Atch_6_Progress_Schedule.xlsx
XLSX spreadsheet 24 KB Posted
- Attached to
- Fire Suppression System. bldg 61
- Solicitation number
- FA301618R0072
About this file
Attachment 6, Progress Schedule Example
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Atch_2,_Wage_Determination_July_6,_2018.docx | DOCX document | |
| RFP_FA301618R0072_Amendment_0002_signed.pdf | ||
| RFP_FA301618R0072_Amendment_0001.pdf | ||
| Atch_1_Statement_of_Work_12Jul2018.docx | DOCX document | |
| Site_Visit_Questions_and_Answers.docx | DOCX document | |
| Atch_4,_AETC_Form_47.pdf | ||
| RFP_FA301618R0072.pdf | ||
| Atch_1,_Statement_of_Work.docx | DOCX document | |
| Atch_7_Local_Information.pdf | ||
| Atch_3,_Base_Access_Request_Form.pdf | ||
| Atch_2,_Wage_Determination.docx | DOCX document | |
| Atch_9,_Draft_DD_Form_1354.pdf | ||
| Atch_5,_HAZMAT_Letter.pdf | ||
| Atch_10,_Cost_Estimate_Breakdown.xls | XLS spreadsheet | |
| Atch_8,_Project_Location.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals
| 1. CONTRACT NO. | 8. PROJECT TITLE: Repair South Switching Station | 10. APPROVAL RECOMMENDED BY | |||||||||||||
| FA3016-18-C-XXXX | DATE SIGNED | ||||||||||||||
| 3. COMPLETION DATE: | 9. SUBMITTED BY: | ||||||||||||||
| 4. PURCHASE REQUEST NO. | Contractor's Name | DATE SIGNED | CONTRACTOR'S SIGNATURE | 11. APPROVED BY | |||||||||||
| 5. PROJECT NO. | Contractor's Address | DATE SIGNED | CONTRACTING OFFICER'S SIGNATURE | ||||||||||||
| 6. ACTUAL STARTING DATE: | Contractor's Address | ||||||||||||||
| 7. ACTUAL COMPLETION DATE: | |||||||||||||||
| LINE NO. | WORK ELEMENTS | % | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | Jun |
| A | B | C | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 | 2018 |
| 1 | Bonds | 2.00% | 2.00% | ||||||||||||
| 2 | Schematic Drawing | 5.00% | 5.00% | ||||||||||||
| 3 | Site Prep | 13.00% | 13.00% | ||||||||||||
| 4 | Construction | 60.00% | 60.00% | ||||||||||||
| 5 | Cleanup | 15.00% | 15.00% | ||||||||||||
| 6 | Contract Closeout | 5.00% | 5.00% | ||||||||||||
| 7 | |||||||||||||||
| 8 | |||||||||||||||
| 9 | |||||||||||||||
| 10 | |||||||||||||||
| 11 | |||||||||||||||
| 12 | |||||||||||||||
| 13 | |||||||||||||||
| 14 | |||||||||||||||
| 15 | |||||||||||||||
| 16 | |||||||||||||||
| 17 | |||||||||||||||
| 18 | |||||||||||||||
| 19 | |||||||||||||||
| 20 |
| 100.00% | |||||||
| MONTHLY TOTAL: | 7.00% | 73.00% | 15.00% | 5.00% | 100.00% | ||
| ACTUAL PROGRESS: | 7.00% | 80.00% | 95.00% | 100.00% | 100.00% | ||
| Highlighted areas to be completed by the contractor; dates and percentages contained are for format example only |
FA301618R0072 Attachment 6