Assumption Day 15 August
Founding of the Republic 05 October
All Saint's Day 01 November
Restoration of Independence 01 December
Immaculate Conception 08 December
*Christmas Day 25 December
*Martin Luther King's Birthday Third Monday in January
*President's Day Third Monday in February
*Memorial Day Last Monday in May
*Independence Day 04 July
*Labor Day First Monday in September
*Columbus Day Second Monday in October
*Veteran's Day 11 November
*Thanksgiving Day Fourth Thursday in November
(*) NOTE: Any of the above holidays falling on a Saturday will be observed on the proceeding Friday. Holidays falling on a Sunday will be observed on the following Monday.
DOCUMENT 00 73 03 Page 4
1.4 CONDUCT OF CONTRACTOR PERSONNEL
The Contractor shall report to the Contracting Officer, immediately upon receipt or discovery of any information, whether or not verified, relating to physical security incidents, misconduct, crimes, and misdemeanors, including but not limited to murder, arson, larceny of any weapon, ammunition, or explosives, larceny of other property, robbery, burglary, narcotics and dangerous drugs, destruction of Government property, fraud, malfeasance, sabotage, subversions, disaffections, treasons, or espionage. The Contractor shall recognize and comply with the rules and regulations promulgated by the foreign country where the work is performed to the extent required by international agreements.
1.5 EMPLOYEE RECRUITING (PORTUGUESE NATIONALS)
a. The Contractor, using the Contractor's own contracting forms, may contract directly or request assistance from the Civilian Personnel Office, Civilian Recruitment Section Headquarters Azores Air Zone (SRPC, HAAZ), in contracting Portuguese National employees. The Contractor's contract form shall include, as a minimum, the following: Organization or firm (name and address), contract and project numbers; contract start and expiration dates; and the following information concerning the employee: name, social welfare number, date and place of birth, residence (village and council), parents' name, marital status, spouse's maiden name, professional degree or skill, salary, and meal and transportation allowances.
b. It will be the Contractor's responsibility once employees have been hired, to clear them through SRPC, HAAZ to gain access to the installation .
c. The Contractor shall request base access through 65th CONF, for all employees and vehicles. The contractor shall also request base access through 65th Contracting Flight (65th CONF) for subcontractors, and shall specifically indicate in the request sheets, the subcontract's full name, civilian identification number and subcontractor companies legal designation.
1.6 INVESTIGATION OF DAMAGE OR INJURY
The U.S. Government will have the right to conduct an investigation, or participate in the Contractor's investigation, of any damage or injury to U.S. Government property, equipment, or personnel.
1.7 PROCESSING OF CONTRACTOR'S PERSONNEL AND PROPERTY
The Contractor shall process Contractor personnel and property through 65th CONF prior to commencement and at the completion of work under this contract. This processing shall include such things as registering and deregistering vehicles, arranging for the issuance and turn-in of identification and passes, and clearing liabilities incurred such as clubs, billeting, and loans.
1.8 RADIO FREQUENCIES FOR MOBILE AND PORTABLE RADIOS
Contractors requiring the use of mobile and portable radios on the project shall obtain Government of Portugal approval via the HAAZ Frequency Coordinator. Information needed by the Radio Frequency coordinator coordinator from the Contractor includes type of equipment, type of
DOCUMENT 00 73 03 Page 5 emission, frequency desired, power, geographical coordinates of the project site, hours of radio operation, and start and end dates of frequency requirement. For planning purposes, the frequency coordination process normally requires 60 to 90 days for completion. The Government of Portugal closely monitors frequency usage and unauthorized users are subject to severe fines. COMUSFORAZINST 2410.1D pertains.
1.9 SPECIAL REQUIREMENTS FOR OUTDOOR SIGNS
In accordance with USFORAZINST 5710.2D outdoor signs displayed on local military facilities are mandatory to be in both Portuguese and English languages. Identical size lettering shall be used for both languages, with Portuguese on top. The same requirement applies to project signs and safety and warning signs as used by the Contractor, project signs shall be according Lajes Facilities Construction Standards.
1.10 WRITTEN CORRESPONDENCE
Written correspondence from the Contractor to 65th CONF shall be in English language, including but not limited to Contractor's invoice, Contractor's Monthly Estimate for Voucher, Contractor's schedules, samples and submittals, reports, and as-built drawing markups, this correspondence shall be digital signed and sended by email.
