PostedPre-solBriefingPart2of3.ppt

PPT presentation 6 MB Posted

Attached to
SATOC Federal contract opportunity
Solicitation number
FA3002-06-R-0001
Issued by
Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency

About this file

SATOC Pre-solicitation Briefing Slides Part 2 of 3

View the file

Other files for this federal contract opportunity

Other files attached to SATOC, newest first.
File Type Posted
NoticetoContractAwards-28JAN08-SATOC.pdf PDF
NOTICETOOFFERORS2JAN08-satoc.pdf PDF
NOTICETOOFFERORS14DEC07-satoc.doc DOC document
NOTICETOOFFERORS3DEC07-satoc.doc DOC document
NoticetoOfferors-30AUG07-SATOC.pdf PDF
NoticetoOfferors-17JUL07-SATOC.doc DOC document
RFP_Atch789_SectL_Cost_18Apr07_Revised.xls XLS spreadsheet
Amendment0006 20Apr07SF30.pdf PDF
SATOCNoticetoOfferors-29MAR07.doc DOC document
SATOCNoticetoOfferors-18JAN07.doc DOC document
SATOCNoticetoOfferors-01DEC06.doc DOC document
SATOCNoticetoOfferors-19OCT06.doc DOC document
SATOCNoticetoOfferors-06SEP06.doc DOC document
SATOCNoticetoOfferors-05JUL06.doc DOC document
SATOCPPQuestionnaire.doc DOC document
FA3002-06-R-0001Amendment0005RM9MAR06.pdf PDF
Atch4_SectJ_SubcontractingWS7Mar.xls XLS spreadsheet
FA3002-06-R-0001Amendment0004RM6MAR06.pdf PDF
Atch12_SecL_SampleTOSOWmegdtd6Mar06.pdf PDF
IndustryInformation03Mar06.doc DOC document
Amendment0003 SF30.pdf PDF
IndustryInformation28Feb06.doc DOC document
Amendment0002SF30.pdf PDF
WorkingcopyAtch_1_SectL_ChoiceofCompetition.pdf PDF
RFP_Atch3 4_SectL_PPI_PPQ_.pdf PDF
Atch4_SectJ_SubcontractingWS9Feb.xls XLS spreadsheet
IndustryInformation26Jan06.doc DOC document
InformationforIndustry20Jan06.doc DOC document
1_Atch6_SectL_ClientAuthorizationLetter.pdf PDF
1_Atch5_SectL_ConsentLetter.pdf PDF
EXHIBITACDRL-DIDFILE.pdf PDF
1_Atch5_SectJ_dd254.pdf PDF
SampleTOSOW.pdf PDF
FLOOR SITEPLAN.pdf PDF
Atch3 4PPIF PPQ.pdf PDF
FA3002-06-R-0001OfficialRFPRM05JAN06.pdf PDF
RFI-RAH.doc DOC document
NoticetoOfferors-13DEC05.doc DOC document
IndustryInformation23Nov05.doc DOC document
PreSolicitationConferenceFinalAttendeeList.doc DOC document
CommentQuestionform.doc DOC document
Atch3 4_SectionL_PPI_PPQ.pdf PDF
Atch5_SectL_ConsentLetter.pdf PDF
Atch7 8_SectL_LaborRates_Field Home.xls XLS spreadsheet
Atch1_SectJ_SOWdtd23Sep.pdf PDF
DraftRFPCoverLetter.pdf PDF
ExhibitA_SectJ_CDRLS-DIDS_30Sep.pdf PDF
Atch4_SectJ_SubcontractingWS.xls XLS spreadsheet
Atch9_SectL_SATOCCostDetailReport.xls XLS spreadsheet
FBOPostingNotice.doc DOC document
Show all 50

SATOC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

I n t e g r i t y - S e r v i c e - E x c e l l e n c e Headquarters U.S. Air Force

Acquisition Strategy and Draft RFP Discussion

Mrs. Susan Gill

AETC CONS/LGCK

Acquisition Strategy The SATOC acquisition strategy is undergoing internal reviews and approvals. Be advised, the strategy could change prior to issuance of the RFP. If the strategy is altered significantly, you’ll be advised and information will be posted to the SATOC website and Fedbizops prior to publishing the final RFP.

