Attachment_5_B550_Form_66.xlsx

XLSX spreadsheet 54 KB Posted

Attached to
HVAC Interior Renovation/Bldg 550 Federal contract opportunity
Solicitation number
FA302218R0007
Issued by
Department of the Air Force Air Education and Training Command

About this file

Attachment #5: B550 Form 66

View the file

Other files for this federal contract opportunity

Other files attached to HVAC Interior Renovation/Bldg 550, newest first.
File Type Posted
FA302218R0007_Conformed_Copy.pdf PDF
FA302218R0007_Amendment_1.pdf PDF
UEQ_B550-Questions_and_Answers_20180723.pdf PDF
B550_DBSOW_20180721.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
Attachment_2_B550_Drawings.pdf PDF
Attachment_3_Wage_Determination.pdf PDF
Attachment_6_Contractor_Insurance_Certification.pdf PDF
Attachment_1_-B550_DBSOW_21_June_2018.pdf PDF
FA302218R0007,_B550_HVAC_Interior_Renovation.pdf PDF
Attachment_4_DD_1354.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General

SCHEDULE OF MATERIAL SUBMITTALSProject No:Project Title:Date:
FA302218R0007Repair UEQ HVAC/Interior Finishes B5508-Nov-17
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
1Work PlanBASIC4
2Demolition PlanBASIC4
3Construction PlanBASIC4
4As-Built DrawingsBASIC4
5Progress ScheduleBASIC4
6Guarantees and WarrantiesBASIC4

Environmental

SCHEDULE OF MATERIAL SUBMITTALSProject No:Project Title:Date:
FA302218R0007Repair UEQ HVAC/Interior Finishes B5508-Nov-17
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
7Appropriate MSDSBASIC4
8Hazardous Waste ReportBASIC4
9Hazardous Material Report (AF Form 3000)BASIC4
10Recycled Material Report/Construction Debris reportBASIC4
11State Notification for Demolition & Renovation 10 Day NoticeBASIC4
12Disinfection Report for Domestic WaterBASIC4
13EPA Certifications of PersonnelBASIC4
14Air Emission Source SpecificationsBASIC4

Architectural

SCHEDULE OF MATERIAL SUBMITTALSProject No:Project Title:Date:
FA302218R0007Repair UEQ HVAC/Interior Finishes B5508-Nov-17
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
15Architectural DrawingsBASIC4
16Gypsum boardBASIC4
17Acoustical Ceiling SystemBASIC44
18Primer/PaintBASIC444
19Sealant/CaulkBASIC4
20Door(s)BASIC4
21Door hardwareBASIC4
22Door frame(s)BASIC4
23WindowsBASIC4
24CabinetsBASIC444
25CountertopsBASIC444
26Flooring (tile, carpet, etc…)BASIC444
27Wall tileBASIC444
28Cove Base (tile, vinyl, wood, etc…)BASIC444
29Paper Towel DispenserBASIC4
30Waste RecepticleBASIC4
31Soap DispenserBASIC4
32Toilet Paper DispenserBASIC4
33MirrorBASIC4
34Plumbing Fixture(s)BASIC4
35Grab BarsBASIC4
36Equipment ManualsBASIC4
37Test ReportsBASIC4

Civil

SCHEDULE OF MATERIAL SUBMITTALSProject No:Project Title:Date:
FA302218R0007Repair UEQ HVAC/Interior Finishes B5508-Nov-17
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
38Site/Civil Plan and CalculationsBASIC4
39Test ReportsBASIC4
40Equipment ManualsBASIC4

Mechanical

SCHEDULE OF MATERIAL SUBMITTALSProject No:Project Title:Date:
FA302218R0007Repair UEQ HVAC/Interior Finishes B5508-Nov-17
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
41Mechanical Plan and calculationsBASIC4
42Test ReportsBASIC4
43Air Handling UnitsBASIC44444
44Fan Coil Units44444
45Heating and Cooling PipingBASIC4
46Ducting and Ducting DesignBASIC44
47Diffusers/Registers/Grilles/LouversBASIC44
48Direct Digital ControlsBASIC44444
49Testing/Adjusting/Balancing ReportsBASIC4
50Domestic Water Piping, Fittings and HardwareBASIC4
51Water HeaterBASIC44444
52LavatoriesBASIC4
53Water ClosetsBASIC4
54Flush ValvesBASIC4
55UrinalsBASIC4
56Exhaust FanBASIC44
57Hangars and SupportsBASIC44
58FlashingBASIC4
59SleevesBASIC4
60Mechanical Identification/Nameplates/MarkersBASIC4
61Duct/Piping InsulationBASIC4
62Pumps/Pump CurvesBASIC44444
63ValvesBASIC44444
64Equipment ManualsBASIC4
65Test ReportsBASIC4
66Firestopping and AccessoriesBASIC4

Electrical

SCHEDULE OF MATERIAL SUBMITTALSProject No:Project Title:Date:
FA302218R0007Repair UEQ HVAC/Interior Finishes B5508-Nov-17
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
67Electrical Plan and CalculationsBASIC4
68Circuit BreakersBASIC444
69Ground Rods and ConnectorsBASIC4
70Electrical Hangars and SupportsBASIC444
71Electrical Identification/Nameplates/MarkersBASIC4
72Building WireBASIC4
73Raceway and BoxesBASIC4
74Receptacles/SwitchesBASIC4
75MotorsBASIC4444
76FusesBASIC444
77Disconnect SwitchesBASIC444
78Dry-Type TransformersBASIC4444
79LuminairesBASIC444
80Emergency LightingBASIC444
81Communications WireBASIC4
82Communications Circuits Test/Certification ReportsBASIC4
83Test ReportsBASIC4
84Equipment ManualsBASIC4

Special Systems

SCHEDULE OF MATERIAL SUBMITTALSProject No:Project Title:Date:
FA302218R0007Repair UEQ HVAC/Interior Finishes B5508-Nov-17
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
NA

Other & Misc

SCHEDULE OF MATERIAL SUBMITTALSProject No:Project Title:Date:
FA302218R0007Repair UEQ HVAC/Interior Finishes B5508-Nov-17
LINE NO.ITEM DESCRIPTIONSPEC REFNUMBER OF COPIES REQUIREDDATE KTR REQUIRES APPROVALDATE RECEIVED KTRDATE TO CIVIL ENGDATE RECEIVED FROM CEDATE CONTRACTOR NOTIFIED APR DISAPRCONTRACT RESUBMIT DUECONTRACT RESUBMITTAL RECEIVEDFINAL APPROVAL RCVD KTR NOTIFIED
Certificate of ComplianceShop DrawingsSamplesColor SelctionManufacturer's RecommendationsManufacturer's WarrantyCatalog DataOperating InstructionsOther
GENERAL
NA