1.11 PORTUGUESE EQUIVALENT
Where equipment, materials, or installations are to be in accordance with American standards, the equivalent Portuguese standard may be used subject to the approval of the Contracting Officer. The Contractor shall be responsible for proving the equivalency of the Portuguese standard.
1.12 SOURCE REQUIREMENTS CLAUSE (01 MAY 86)
The requirements of this clause are material conditions of this contract.
The Contractor shall, in the performance of this contract, use Portuguese sources to the maximum extent feasible for the goods and services required to perform the contract including labor, materials, supplies, services, equipment, and subcontracts provided such goods and services meet the contract specifications and standards, will be available at the required locale within the required time limits and are equal or lower in cost than those from other sources. The Contractor shall demonstrate compliance with this requirement.
The requirement to use Portuguese sources to the maximum extent feasible does not apply when not in accordance with requirements, standards, or specifications specifically set forth elsewhere in this contract.
Consistent with the foregoing, the Contractor shall submit a four-part written "Report of Sources" to the Contracting Officer as follows:
PART I . The Contractor shall prepare a listing indicating for each category of expenditures anticipated under the contract the U.S. dollar value estimated to be paid to Portuguese sources and the U.S. dollar value estimated to be paid to other sources. The categories shall include as a minimum those shown in the following sample format:
DOCUMENT 00 73 03 Page 6
REPORT OF SOURCES
Category $ to Portuguese Sources
$ to Other Sources
Transportation
Direct Hire Labor
Construction Materials
Equipment
Purchases
Rentals
Supplies
Services
Subcontracts
Other
Total: (Sum must equal contract price)
NOTES:
(1) Items that are included in subcontracts, such as labor and materials, should be reported only as subcontracts and shall not be included with other categories.
(2) Overhead and profit must be prorated among the categories.
PART II . The Contractor shall prepare a list of subcontracts indicating the purpose of the subcontract, the name of the subcontractor, and whether Portuguese or other source.
PART III . The Contractor shall prepare a list of each item or subcontract not procured from a Portuguese source, indicating the reason for not procuring the item or subcontract from a Portuguese source.
PART IV . The Contractor shall indicate the approximate percentage of the total contract price that he will pay collectively to Portuguese sources.
The initial four-part "Report of Sources" shall be submitted by the Contractor to the Contracting Officer not later than 30 calendar days after contract award. In addition, the Contractor shall submit an updated report in the same four-part format every 30 calendar days thereafter. If no changes have occurred since the last report, the Contractor may submit a negative report by letter.
PART 2 PRODUCTS
Not Used
DOCUMENT 00 73 03 Page 7
PART 3 EXECUTION
Not Used
-- End of Document --
DOCUMENT 00 73 03 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
08/15 a description of work covered in this contract and is required for use in all projects
PART 1 GENERAL
1.1 SUBMITTALS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description:
1.2.1.1 Demolition Work
1.2.1.2 New Work
1.2.2 Location
1.3 OCCUPANCY OF PREMISES
1.4 EXISTING WORK
1.5 LOCATION OF UNDERGROUND UTILITIES
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description:
1.2.1.1 Demolition Work
A. Mill/remove and dispose of existing asphalt on area-A (17.8cm thick) completely (approximately 2350 SM.), as per project drawings.
B. Remove existing asphalt (17.8cm thick) (approximately 4709 SM.), including base (7.6 cm) and sub-base (30.5 cm) in area - B, as per project drawings.
C. Remove existing concrete curb (approximately 135 M), turf and soil (approximately 2646 SM.) in order to prepare sub base and base to receive new asphalt, as per project drawings.
D. Remove existing turf and soil and prepare area for new sidewalk with concrete curbing around T-605 and T-606 ( approximately 452 SM.).
E. Remove/demolish existing reinforced concrete (17.8 cm thick) completely, as per attached drawings (approximately 355 SM.) including base (7.6 cm) and sub-base (30.5 cm), as per project drawings.
F. Remove/demolish existing concrete stairs completely, as per project drawings (approximately 2.26 CM.).
G. Remove/demolish existing 1.22m height CMU wall, with stone facing and 1.5m height metal fence on top, as per project drawings (approximately 32m.).
h. Remove/demolish existing 2.49m height, metal fence, poles, barbed wire and concrete footings, as per project drawings (approximately 58m).