Program Ceiling $10 B
Based on budget forecasts
Unpredictable world events (Rita, Katrina, Iraq)
Other federal agencies allowed to use
Full Trade-Off Source Selection Procedures
Approximately 15-20 awards
Up to five 8(a) Set Aside
Up to one Service Disabled Veteran Owned Small Business Set Aside
Up to one HUBZone Small business Set Aside
Period of Performance
Ordering Period: 5 years plus 5 one-year options
Max Performance completion: 48 months thereafter
TO will specify period of performance

Award by Jul 06

We intend to award without discussions

Number of Contracts

Approximately 15-20 contracts to be awarded
Full and Open
Large business and Small business automatically evaluated
8(a), HUBZone, SDVOSB can elect to compete but must identify their intent to compete
Competitive Set Asides
Up to five 8(a) awards
Up to one HUBZone award
Up to one Service Disabled Veteran Owned Small Business award
Offerors with certifications in multiple small business categories can compete in applicable categories, but must identify their intent to compete

Choice of Competition

Offerors must identify the choice of Competition via Attachment L-1
Full and Open Competition
8(a) Set-Aside Competition
HUBZone Small Business Set-Aside Competition
Service Disabled Veteran Owned Small Business Set-Aside Competition
Total number of awards will be based on the quality and quantity of proposals received

Contract Specifics

Contract Types
Firm Fixed Price (FFP)
Cost Plus Fixed Fee (CPFF)
NAFI CLINS for both types
Indefinite Delivery-Indefinite Quantity
Multiple Awards
Contractual Minimum Guarantee, Initial TO $2,500.00
SATOC Contractor School (SOW, Atch L-2)
Minimum TO size will be $20,000.00
Historical CONUS Average TO Size $ 730,000.00
Historical Min/Max TO $62K - $6.4M
Maximum TO size will be $50 Million

Teaming

Prime Contractors
Fully responsible for contract performance and submittals
Shall identify teaming partners
Each team partner must have TA/LOI provided in Vol 1, Contracting
Subcontractors without a TA/LOI will not be considered or evaluated as part of the team
Team members will be written into the contract, reference H013, Teaming Arrangements
CO must approve any deviation from teaming arrangement
Prime can only be awarded one contract as a prime or as part of a Joint Venture

Bonding

FAR 28.102-3 – Performance and Payment Bonds required for construction contracts greater than $100,000
52.228-15 Performance and Payment Bonds, Construction
Exceptions
DFARS 228.102
Waives performance and payments bonds for cost-reimbursable contracts however,
Prime must obtain from each of its construction subcontractors performance and payments bonds for construction subcontracts greater than $100,000 in accordance with DFARS 228.102-1.

Bonding

Miller Act allows CO to waive requirement for performance and payment bonds for any construction contract greater than $100,000 for work in a foreign country
Will be determined at TO level

Terms/Conditions

H016, Performance Agreement
Contractor agrees work will be performed in any location where AFCESA customers have needs; including remote, austere and hostile environments or,
Contractor agrees work will be performed in any location where AFCESA customers have needs, but will not work in hostile environments
Be sure to complete and include in Vol 1, Contracting
H015 – Key Personnel proposed are written into the contract
Program Manager, Program QA/QC Manager, Program Construction Manager and Program Health and Safety Manager
ACO and PM notified of changes 10 days in advance and gov’t reserves the right to reject proposed change
H038, Status of Forces Agreements –
Incorporated at Task Order level

Fair Opportunity

H032 Fair Opportunity
Each order >$2,500, each awardee provided a fair opportunity and is considered
Exception: Urgency, highly specialized capability, logical follow-on or satisfying a minimum guarantee
Gov’t will first evaluate data already previously obtained
Original proposal data
Past performance
Awardees capabilities regarding functional or technical aspects of requirement
Other factors determined by CO
Gov’t may request additional data

Fair Opportunity

After proposals requested and received
Integrated evaluation will be conducted
Past Performance
Technical and/or managerial expertise
Cost/price
Capacity
Small Business Subcontracting Participation
Other factors added by CO

Pre-Award Reviews Offeror’s without an approved accounting system should request a review through the SATOC website or by contacting the CO

All offerors and teaming partners performing more than 20% or more of the work – register on SATOC website for Financial Review

Schedule Milestone Dates (dates are approximate and subject to change without notice)

RFP Release 15 Dec 05
Past Performance Information 30 Jan 06
Due Government
Proposals Due15 Feb 06
Awards Jul 06

Headquarters U.S. Air Force

Scope of Work and Evaluation Criteria

Mr. Frank Simas, P.E.

Chief, S/R&M Pavements Division

SOW Overview Work Classification

S/R&M Requirements
Programs
Approvals

Construction Requirements

Delivery Types

Work Classification Three general categories:

Maintain

Repair

Construct

Work Classification describes the nature of work to be accomplished on facilities and infrastructure.

