Solicitation Amendment FA301620B00180005.pdf

PDF 522 KB Posted

Attached to
RPR Chiller Building 10504 Federal contract opportunity
Solicitation number
FA301620B0018
Issued by
Department of the Air Force Air Education and Training Command

About this file

This amendment to a federal solicitation modifies the statement of work and attachments for a project to demo and replace an existing air-cooled chiller at Joint Base San Antonio Lackland in Texas. Offerors must provide all labor, equipment, materials and incidental work to complete the project in accordance with the revised statement of work dated September 4, 2020. Proposals are due by September 14, 2020 at the local Air Force contracting office. The construction wage requirement applies, and the project is set aside for women-owned small businesses. The magnitude of the project is estimated between $500,000 and $1,000,000.

View the file

Other files for this federal contract opportunity

Other files attached to RPR Chiller Building 10504, newest first.
File Type Posted
Attachment 9 - Wage determination TX20200231 Rev28Aug2020.docx DOCX document
Amendment 0006 FA301620B00180006.pdf PDF
Questions and Answers - FA301620B0018.pdf PDF
Attachment 1 - Statement of Work Rev 04Sep2020.pdf PDF
Attachment 7 - Section L Rev2 Sept2020.pdf PDF
Solicitation Amendment FA301620B00180004.pdf PDF
FA301620B00180003.pdf PDF
Solicitation Amendment FA301620B00180002 SF 30 (1).pdf PDF
Solicitation Amendment FA301620R00920001.pdf PDF
Attachment 7 - Section L Rev21Aug2020.pdf PDF
Solicitation Amendment 001 FA301620B00180001 SF 30 (1).pdf PDF
Attachment 3 DD 1354 5_4_2020 2.pdf PDF
FA301620B0018.pdf PDF
Attachment 4 climo 8_10_2020 1.pdf PDF
Attachment 6 Asbestos Survey 2020 6_17_2020 8.pdf PDF
HVAC Chiller Justification and Approval.pdf PDF
Attachment 1 statement of work 6_17_2020 306.pdf PDF
Attachment 2 Submittal Register 5_4_2020 32.pdf PDF
Attachment 10 - Construction Cost Estimate Breakdown - 8_11_2020 - NA.xls XLS spreadsheet
Attachment 9 - Wage Determination TX20200231 - 2_14_2020 - 7pgs..pdf PDF
Attachment 8 - Section M - 8_10_2020 -- 3pgs..pdf PDF
Attachment 5-- Backflow Device Test Form - NA -- 1pgs..pdf PDF
Attachment 7 - Section L-- 8_10_2020 -- 2pgs..pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section B - Supplies or Services & Prices or Costs

The following CLIN(s) / SLIN(s) were modified:

0001 - RPR Chiller B10504:

The contractor is to provide all labor, equipment and materials to demo and replace the existing air cooled chiller, DDC EMCS sensors, limited piping, expansion take, air separator, chill water valves, actuators, pipe and supports, gauges, thermometers, electrical circuits, switches, conduit, conductors, components, appurtenances necessary and incidental related work IAW SOW Rev 04Sep2020. This is a brand name requirement for Trane HVAC equipment.

INFORMATION FROM TO

Description

RPR Chiller B10504:

The contractor is to provide all labor, equipment and materials to demo and replace the existing air cooled chiller, DDC EMCS sensors, limited piping, expansion take, air separator, chill water valves, actuators, pipe and supports, gauges, thermometers, electrical circuits, switches, conduit, conductors, components, appurtenances necessary and incidental related work IAW SOW dated May 2020. This is a brand name requirement for Trane HVAC equipment.

RPR Chiller B10504:

The contractor is to provide all labor, equipment and materials to demo and replace the existing air cooled chiller, DDC EMCS sensors, limited piping, expansion take, air separator, chill water valves, actuators, pipe and supports, gauges, thermometers, electrical circuits, switches, conduit, conductors, components, appurtenances necessary and incidental related work IAW SOW Rev 04Sep2020. This is a brand name requirement for Trane HVAC equipment.

Section F - Deliveries or Performance

The delivery information for the following CLIN(s) / SLIN(s) were deleted:

0001 - RPR Chiller B10504:

The contractor is to provide all labor, equipment and materials to demo and replace the existing air cooled chiller, DDC EMCS sensors, limited piping, expansion take, air separator, chill water valves, actuators, pipe and supports, gauges, thermometers, electrical circuits, switches, conduit, conductors, components, appurtenances necessary and incidental related work IAW SOW dated May 2020. This is a brand name requirement for Trane HVAC equipment.

Period of Performance

Section J - List of Attachments

Miscellaneous text in this section has been modified to:

Tittle -- Date -- Pages Attachment 1-- Statement of Work Rev 04Sep2020 -- 311 pgs.

Attachment 2-- Submittal Register - 5_4_2020 -- 32 pgs.

Attachment 3-- DD 1354 - 3_3_2020 -- 2 pgs.

Attachment 4--climo - 8_10_2020 -- 1pgs.

Attachment 5-- Backflow Device Test Form - NA -- 1pgs.

Attachment 6-- Asbestos Survey 2020 - 6_17_2020 -- 8pgs.

FA301620B00180005

Attachment 7 - Section L Rev2 Sept2020 - 3 Pgs Attachment 8 - section M - 8_10_2020 -- 3pgs.

Attachment 9 - Wage Determination TX20200231 - 2_14_2020 - 7pgs.

Attachment 10 - construction cost estimate breakdown - 8_11_2020 - NA

FA301620B00180005

IDCode:
Page: 1
Pages: 3
AmendNo: 0005
EffDate: 9/2/2020
ReqNo: F2M3CC0058AW02
ProjNo: MPLS203738-1093738
IssCode: FA3016
AdmCode:
IssuedBy: FA3016 502 CONS CL

1655 SELFRIDGE AVE BLDG 5450

CP 210-671-3617

JBSA LACKLAND, TX 78236-5286

United States Carlie Hammontree, Email: Carlie.Hammontree@us.af.mil Telephone: 210-671-1712

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA301620B0018
SolDate: 8/13/2020
AwardChg:
AwardNo:
AwardDate:
Amended: 1
OffrExt:
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G
ChgeOrd:
ChgeOrder:
Modify:
SuppAgre:
SuppAuth:
ModOthr:
OthrSpec:
NoReq: 1
Require:
Copies:
Descript: The purpose of this amendment is:

1) To correct the due date of proposals previously stated in Amendment 0004. Proposals due date is as originally stated in the SF1442 on Monday September 14, 2020 at 10:00 a.m. local San Antonio, TX time.

2) To incorporate the revised SOW/Specifications (Attachment 1 - Statement of Work Rev 04Sep2020) into Section J of the solicitation.

All other terms and conditions of the solicitation as amended remain unchanged.