I. Remove/demolish existing 6m long, double swing gates and all associated hardware (2 Ea.).
J. Remove/demolish existing building (T-606) completely including foundations (approximately 1112 SM.). All existing infra-structural lines ( water, sewer, power, comm, fiber) shall be removed all the way up to their main lines and there they shall be properly disconnected and/or capped.
K. Prior to T-606 demolition Contractor shall properly abate and dispose
SECTION 01 11 00 Page 2 of asbestos containing materials (ACM) (approximately 18.00 SM) and lead base paint (LBP) (approximately 1340 SM.) with-in the building as per project drawings
L. Remove/demolish existing concrete pole, transformer, associated pad and secondary power lines that feed T-606 and T-605 all the way to the existing riser/transformer located at T-607
M. Excavate trenches to accommodate new storm drain system at the parking area (approximately 150 M.)
N. Excavate trenches to accommodate new power lines to feed T-605 and new parking lot (approximately (183M)
Demolition - General notes
A. Demolition materials shall be properly disposed
B. Use appropriate equipment and techniques for demolition or removal work in order to avoid damages on surrounding area.
C. Existing fire alarm panel, interior lights, water backflow preventer, electrical pole accessories and exterior power transformer are to be turn in to the Civil Engineering Squadron Electrical & Water Fuels Maintenance Shop
1.2.1.2 New Work
A. Prepare pavement to receive tack coat (approximately 10,060 SM.) and new asphalt, 17.8cm thick (approximately 10,060 SM.).
B. Provide new base (7.6 cm) and sub-base (30.5 cm) in all areas with exeption of area - A, re-arrange slopes, and any existing manhole covers and/or valves covers or sleeves to match new pavement slopes.
Contractor shall re-arrange existing slopes in order to assure a smooth and constant slope all the way to the compound main gate, therefore they shall have in account the area where T-606 was located and the entrance to the new adjacent parking lot ( old area 5).
C. Place Portland cement concrete pavement, 2,500 psi, 10cm thick (approximately 742 SM.), including concrete curbing (European style) (approximately 450 M.) at new sidewalks and access ramp, as per project drawings. Saw cut new joints on the concrete, place backer rod in all joints and appropriated joint sealant (every two meters).
Sidewalk on the back and sides of T-605 & T-606 are to be 1.83m wide.
As per the remaining sidewalks they are all to be 1.2m wide.
D. Construct new 1.22m height and 0.60m wide CMU (concrete masonry unit) wall with stone facing and install 1.5m decorative fence on top of wall, manufacturer "Betafence", model "Barofor Square", RAL 6005,including all necessary hardware, as per manufacture recommendation, or equivalent (approximately 100M.). Stucco side to be painted as per LFFES.
E. Repaint new floor markings with thermoplastic paint, (approximately 150 SM.) as per project drawings.
F. Install new ADA compliant handrail at new access ramp, handrail to be
SECTION 01 11 00 Page 3 in metal, prepared, prime and painted. (approximately 15 M.).
G. Install new aluminum vertical sign for Handicap parking spot, and wherever needed in order to direct new traffic flow as per project drawings ( approximately 8 Ea.). New signs shall comply with the European standards and shall be of retroreflection level 3.
H. Re-arrange any existing manhole covers and/or valves covers or sleeves to match new pavement slopes ( approximately 6 Ea.).
I. Install new COMM manhole cover, made of spheroidal graphite cast iron D400 class, with anti-theft system, manufacturer "CAPA Drain", model "Easyflex RD600", Ref:. 922023 or equivalent, (2 EA). Cover shall be marked with (COMM) on the top side, with the minimum size letters of 2"
J. Install new precast concrete storm water drainage boxes, with 706mm x 380mm, grating and frames made of spheroidal graphite cast iron D400 class, with anti-theft system, manufacturer "CAPA Drain", model "Grelhas Sumidouro", Ref:. 924114, or equivalent, (14 EA).
K. Install new Ø200mm underground, PVC schedule 40 or SN4, drainage pipe interconnecting new drainage boxes and connecting them to the existing storm water box, locate near T-608 main entrance, (approximately 150 M.).
