Project # MXDP 16-1040 June 08, 2018
STATEMENT OF WORK
REPLACE COOLING SYSTEM, B448
PROJECT LOCATION: Laughlin AFB, TX
BASE PROJECT NUMBER: MXDP 16-1040
08 JUNE 2018
1.0 INTRODUCTION
Services are required to replace the existing central energy plant at Building 448 with a new cooling system and reduce the rising maintenance costs resulting from the inefficient/inoperable heating, ventilation and air conditioning (HVAC) system. The completed project shall include the replacement of the chiller, cooling tower, pumps and pipes. Failure to provide this project will allow numerous dorm rooms in building 449 and 450 to remain unusable due to the lack of HVAC, which will drive up the cost of housing students on the local economy.
2.0 SCOPE OF WORK
The Contractor is to furnish all materials, labor, tools, equipment, transportation, and all other incidentals necessary to complete the work outlined in this Statement of Work (SOW) and to turn over to the Government a complete and useable area. Work shall include the replacement of the chiller, cooling tower, pumps, pipes and the construction of a new mechanical yard to match the existing.
2.1 Description of Work
The Contractor shall accomplish the objectives listed below:
2.1.1 Architectural – Construction (approximately 405 SF): Add new mechanical yard to match the existing (see attachment 1 for location and dimensions).
2.1.2 Plumbing – Provide new makeup water connection.
2.1.2.1 New makeup water connection will connect to existing water service.
2.1.2.2 Existing eye wash station in building 448 will remain.
2.1.3 Mechanical – Demolition: Remove existing cooling system, pumps, and pipes indicated in the design drawings (see attachment 1).
2.1.3.1 Demolish and remove existing chiller, cooling tower, chilled and condenser water pumps, chilled/condenser water chemical treatment system, chilled water expansion tanks, chemical shot feeder, refrigerant sensor, exhaust fan, and all associated piping and ductwork.
2.1.4 Mechanical – Renovation: Replace cooling system, pumps, and control system indicated in the design drawings (see attachment 1).
2.1.4.1 Existing chill water supply and return piping to building 449 and 450 shall remain and be re-used.
2.1.4.2 Existing boiler and heating water pump shall remain and the heating water system will not be changed.
2.1.4.3 Existing cooling system will be replaced with two new 80 ton air cooled chillers each sized at 60% of the peak load.
2.1.4.4 Existing pumps will be replaced with two new base mounted pumps located inside building 448.
2.1.4.4.1 New pumps will each have a variable frequency drive (VFD) and serve a common variable-primary loop pumping out to both buildings 449 and 450.
2.1.4.5 Provide a new differential pressure sensor for chilled water.
2.1.4.6 New cooling system will include all accessories and components necessary to be complete and functional. These will include:
2.1.4.6.1 Expansion Tanks
2.1.4.6.2 Air Separators
2.1.4.6.3 Chemical Feed Systems
2.1.4.6.4 Heat Tracing
2.1.4.7 New cooling system will be fully controlled and monitored by the Siemens Apogee System to allow for all control functionality to be available at the Siemens Apogee Workstation.
2.1.4.7.1 New control system functionality shall include, but not be limited to, database (programming and points) viewing and editing, graphic viewing, commanding and editing, scheduling of control functionality, central alarm monitoring, information collection, and trend logging and analysis.
2.1.4.7.2 Flow and British Thermal Unit (BTU) Meters shall be installed on the heating hot water supply and the chilled water supply at building 449 and 450 entry points; chilled water flow shall be balanced to 190 Gallons Per Minute (GPM) for building 449 and 130 GPM for building 450.
2.1.4.7.3 New controls shall interface with the base Energy Management Control Systems (EMCS), which are Siemens Insight 3.13 and Johnson Controls Metasys SMP 7.0.0.4400.
2.1.4.8 Contractor shall provide testing and balancing for all existing fan coil units to ensure all units are balanced.
2.1.4.9 Contractor shall provide new thermostats for all fan coil units that allow user temperature adjustment +/- 3 degrees Fahrenheit from the set point.
2.1.5 Electrical – Demolition: Remove all conduits and conductors associated with the demolished equipment and devices.
2.1.5.1 Demolish and remove existing utility transformer, disconnect for the cooling tower, starter for the cooling tower, 400 Amp (A) service to disconnect, R-22 sensor, below-grade service entrance feeder, refrigerant exhaust fan, and all associated conductors and circuits.
2.1.5.1.1 Return demolished utility transformer to utility company.
2.1.5.1.2 Patch and backfill concrete as necessary.
2.1.5.2 Existing HWP-1 and starter shall remain.
2.1.5.3 Existing Panel 6x shall remain.
2.1.5.3.1 Remove all breakers and wires serving the equipment and devices that will be demolished; mark all associated circuits as spare.
