Revised Statement of Work dated 14 August 2019

View the file

Other files

File Type Posted
ADDITIONAL_QUESTIONS_AND_ANSWERS.pdf PDF
Added_1728_DRAWING.pdf PDF
QUESTIONS_WO__66946_Building_upgrades_B1728.pdf PDF
Statement_of_Work_B1728.pdf PDF
Solicitation_-_FA283519RA054.pdf PDF
1728_DRAWING.pdf PDF
Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

For

Repair/Remodel Education Center

Location Building: 1728

By: Mike Schubmehl

WORK ORDER NUMBER: 66946

DATED: 25 March 2019

Revised: 14 August 2019

1. GENERAL INFORMATION:

This project is intended to repair/remodel the education center in accordance with all applicable

National, Air Force, State and local building codes and regulations. This work will consist of supplying/furnishing all labor, materials, tools, equipment, shop drawings, and expenses necessary to accomplish the work described below in compliance with the Commonwealth of

Massachusetts Building Code and Massachusetts General Law requirements, state and federal codes, base standards and manufacturer’s instructions. Where there is a conflict between nationally recognized codes and local codes, the most stringent shall apply. Effective immediately: Due to safety concerns the use of manhole fixed ladders on Hanscom AFB for the purpose of entry or egress is prohibited. The use of an alternative means of entry/egress

(i.e. appropriate portable ladder/personnel lowering device) is authorized.

2. SCOPE: Renovate Building 1728

Part 1: Hallway 140

Remove 11’ of countertop

Remove 11’ of base cabinets

Patch existing wall

Prime and paint walls using 2 coats Navajo white, latex, egg shell finish

Install 11’ of upper wall birch cabinets/raised panel/ HUD/ Soft close doors and drawers

Round silver satin finish pulls

Install fillers as needed

Install 4’ of birch cabinets/raised panel/ HUD/ Soft close doors and drawers/Round silver satin finish pulls

Install 4’ of Formica style countertop on new base cabinets (Color TBD)

Install new toe kick around new cabinets to match cabinets

Install new LED light fixture under cabinet in hallway 140

Install 1 duplex outlet and comm. port at work surface counter

Install 1 duplex outlet and comm. port on wall to accommodate printer and shredder

Install provided carpet tiles as needed around new base cabinets

Part 2

Remove 6’ kitchen counter and sink

Remove 6’ of kitchen cabinets and kitchen upper cabinets

Remove all kitchen plumbing fixtures and hardware (Commercial Grade Chrome)

Remove all vinyl flooring and carpet in kitchen room 126 and room 127

Save carpet tiles for reused in hallway 140 area, around new cabinets

Remove 3 doors and frames in kitchen

Remove door and frame in room 127

Remove 12’ X 8’ of wall that separates kitchen and room 127 for new breakroom/kitchen area

Remove 4 X 8’ of wall that separates kitchen and storage room 126

Remove 6’ X 8’ wall that separates room 124 and 123

Remove fire alarms strobes and horn from hallway save to relocate

Reconnect horn/strobe on opposite wall

Remove 16’ X 8’ of wall that separates hallway and room 124 for new vending area

Remove vinyl flooring in room 124

All new walls to be 5/8” drywall with level four finish

Install 3’ X 8’ of new wall where door was removed between kitchen and room 127

Install 3’ X 8’ of new wall in hallway where door to kitchen was removed

Install 6’ X 8” of new wall in room 124

Prime and paint walls in new vending area and new kitchen/breakroom area using 1 coat of primer and 2 coats of Navajo White latex egg shell finish

Install approximately 42’ soffit where walls removed

Prime and paint soffit to match existing finish

All trim to match existing finishes

Patch and level floor

Install vinyl composition 12”x12” 1/8” thick (Armstrong or approved equal) in new breakroom/kitchen area (Color TBD)

Install approximately 100 sq. ft. of vinyl composition tile 12”x12” 1/8” thick (Armstrong or approved equal) in new vending area (Color TBD)

Install approximately 200 sq. ft. of vinyl composition tile 12”x12” 1/8” thick (Armstrong or approved equal)in new kitchen/breakroom area (Color TBD)

Install new rubber black transition strips where existing carpet meets new VCT flooring

Install approximately 100 linear feet of cove base to match existing

Re-route hot/cold water supply and drain to opposite floor/wall in kitchen

Install 6’ of birch cabinets in kitchen /raised panel/ HUD/ Soft close doors and drawers

Round silver satin finish pulls

Install new toe kick around new base cabinet in kitchen

Install approximately 6’ of solid surface countertop (Corian)with backsplash on top of base cabinet

Properly caulk and seal countertop where it meets the wall (Color TBD)

Install stainless steel sink in countertop

Install all new necessary plumbing fixtures and hardware (Commercial Grade Chrome)

Install 6’ of wall mounted above countertop birch cabinets/raised panel/ HUD/Soft close doors and drawers Round silver satin finish pulls

Install new GFI duplex outlet at kitchen countertop

Install duplex outlet to the right of kitchen cabinets

Install 4 duplex outlets in vending area 1 on each side wall and 2 on back wall evenly spaced

Install 20’8” x 7’ X 9’ acoustic partition in classroom D on existing ceiling mounted track

All removed items will be disposed of properly

Contractor to dispose of all construction debris properly (demo and created) off of

Hanscom AFB

3. GENERAL REQUIREMENTS:

Work includes, but is not limited to the following:

a. Provide resolutions of any technical problems that arise during the construction.

b. Should any change in scope be required, it must be coordinated with the Project POC and approved as a change order prior to performing the change in work.

c. Provide updates to Project POC. Any construction issues, changes to schedule, or schedule slippages with justification must be reported at the periodic updates.

d. The Contractor is solely responsible for compliance with the Occupational Safety and

Health Act of 1974 (OSHA) and the protection of their employees and all sub-contractor employees. In performing work under this contract on a Government installation, the contractor shall report any accidents involving Air Force property/equipment damage, or contractor personnel injuries occurring on the job or an accident resulting in death, injury, occupational disease, or adverse environmental impact to the contracting officer within five days.

e. Complete the “builder data inventory and assessment sheet” for newly installed assets, ensuring the bar code number is attached to the new equipment. Transfer bar codes from any removed equipment to the builder assessment ½ sheet form

f. Provide three (3) copies of O & M manuals and warranty letter

g. Period of Performance 60 days after award of contract

4. ADMINISTRATION:

Points of Contact (POC):

POC: Mike Schubmehl Phone Number. (781) 225-2958

Alternate POC: Roland Hartz Phone Number. (781) 225-5924