L. Install new Ø200mm underground, PVC schedule 40, drainage pipe interconnecting new drainage boxes and connecting them to the existing storm water box, locate near T-608 main entrance, (approximately 150 M.).
M. Install new Ø150mm, concrete filled, metal, schedule 80, protective bollards, spaced 1.20m from each other's, to protect new sliding gate.
(11 for the gate & 3 for fire hydrant protection).
N. Install new 12m x 2.40m, motorized sliding gate, manufacturer "Betafence", model "Robusta SR", RAL 6005, including dental strip on top of gate as overclimb protection and all necessary hardware, as per manufacture recommendation, or equivalent,(1 EA). Also, gate shall be provided with two remote controls and have the capability of being operated locally.
O. Install new 8m x 2.43m, double swing gate, manufacturer "Betafence", model "Robusta SQ25", RAL 6005, including dental strip on top of gate as overclimb protection and all necessary hardware, as per manufacture recommendation, or equivalent, (1 EA).
P. Extend existing water line, remove and save to re-install existing fire hydrant. Fire hydrant to be installed as close as possible to the new wall and protected by concrete filled bollards (approximately 20 M).
Q. Install two (2) wall mounted, PVC, IP67, power boxes to feed new motorized gate and future street lights
S. Install two (2) Ø100mm, concrete encased, PVC, schedule 40, conduits for new electrical systems (approximately 183 M.), as per attached drawings, including all necessary electrical cables and switches to feed building T-605, new sliding gate and new LRS parking light poles.
Sliding gate and light poles are to be connect at T-608 mechanical room.
SECTION 01 11 00 Page 4
T. Install new photocell system outside T-608 mechanical room and connected to existing parking lot electrical systems ( T-709 parking area and LRS parking). Photocells shall be hermetically sealed, silicon diode light sensor type, rated at 150 watts, 230 volts, 50 Hz with single-pole, double-throw contacts. Photocell shall be designed to fail to the ON position. Housing shall be constructed of polycarbonate, rated to operate within a temperature range of minus 40 to 70 degrees C / minus 40 to 158 degrees F. Photocell shall have a 13 mm / 1/2 in threaded base for mounting to a junction box or conduit. Provide fixed base type housing. Photocell shall turn on at 10-30 lux/ 1-3 footcandles and turn off at 30 to 150 lux/ 3 to 15 footcandles. A time delay shall prevent accidental switching from transient light sources. Provide a directional lens in front of the cell to prevent fixed light sources from creating a turnoff condition.
I. Install new 0.60m X 0.60m X 0.60m precast concrete electrical handhole, with cover, made of spheroidal graphite cast iron D400 class, with anti-theft system, manufacturer "CAPA Drain", model "Tampa Rasa Traffic - 600", Ref:. 920314 or equivalent, (1 EA). Cover shall be marked with (ELECTRICAL) on the top side, with the minimum size letters of 2"
1.2.2 Location
The work is located at Avenida do Imperio, LRS Compound (T-608 Area, Lajes Field, Azores, Portugal.
1.3 OCCUPANCY OF PREMISES
Buildings in the project area will be occupied during performance of work under this Contract.
Before work is started a phasing plan must be provided to ,the Contracting Officer with thesequence of procedure, means of access, space for storage of materials and equipment, and use of approaches,in order to minimize the impact on tenants daily operations
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. The contractor shall only remove or alter existing work, when specifically authorized to do so, or in manner that prevents injury or damage to any portion of existing work.
b. The contractor shall repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
SECTION 01 11 00 Page 5
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain AF Form 103 work clearance request approved by CEO chief prior to start job , and comply with Installation requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 48 hours] prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.] Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground, pier deck or paved surface where existing underground utilities ]are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
11/11 work and site restrictions
PART 1 GENERAL
1.1 SUBMITTALS
1.2 SPECIAL SCHEDULING REQUIREMENTS
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
1.3.1.1 Subcontractors and Personnel Contacts
1.3.1.2 Identification Badges and Installation Access
1.3.1.3 No Smoking Policy
1.3.2 Working Hours
1.3.3 Work Outside Regular Hours
1.3.4 Occupied Building[s]
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
Personnel List; G
Vehicle List; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Project site access for personnel and vehicles must be submitted to the Contracting Officer and approved by HAAZ (Headquarters Azores Air Zone) before work is started.
b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 21 calendar days prior to the desired date of interruption and approved by HAZZ or Base Group Commander.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
SECTION 01 14 00 Page 2
1.3.1.2 Identification Badges and Installation Access
Application for and use of badges will be as directed.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 8 hour hours period , between 8 a.m. and 5;00 p.m., Monday through Friday.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 21 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.3.4 Occupied Building[s]
The Contractor shall be working around existing buildings which are occupied.