2.1.6 Electrical – Renovation:
2.1.6.1 Install new 800A, 480Y/277V, 3 phase, 4 wire fused service disconnect switch.
2.1.6.2 All primary electrical work must be subcontracted out to Rio Grande Electric
Cooperative, Inc. (Attachment 6).
2.1.6.3 Install new distribution panelboard.
2.1.6.3.1 New panelboard will include two 300A breakers, one 225A breaker, one 60A breaker, and two 20A breakers.
2.1.6.3.2 New pumps will be served from the new distribution panelboard.
2.1.6.3.3 The existing 400A, 480Y/277V, 3 phase, 4 wire distribution panelboard will continue to serve existing 208Y/120V and 120/240 transformers as well as any fans and pumps that have not been de-commissioned.
2.1.6.4 Install a surge protective device, which will help to protect sensitive electronic equipment in the central plant.
2.1.6.5 Install a new utility pad mounted transformer depending upon power utility sizing criteria.
2.1.6.5.1 New transformer will require a new primary duct bank from a new utility riser pole.
2.1.6.5.2 Primary duct bank will be provided by contractor to conform to utility requirements.
2.1.6.6 Connect to existing equipment receptacle circuits serving building 448.
2.1.6.7 Route new incoming secondary service feeders below grade from new utility transformer to new service entrance disconnect switch.
2.1.6.8 Coordinate all routing with other utility pipes and conduits in the area.
2.2 Additional Information
2.2.1 The contractor is responsible for conducting a thorough site inspection in order to obtain the information necessary to complete the project. The Contractor shall attend a Pre-Construction Conference after the contract is awarded and after issuance of the first Notice to Proceed. The Government will notify the Contractor when this conference will be held.
2.2.2 Contractor shall take pictures of the interior and exterior of the building prior to construction and at end of the construction period. Contractor shall invite the Contracting Officer to be in attendance while taking pictures.
2.2.3 Prior to Government acceptance, all areas shall be free of construction debris. Provide, in writing, the location for disposal of any debris. If using other than approved disposal sites, approval must be obtained from the city and/or county. Approval documents shall be submitted to the Contracting Officer. Construction work areas shall be clean and free of any and all debris at the end of each work day. Contractor shall return site to preconstruction condition or better and at no additional cost to the Government.
2.2.4 The Contractor shall provide temporary equipment to mitigate effects of an outage. Refer to notes in the design drawing sheet G-002 in attachment 1. If required, outage(s) must be approved by the Contracting Officer as dictated by the user’s needs. Requests for outage shall be provided to the Contracting Officer no fewer than 14 calendar days in advance of the requested outage.
2.2.5 The Government will furnish copies of available records as necessary to aid in the completion of this project; however, use of Government furnished data does not relieve the Contractor from performing a thorough site investigation in order to obtain the information necessary to properly complete this project.
2.2.6 All work shall be performed during normal duty hours, which are 0730 to 1630, Monday to Friday. Contractor must leave the worksite weather tight at the end of each work day. Work shall not be performed during Federal holidays. Requests to work outside of normal duty hours shall be submitted to the Contracting Officer no fewer than 5 calendar days in advance. The Contractor should be aware that requests may not be approved.
2.2.7 Base Security Forces requires all Contractors to submit background checks for each employee prior to getting access to base. The Contractor shall submit fully completed background check forms to the Contracting Officer a minimum of 14 calendar days in advance of the Contractor’s need for access.
2.2.8 All work on this project shall be accomplished in accordance with the Statement of work, unless modified by unique contract specifications, the design specifications (Attachment 2) and the Laughlin AFB Division 1 (Attachment 6) defined by the Construction Specifications Institute (CSI) MasterFormat (current edition). If there are any conflicting specifications between the Laughlin AFB Division 1 and the CSI MasterFormat, the most stringent will take precedence. In any instance where work is required that is not specifically covered by the Laughlin AFB Division 1 specifications cited above, the work shall be accomplished in accordance with the most applicable industry standard for the specific work required. All work shall be in accordance with the Uniform Building Code, Unified Facilities Criteria 4-022-01 (Attachment 7), and all applicable Air Force, State, Federal, and local codes.
2.2.9 Use of existing condition data provided by the Air Force conveys acceptance and, as such, does not relieve the Contractor of liability associated with performance. The Contractor shall be solely responsible for verification and validation of existing conditions, coordination of existing conditions in parallel with proposed requirements, and above and below-grade condition assessment.
2.2.10 All base provided drawings are considered approximations and the contractor is required to verify all measurements before material is purchased or cut.
2.2.11 All as-built drawings submitted must be in the AutoCAD Version 2014 format.
2.3 Period of Performance
This project will require multiple Notices to Proceed (NTP): one for submittals, one for the order and delivery of supplies/materials, and one for construction. The Contractor is required to attend a Pre-Construction Conference after the first NTP is given, prior to the start of ordering and delivery of supplies/materials and construction. The Government will notify the Contractor when this conference will be held. The NTP for the construction phase will not be issued until the order and delivery phase is complete unless otherwise approved by the Contracting Officer.
The Period of Performance (POP) for the submittal phase will be 120 calendar days from the start date identified written on NTP #1, the POP for the ordering and delivery of supplies/materials phase will be 60 calendar days from the start date identified on written NTP #2, and the POP for the construction phase will be 198 calendar days from the start date identified on written NTP #3.
2.4 Submittal Phase
Contractor shall provide required submittals as indicated on AF Form 66, Schedule of Material Submittals (Item 12).
The Contractor shall provide electronic copies of all required submittals.
The Contractor shall provide submittals on the schedule, materials, and Safety Data Sheets (SDS) for Government review. All construction materials and submittals shall be approved prior to issuance of NTP #2. The Government has 14 calendar days to review each submittal in order to approve or disapprove the submittal.
2.5 Order and Delivery Phase
Upon issuance of NTP #2 and approval by the Contracting Officer, the contractor shall begin ordering approved materials and supplies required to complete construction. Contractor shall have 60 calendar days to order and receive all materials and supplies and have them ready to utilize once the construction phase begins.
2.6 Construction Phase
Upon the approval by the Contracting Officer, the Contractor may commence onsite construction activities and shall complete the work.
2.7 Pre-Construction Kick-Off Meeting
47 CONF will host a pre-construction (i.e., Kick-Off) meeting to advise and coordinate on local procedures, safety and security requirements, and project coordination activities. The CO Representative (COR) will arrange for a suitable Kick-Off meeting location. The COR will schedule the pre-construction meeting after NTP #1 and before NTP #3. No submittal is required for this meeting. This meeting will be an opportunity for the Contractor to meet with stakeholders, end users and maintainers in order to ensure a full understanding of the scope of work. The COR will ensure the appropriate base agencies attend the Kick-Off meeting to provide necessary information or briefings to facilitate the success of the contract effort. This shall include stakeholders such as the base Fire Department, Bioenvironmental Engineering Flight, Wing Safety, Civil Engineer Squadron, the user, etc.
During the meeting the Contractor shall present a complete overview of the project, review the schedule, highlighting any issues (review periods, material submittals, etc.) which are key to maintaining the schedule. The Contractor shall take meeting minutes to include the recording of the attendance list and the Contractor shall send the meeting minutes to the CO.
3.0 REFERENCES
Work under this contract shall comply with all federal, state, local, Air Force and all other current applicable requirements. All work accomplished by the Contractor shall comply with these criteria unless a written waiver is obtained from the Air Force when conditions warrant such consideration. The Contractor shall conform to all standards and specifications in the Unified Facilities Guide Specifications (UFGS) and common construction practices. The Contractor shall thoroughly review these specifications and follow them accordingly.
4.0 DELIVERABLES
4.1 Contract Progress Schedule
The Contractor shall submit a signed Progress Schedule (Attachment 8) depicting an overall contract progress schedule for the main elements of work for the period of performance, as described in the Schedule of Material Submittals. The Contractor shall also provide a line graph depicting actual construction progress (solid line) versus scheduled construction progress (dotted line) throughout the period of performance. The progress schedule shall be signed by the COR or the Government inspector recommending approval, and approved by the CO. Payment for materials stored on or off site will not be authorized. This submittal shall be submitted to the Contracting Officer no later than stated in the Table of Deliverables in paragraph 4.4 and shall be approved by the Government prior to commencement of construction operations.
4.2 Contract Progress Report
The Contractor shall submit a signed Progress Report (Attachment 8) every two weeks during construction as described in the Schedule of Material Submittals. The Progress Report shall be signed by the Contractor’s on-site representative. The work elements and percentages of the total job identified on the Progress Report shall be identical to the work elements and percentages on the Progress Schedule. The Contractor shall obtain either the COR or the Government contract inspector’s acceptance by signature of the actual reported progress prior to submission to the CO. Additionally, the Contractor shall submit the updated Progress Schedule as an attachment to the Progress Report.
