PROJECT NUMBER: PROJECT TITLE: SOLICITATION/CONTRACT NUMBER:
SCHEDULE OF MATERIAL SUBMITTALS JBSF122000D REPAIR ROOF, B2735
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED
L
IN
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM,
CONTRACT REFERENCE, TYPE OF
SUBMITTAL
C
E R
T
IF
IC
A
T
IO
N O
F
C
M
P L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L E
C T
IO
N
M A
N U
F A
C T
U R
E R
'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S
W A
R R
A N
T Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
IN
S
T R
U C
T
IO
N S
D O
C U
M E
N T
E
L E
C T
R O
N
IC
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N
D A
T E
D A
T E
R E
C E
IV
E
D I
N
C O
N T
R A
C T
IN
G
D A
T E
T O
C
IV
IL
E N
G
IN
E E
R
IN
G
R E
T U
R N
S U
S P
E N
S E
D A
T E
S U
B M
IT
T
A L N
U M
B E
R S
DATE
CONTRACTOR
NOTIFIED
C O
N T
R A
C T
O R
R E
S U
B M
IT
T
A L
F
IN
A L A
P P
R O
V A
L
REMARKS
APPROVED
DIS-
APPROVED
Contract Progress Schedule AF
Form 3064 (SOW Ref)
Roofing Manufacturers Approved
Installation Drawings (SOW Ref) X 2
3 Safety Plan (SOW Ref) 2
4 Quality Control Plan (SOW Ref) 2
5 Demolition Plan (SOW Ref) 2
Asbestos. Lead Based Paint
Abatement Plan (SOW Ref)
7 Waste Manifests (SOW Ref) 2
8 DD 1354 (SOW Ref) 2
9 Warranty Letters (SOW Ref) 2
10 As-Built Drawings (SOW Ref) X 2
Divison 1 General Requirments
(SOW Ref)
FA3016-17-R-0054 - Attachment 4 Schedule of Material Submittals
NOT ALL INCLUSIVE
PROJECT NUMBER: PROJECT TITLE: SOLICITATION/CONTRACT NUMBER:
SCHEDULE OF MATERIAL SUBMITTALS JBSF122000D REPAIR ROOF, B2735
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR
NUMBER OF COPIES REQUIRED
L
IN
E N
U M
B E
R
ITEM OR DESCRIPTION OF ITEM,
CONTRACT REFERENCE, TYPE OF
SUBMITTAL
C E
R T
IF
IC
A T
IO
N
F
C
M
P L
IA
N C
E
S H
O P
D R
A W
IN
G
S
S A
M P
L E
S
C O
L O
R S
E L E
C T
IO
N
M A
N U
F A
C T
U R
E R
'S
R E
C O
M M
E N
D A
T
IO
N S
M A
N U
F A
C T
U R
E R
'S
W A
R R
A N
T Y
C A
T A
L O
G D
A T
A
O P
E R
A T
IN
G
IN
S
T R
U C
T
IO
N S
D O
C U
M E
N T
E
L E
C T
R O
N
IC
R E
Q U
IR
E
D S
U B
M
IS
S
IO
N
D A
T E
D A
T E
R E
C E
IV
E
D I
N
C O
N T
R A
C T
IN
G
D A
T E
T O
C
IV
IL
E N
G
IN
E E
R
IN
G
R E
T U
R N
S U
S P
E N
S E
D A
T E
S U
B M
IT
T
A L N
U M
B E
R S
DATE
CONTRACTOR
NOTIFIED
C O
N T
R A
C T
O R
R E
S U
B M
IT
T
A L
F
IN
A L A
P P
R O
V A
L
REMARKS
APPROVED
DIS-
APPROVED
Divison 2 Existing Conditions
(SOW Ref)
13 Division 5 Metals (SOW Ref) 2
Division 7 Thermal and Moisture
Protection (SOW Ref)
Division 9 Paints and Coatings
(SOW Ref)
FA3016-17-R-0054 - Attachment 4 Schedule of Material Submittals
NOT ALL INCLUSIVE