Maintain / Sustainment

Work required to preserve real property systems or components and prevent premature failure or wearing out of the same. Includes work to prevent and arrest component deterioration, as well as landscaping or planting work which is not capitalized.
Protective Coatings (Paint)
Landscaping
Cathodic Protection
Fog/Chip Seal or Pothole repair

Source: AFI 32-1032

Repair / Restoration

Work to restore real property systems or components to such condition that they may effectively be used for their designated functional purposes. …Need not have failed to permit a repair project.
Repair by replacement
Rectify Code Deficiencies
All Interior Rearrangements (including load-bearing members)
Utility Modifications for Current Usage
Installation of Mezzanines
Replacement of roofs, utility systems, pvmts
Force Protection

Construct / Modernization

To build, develop, convert, or extend real property systems or components
Creating new or enlarging (volume or footprint)
Facility Replacement
Conversion (change in functional use)
Installing Air Conditioning
Relocating Facilities
Upgrading surface of unpaved transportation systems
Repair that entails complete replacement of vertical section of building AND includes a substantial portion of its foundation

Air Force Programs

Plan Identify Rqmts Develop Scope Develop Cost Economic Analysis

Maint Repair Const

P-341 Classify Work Select Program Avenue O&M

MILCON

NAF

MFH

Execution Vehicles

Determine Fund Source

APF

NAF

Validate

SATOC

HERC

Multi

DBP03

Approval Authorities

$5 M $750K

SAF/IEI

Const

MAJCOM

Congress/MILCON Const Rpr Maint

MAJCOM

Congress $7.5 M Install/CC

S/R&M Requirements Outlook

FY 07-11 FYDP for Restoration and Modernization
Approximately $4B

Sustainment is much larger however primarily locally executed

Defense Energy Support Center
$80 - $250M year estimated
Contingency / Disaster Response
Unpredictable

SATOC Construction Requirements SATOC is a construction contract

A Project Management Plan (PMP) is required for all task orders
WBS
Quality Control and Health/Safety Plan
Project Schedule
Additional requirements are listed in the SOW

Construction Management and Documentation

Site security and safety
Remote, Austere, and Hostile Locations Possible

Delivery Types

Turn – key
Manage/coordinate all facility delivery activities
Design Build / Design Build Plus
Professional AE services and CD assist
Concept Work Plan / Implementation Work Plan
SATOC contractor not AE of Record

Traditional Construction

Maintenance activities

Mission Capability Evaluation Criteria

1.1 Resources

1.2 Management Approach

1.3 Sample Task Order

1.4 Small Business Participation

Sub-factors 1.1 and 1.2 are equally important. Sub-factor 1.3 is less important than 1.1 and 1.2. Sub-factor 1.4 is less important than 1.3

Sub-Factor 1.1 - Resources Key Personnel

Prime Resources

Team Resources

Geographically Dispersed

Remote, Austere, and Hostile capabilities

Bonding Capacity

Key Personnel

Program Manager
Technical bachelor’s degree
Program Management Experience
10 years minimum
7 years minimum in construction
4 years minimum in DoD construction
Professional registration requirement removed

Will be evaluated using resumes and organizational chart

Desirables: None

Program Construction Manager
Bachelor’s degree requirement to be removed
Construction Management Experience
10 years minimum construction experience
5 years minimum in construction management
4 years minimum in DoD construction

Will be evaluated using resumes and organizational chart

Desirables: Bachelor’s degree

> 15 years construction experience

Program QA/QC Manager
Bachelor’s degree in technical field
8 years of additional experience can substitute
QA/QC Experience
10 years minimum construction experience
5 years minimum in construction QA/QC

Will be evaluated using resumes and organizational chart

Desirables: > 15 years construction experience

Program Health and Safety Manager
Bachelor’s degree in relevant field
8 years of additional relevant experience can substitute
Health and Safety Experience
10 years minimum construction experience
5 years minimum in construction health and safety

Will be evaluated using resumes and organizational chart

Desirables: none

Bonding Capacity Revised per Industry Feedback

Letter from surety on surety letterhead

Minimum Bonding Requirements (excess):
Full and open competition:$25M
8(A) set asides:$10M
Hubzone:$10M
SDVOSB:$10M

Desirable: Demonstrate capacity above minimum

Team management
CONUS and OCONUS
Geographically Dispersed TOs

Processes to manage QA/QC and Health/Safety

Processes for Cost, Schedule, and Quality management

Evaluated using descriptions provided by offeror

Desirables: Prime using own resources to manage

Sub-Factor 1.2 – Management Approach

Sub-Factor 1.3 - Sample Task Order

Statement of Work
New construction – approx 3000 sf facility
General concept provided
Location: 250 miles from local office assumed

Project Management Plan

Proposal – reasonable estimates
Direct material, labor, equipment costs provided
No need for sub-contract quotes

Implementation Work Plan

Desirables: None

UNKNOWN-0.ppt

Colonel Gus G. Elliott, Jr. Commander, HQ AFCESA

Commander’s Call

GOOD MORNING OR GOOD AFTERNOON, I AM MR. BRIAN LALLY, EXECUTIVE DIRETOR OF HQ AIR FORCE CIVIL ENGINEER SUPPORT AGENCY AT TYNDALL AFB FL.

Briefing Subjects

AF CE Awards Presentation

Unit Compliance Inspection

O&M Sustainment, Restoration & Modernization (SRM) Update

Reach-Back & Call Center Operations

AFCESA CARE Banquet

Civilian Personnel Update

Space Utilization Update

Unit Compliance Inspection

Schedule

Dates/Timeline

Purpose

Areas of Inspection

Monday –

Tuesday –

Wednesday –

Thursday –

Friday --

4 – 8 April

Mon- Friday, 0800-1600??

AFCESA O&M SRM Program

Funding

Transfer SRM to AFCESA

Milestones

OPR: Myron Anderson DSN 523-6470

Supports Back-to-Bases Vision

O&M SRM identified as overlap and shortfall of

FOAs

Aligns more closely w/AFCESA roles and missions

Perfect fit with our subject matter technical experts

Feedback from SRM and POL work, will improve engineering criteria, standards and specifications

Goal: Sustain contractor staffing with 2.5% payment charge to customer

Day-to-Day Construction Management and Inspection = % negotiated

Initiated AFCESA SRM staffing based on $150M workload estimate

DESC will fund 4.5% management fee for POL projects

1 Oct 04

1 Oct 05

Current Projects

MAJCOM

ACC

AMC

AFSOC

AFMC

# Projects

Value (K)

$ 979.4

$ 3,000.0

$ 3,100.0

$ 980.0

Total - $8.1M

AFRC - Youngstown AFRS Tank Repair Project

In Project Development- Cost: $500K+

Initial Operational Capability

Partial staff in place

Use of AFCESA & AFCEE contracts

Does not include overseas MAJCOMs

Full Operational Capability

Full staff in place

AFCESA SRM Full Worldwide Support

Innovation and Expertise

Innovative cost and project tracking software

SRM PMs have direct access to the AF Subject Matter Experts (SME) in the following areas:

Electrical Systems

Roofs

AT/FP

Water/Waste Water Systems

Pavements

Cathodic Protection/Protective Coatings

Fire/Life Safety Engineering

POL Systems

HVAC

Agronomy/ Pest Management

PACES

Lightning Protection/Grounding

Controls

Small Arms Ranges

AFCESA will use the powerful Soloman software to help manage/track essentially all aspects of the SRM program. SME list is typical and may not be all inclusive of the kinds and depth of expertise AFCESA brings to the SRM table.

Contracts Available

Full Architect/Engineering Services and Construction

4P A-E (WORLDWIDE PLANING PROGRAMMING AND DESIGN)

30 Primes

ECOS (ENVIRONMENTAL CONSTRUCTION AND OPERATIONS & SERVICES)

7 Primes

WERC (WORLDWIDE ENVIRONMENTAL RESTORATION & CONSTRUCTION)

27 Primes

AE45PC (MILITARY FAMILY HOUSING A-E)

7 Primes

DBP03 (DESIGN BUILD PLUS 03)

6 Primes

4pae – traditional design services including title 2 ceiling 1.1B-2.75B

ECOS – construction repair force protection and demo. Ordnance removal and disposal energy management and GIS

WERC – construction and engineering services incl. Demo repair emergency response operation and maintenance

AE45PC – design – value engineering condition studies renderings inspection studies pubs guides handbooks

DBP03 – design build

Contacts

CEI Four Divisions

POL/Fuels (CEIF)

Pat Mumme DSN 523-6361

Pavements (CEIP)

Jim Greene DSN 523-6334

Utilities (CEIU)

Mike Giniger DSN 523-6520

Vertical (CEIV)

Norm Fowler DSN 523-6345

This Directorate is divided into four divisions according to work type. Call any one of them for quick answers on how to use our services.

We cost less than anyone else other than your own staff. All POL and Fuels projects are centrally funded from the Defense Energy Support Center (DESC) while all other services cost 2.5% to cover AFCESA’s staffing costs. The team comes to you with the experts to implement your SRM program quickly in a quality manner.

AFCESA Contracting Support

AFCESA Support Flight

SRM/POL

Contract Negotiator

GS-12 (1)

AETC/CONS

1 PCO

1 Attorney

1 Reviewer - Cost/Price Analyst

AFCAP

All Tasks prioritized by and flow through AFCESA Task Leads

AFCESA Task Leaders

SRM/POL/Agency Support Team Lead

GS-13 (1)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

Contract Specialist

GS-11 (1)

Contract Specialist

GS-11 (1)

AFCAP

Team Lead

GS-13 (AFCAP Variance Position)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

Contract Negotiator

GS-12 (1)

AFCESA Task Lead

Current Inbound Staff

Future Projected Staff (#s TBD by workload)

HQ AFCESA/CC

Business Operations Support Directorate

AFCESA Support Flight Chief

GS-14 (AFCAP Variance Position)

Bold Boxes Rep.

18 Permanent Gov’t

Positions Added to AETC UMD

AFCESA Reach-Back & Call Center Support

Provide AFCESA customers streamlined, multi-tiered access to the technical and professional knowledge produced by AFCESA experts.

OPR: Mr. Kurt Bergman, DSN 523-6679

AFCESA Reach Back Center (ARBC)

Capture data from deployed locations/teams

Centralized master deployment library

Site data, joint concepts, lessons learned, and observations

Compliment existing Geo-Initiatives

Create a worldwide peer-to-peer network for expeditionary engineering

Contingency Engineering Support

Portal

Milestones

Provide access to AFCESA experts and knowledge

Via various technologies (forums, phones, email, chat)

Centralized service desk for all support

Information requests tracked from creation to resolution

The right information at the right time

1 Dec 04

1 Mar 05

1 Oct 05

Reach Back Center IOC

“Normal” duty hours

2 Moderators

Expertise Yellow Pages

Centralized contact center

ASK Program FOC

KM processes normalized

K-Map/Database in place

Contingency Engineering Support Site IOC

Contingency support forum

Library - Customer Templates, Flow-charts

The vision for ASK is to create a performance based support environment with the tools and business processes necessary for AFCESA personnel, teams, customers, and communities of practice (CoP) to optimize the effective application of knowledge to assist USAF Civil Engineers with their missions, goals and operational objectives worldwide.

The first year development and deployment of the AFCESA Searchable Knowledge System is focused at putting more validated and actionable information at the disposal of the AF CE career field. This will be accomplished through the creation of the following:

- AFCESA CE Expertise Yellow Pages: A detailed expertise finder for AFCESA SME and a methodology for contacting them

- Centralized AFCESA bulletin board, news letter, calendars, resource scheduling capabilities and virtual online project environments.

- Deployment of a centralized Call Center AFCESA Service desk to provide a single contact point for data requests. Service center will be accessible through various technologies (Internet, Forums, Telephone)

- Deployment of a matured CESS and associated CoPs to put a greater quantity of validated contingency related data and information. Become the repository for AF Contingency Engineering Lessons Learned, deployment data and related information.

What does the “Compliment Existing Geo-Initiatives” mean? ASK program will compliment those on-going efforts (if not already created) on Geo-initiatives such as GEO-Reach, GEO-Base, and GEO-Best, and etc. Basically ASK would not duplicate the same efforts that are already created by these where it can be easily linked to those sites.

AFCEA CARE Banquet

The Commander's Annual Recognition for Excellence Banquet was established to recognize AFCESA's superior performers

When

End of April or 1st Wk of May (TBD)

CEMIRT Facility (TBD)

Recognition Categories

Civilians

Military

Contractors

Special Ind. Unit Spirit Awds

How

Lunchtime event

1200-End of Duty

Family members are invited

Theme—”Excellence in Combat Support”

Games, activities, etc..

Civilian Personnel Update

PURPOSE

Who?

What?

When?

Space Utilization Update

Objectives

Timeline

Current Requirement

New Requirements

Recommended Apportment

27 CEB

57 CEO

CEX

AFCAP

1 CEX (Guardian)

CEX

CE0

1 CEO

Short 30 CEX

1 CEB graphics (in office)

1 CES

3 Knowledge Management in library

1 CE0

CES

CEB

CEX

35 CEI

CEB

CEB

CEX

CE0

Call Center

Puts CEI in one spot but breaks up CEB more. Put contracting far from CEO

This concludes the mission briefing. Are there any questions?