4.3 Transfer and Acceptance of Real Property (DD Form 1354)
The Contractor shall update and submit a DD Form 1354 (Attachment 9) every month during construction as described in the Schedule of Material Submittals. The DD Form 1354 shall be updated monthly based on the equipment and materials installed for the project. The DD Form 1354 capitalizes assets installed by the Contractor and accepts the property into the Air Force Inventory. As construction is completed, a draft DD Form 1354 will be submitted 14 calendars days before the pre-final inspection. After government review, the Contractor will submit a signed final DD Form 1354 at the final inspection.
4.4 Project Deliverables
Project deliverables shall be as shown in the table below.
TABLE OF DELIVERABLES
Document Title Delivery Date
Kick-Off Meeting and Site Visit NLT 7 calendar days after NTP #1
TABLE OF DELIVERABLES
Document Title Delivery Date
Progress Schedule (AF For NLT 7 calendar days after NTP #1
Material Approval (AF Form 3000) In accordance with Schedule of Submittals
Meeting Minutes NLT 3 calendar days after each meeting
Transfer & Acceptance of Military Real Property (DD 1354) 30 calendar days after NTP #3, Monthly
Shop Drawings In accordance with Schedule of Submittals
Phase Plan In accordance with Schedule of Submittals
Safety Plan In accordance with Schedule of Submittals
Weathertight Plan In accordance with Schedule of Submittals
Progress Report (AF 3065 or approved equivalent) Every 14 calendar days
Pre-Final Inspection Report 7 calendar days before Final Inspection
Daily Logs (AF Form 1477 or approved equivalent) Every 7 calendar days
Draft Transfer & Acceptance of Military Real Property (DD 1354) 14 calendar days before Pre-Final Inspection
As-built Drawings 14 calendar days before Final Inspection
Final Transfer & Acceptance of Military Real Property (DD 1354) At Final Inspection
Final Inspection Report 7 calendar days after Final Inspection
5.0 PRE-FINAL INSPECTION
The Contractor shall conduct a pre-final walk through inspection with Base personnel. A pre-final inspection shall not be scheduled if the Contractor has not submitted a draft DD Form 1354, Transfer and Acceptance of Real Property.
6.0 FINAL INSPECTION
The Contractor shall conduct a final inspection with base personnel. The inspection shall concentrate on the items identified at the pre-final inspection and recorded as pre-final inspection items (punch list). A final inspection shall not be performed until the pre-final inspection items (punch list) have been resolved. The Contractor shall present a completed DD Form 1354, Transfer and Acceptance of Real Property at the final inspection.
7.0 DELIVERY/WARRANTY
The Contractor shall complete all inspection and commissioning requirements prior to final inspection. The Contractor shall also prepare and submit a draft DD 1354 (“Transfer and Acceptance of DOD Real Property”) at least 14 calendar days prior to requesting a pre-final inspection. The Contractor shall incorporate Government comments from the draft DD 1354 and submit a final DD 1354 at the final inspection. The warranty shall be issued in accordance with FAR 52.246-21.
8.0 CONTRACT ADMINSTRATION / POINTS OF CONTACT
Contracting Officer (CO), the term used herein, does not include any representative not acting within the scope of his/her authority. Notwithstanding any of the provisions of this contract, the CO shall be the only individual authorized to in any way amend or modify the terms of this contract.
8.1 Contracting Officer (CO)
Mr. Kurt Armbruster
47 CONF/LGCB
171 Alabama Ave Bldg. 7, Room 125 Laughlin AFB TX 78843-5102 kurt.armbruster@us.af.mil
8.2 Contracting Officer’s Representative
Primary
2d Lt Jordan Sowden
47 CES/CENMP
251 Fourth St.
Laughlin AFB, TX 78843 Office: (830) 298-4916 DSN: 732-4916 jordan.sowden.1@us.af.mil
9.0 ATTACHMENTS
Attachment 1 – Design Drawings, B448 Attachment 2 – B448 Specifications Attachment 3 – LAFB Specific Environmental Requirements Attachment 4 – AETC Installation Excellence Guide Attachment 5 – LAFB Architectural Compatibility Guide Attachment 6 – Laughlin Division 01 Specs MXDP161040 Attachment 7 – UFC 4-022-01 Attachment 8 – Blank Progress Schedule and Progress Report Attachment 9 – Blank DD Form 1354 Attachment 10 – AETC 47 Recovered Materials Determination Attachment 11 – Notification of Compliance with Contract Insurance Req.
Attachment 12 – Financial Responsibility Sheet Attachment 13 – Past Performance Questionnaire Attachment 14 – Wage Determination TX218 mailto:kurt.armbruster@us.af.mil mailto:jordan.sowden.1@us.af.mil
| STATEMENT OF WORK |
| Replace Cooling system, b448 |
| Project Location: Laughlin AFB, TX |
| Base Project Number: MXDP 16-1040 |
| 08 JUNE 2018 |