The existing buildings and their contents must be kept secure at all times.
] PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 3
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15 general administrative and procedural requirements for Contractor management and coordination
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 MINIMUM INSURANCE REQUIREMENTS
1.4 SUPERVISION
1.4.1 Minimum Communication Requirements
1.4.2 Superintendent Qualifications
1.4.2.1 Duties
1.4.3 Non-Compliance Actions
1.5 PRECONSTRUCTION
1.6 ELECTRONIC MAIL (E-MAIL) ADDRESS
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval.
1.3 MINIMUM INSURANCE REQUIREMENTS
Not applicable.
1.4 SUPERVISION
1.4.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.4.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
SECTION 01 30 00 Page 2
1.4.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted, and should have authority to make decisions on contractor behalf.
1.4.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.5 PRECONSTRUCTION
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.6 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence, all correspondence shall be digitally send. The Contracting Officer may also use e-mail to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 30 00 Page 3
SECTION 01 30 00 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11 general procedures regarding submittals, data normally submitted for review to establish conformance with the design concept and contract documents
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
1.1.2 Approving Authority
1.1.3 Work
1.2 SUBMITTALS
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
1.3.2
1.4 PREPARATION
1.4.1 Transmittal Form
1.4.2 Source Drawings for Shop Drawings
1.4.2.1 Terms and Conditions
1.4.3 Electronic File Format
1.5 QUANTITY OF SUBMITTALS
1.5.1 Number of Samples SD-04 Samples
1.6 INFORMATION ONLY SUBMITTALS
1.7 SUBMITTAL REGISTER
1.7.1 Use of Submittal Register
1.7.2 Contractor Use of Submittal Register
1.7.3 Approving Authority Use of Submittal Register
1.7.4 Copies Delivered to the Government
1.8 VARIATIONS
1.8.1 Considering Variations
1.8.2 Proposing Variations
1.8.3 Warranting that Variations are Compatible
1.8.4 Review Schedule Extension
1.9 SCHEDULING
1.10 GOVERNMENT APPROVING AUTHORITY
1.10.1 Review Notations
1.11 DISAPPROVED OR REJECTED SUBMITTALS
1.12 APPROVED/ACCEPTED SUBMITTALS
1.13 APPROVED SAMPLES
PART 2 PRODUCTS
PART 3 EXECUTION
SECTION 01 33 00 Page 1
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
05/11
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to:
List of proposed Subcontractors G
Construction progress schedule G
Submittal register G
Health and safety plan G
Quality Control(QC) plan G
Environmental protection plan G
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic
SECTION 01 33 00 Page 3 characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports.
Daily logs and checklists.
Final acceptance test and operational test procedure.
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits.
Text of posted operating instructions.
SD-08 Manufacturer's Instructions
SECTION 01 33 00 Page 4
Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
This data is intended to be incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.1.2 Approving Authority
Office or designated person authorized to approve submittal.
1.1.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor QC approval.
Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register G
List of proposed Subcontractors G
Health and safety plan G
Quality Control(QC) plan G
Environmental protection plan G
Af Form 103 G
SECTION 01 33 00 Page 5
1.3 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.3.1 Government Approved (G)
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."
1.3.2
1.4 PREPARATION
1.4.1 Transmittal Form
1.4.2 Source Drawings for Shop Drawings
No set of Source Drawing files (DWG /AutoCAD) will be provided to the Contractor.
1.4.2.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic Source Drawing files are not construction documents.
Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
SECTION 01 33 00 Page 6
1.4.3 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.
Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer.
1.5 QUANTITY OF SUBMITTALS
1.5.1 Number of Samples SD-04 Samples
a. Submit two samples, or two- sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of non-solid materials.
1.6 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract.