MAHG17-1084_Addendum_1.pdf

PDF 11 KB Posted

Attached to
Replace AHUS Federal contract opportunity
Solicitation number
FA3010-18-R-0018
Issued by
Department of the Air Force Air Education and Training Command

About this file

Please see attached

View the file

Other files for this federal contract opportunity

Other files attached to Replace AHUS, newest first.
File Type Posted
Amend_3.pdf PDF
Attachment_11_B6901a.pdf PDF
Attachment_10_MAHG17-1084_Addendum_2.pdf PDF
Amend_2.pdf PDF
Amend_0001.pdf PDF
Sign_in.pdf PDF
Attachment_3_-Wage_Determination.pdf PDF
Attachment_2_-MAHG171084_REPLACE_AHUS_6_7_9_13_B6901_SOW.pdf PDF
Attachment_4_-MAHG171084_REPLACE_AHUS_6_7_9_13_B6901_DWG.pdf PDF
Attachment_5_-_PPQ.pdf PDF
Attachment_6_-_Reference_List.pdf PDF
Attachment_7_-__Notice_of_Compliance.pdf PDF
Attachment_1_-MAHG171084_REPLACE_AHUS_6_7_9_13_B6901_SPEC.pdf PDF
Attachment_8_-_SF_1444.pdf PDF
18R0018.pdf PDF
Synopsis_signed.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM #1 Date: April 19, 2018

PROJECT NAME: REPAIR-REPLACE AHUs 6 7 9 AND 13 BRYAN HALL

LOCATION: Building 6901 – Keesler AFB, Mississippi

PROJECT NUMBER: MAHG 17-1084

This Amendment is hereby part of the Bid/Contract Documents and as must be acknowledged with the Bid. Failure to do so may subject the Bidder to disqualification. The following conditions take precedence over conflict conditions in the Specifications, on the Drawings, and in any other Contract Document. When a change is called for on a Drawing, this change shall carry through all applicable drawings, including all related architectural, civil, structural, mechanical, plumbing and electrical drawings. The Bid/Contract Documents are hereby amended in the following particulars:

DRAWINGS:

SHEET 7 of 7 Note 3: Remove requirement to install new disconnect switches in all three mechanical rooms.

SOW:

3.2.4 SCOPE: Add

“Project is to be phased in order to minimize impact on building occupants. As such, only one working AHU will allowed to be taken out of service at a time.

Contractor will work with owner/occupants to determine order of phasing.”

3.2.4 SCOPE:

PROVIDE AND INSTALL NEW:

Remove requirement for aluminum jacket on new piping.

Remove requirement for new disconnect switches at air handling units.

Add requirement to supply signage for all new piping and duct insulation that states “Asbestos Free”.

ATTACHMENTS:

NONE

END OF ADDENDUM 1