FA2521-18-B-0002
ANSWERS 1-21
Refuse Collection & Disposal, PAFB & CCAFS, FL
RFP Section _Page 14________ Paragraph __Item 0021 through 0030_______
SOW/Technical Specification/Drawings paragraph/page _1.1.10 &_1.3.1_______
Other (Specify) __Landfill Tipping Fees_________________________
Question 1: According to the PWS 1.1.10, landfill tipping fees will be reimbursed for tipping fees according to submitted invoices. 1.3.1 states the contractor will be responsible for any permit and fees associated with the use of off-base disposal locations and invoice to CLIN 0021 for reimbursement. We assume this means all disposal fees will be paid based on the total of the landfills ticket fees without contractor markup and at the exact total of fees charged by the landfill. Is this correct? If so, it does not seem it would be necessary for the contractor to place a unit price per ton on the landfill reimbursement line items. For example, if we insert $0.01 per ton to keep our bid low, the government will be required to reimburse based on the landfill charges, per the PWS statements. Please clarify.
Answer 1: The Price Schedule has been updated to reflect the estimated workload for CLINS
21, 22, 23, 24, 25 and 1005. Contractor shall not input unit price these CLINS. The actual price for these CLINS will be paid in full upon receipt of the weight ticket provided with the invoices.
The Price Schedule has been updated to reflect the estimated workload for CLINS 26, 27, 28, 29, 30 and 1006. Contractor shall not input unit price into these CLINS. The actual price for any permit or fee associated with the use of off-base disposal location will be paid according to submitted invoices.
SOW/Technical Specification/Drawings paragraph/page ___1.1.3.2________
Question 2: How many extra Roll Off containers by size will the contractor need to provide, excluding those assigned to permanent locations, in order to have enough to meet special requests for additional temporary containers?
Answer 2: Approximately 7 roll off containers. This is an estimate based on historical special request. This is different than Special Events which are addressed in the PWS and paragraph
1.1.3.1.
SOW/Technical Specification/Drawings paragraph/page _PWS 1.1.3.3.__________
Question 3: Please confirm that the government will provide the Public/Common Use MSW
Receptacles, including the hard poly insert inside of the receptacle. Does the government’s requirement for the contractor to replace the plastic liner mean with plastic bags?
Answer 3: The government will provide public/common use MSW receptacles including the hard poly insert.
SOW/Technical Specification/Drawings paragraph/page ___APPENDIX A, TABLE A1 –
ESTIMATED WORKLOAD DATA, Items 9 & 10____
Question 4: Please confirm that Special Event Containers Pickups/Additional Pickups Unit
Prices relate to Front End Loader Containers only and does not include Roll off Container services.
Answer 4: Only Front End Load Containers are intended for Special Events (IDIQ) as described in PWS Paragraph 1.1.3.1. Front End Load Containers shall be used for Appendix A, Table A1-
Estimated Workload Data, Items 9&10.
Roll Offs are a separate requirement in the PWS in accordance with paragraph 1.1.3.2 which is intended for C&D Debris and Green Waste.
SOW/Technical Specification/Drawings paragraph/page __PWS 1.1.8_________
Other (Specify) _____Government-Approved Containers______________________
Question 5: Please confirm that the contractor can use Slant type, or Flat Top Containers with side doors.
Answer 5: Slant type or Flat Top containers are both acceptable.
RFP Section _Line Items 0002, 0003, 0004, 0005 & 0006_________ Paragraph _page 4 of
100________
SOW/Technical Specification/Drawings paragraph/page ___________
Other (Specify) __Description of Supplies/Services and Attachment 3
Question 6: Can the government identify all Food Waste Collection Stations (Building
Numbers)?
Answer 6: CCAFS: Bldg 88900 (Greenhouse), Bldg 01748 (Cafeteria)
PAFB: Bldg 350 (Riverside Dining Facility), Bldg 732 (Bowling Alley), Bldg 967 (Tides Club), Bldg 1000 (Child Development Center), Bldg 1493 (Marina / Manatee Cove Golf Course), Bldg
1369 (Burger King), Bldg 1364 (Base Exchange)
RFP Section __L-4____Page 97 of 100____ Paragraph _E (ATTACHMENT 5: Refuse
Collection IDIQ Pricing Sheet (IFB attachment 5) with proposed unit pricing for all line items to include the aggregate value of each CLIN and the TOTAL Aggregate Price for ALL CLINs (if multiple CLINS). Submitted spreadsheets will be unprotected and contain NO passwords
Question 7: I did not see a pricing sheet template for this. Does the government want the contractor to provide an Excel format, or template for this requested information? Please clarify
Answer 7: Please submit pricing on the Solicitation Attachment #14 PRICING SCHEDULE
BID FORM REV 1.
SOW/Technical Specification/Drawings paragraph/page__Attachment 3
Question 8: Please explain purpose for the Bid Schedule Base Year Sheet in this Excel file. It does not appear to match the Line Item in structure in Schedule B and it only references the Base
Year.
Answer 8: The CLIN schedule Attachment #14, Pricing Schedule Bid Form Rev 1 has been updated to reflect the correct CLIN structure in schedule B of the Solicitation.
SOW/Technical Specification/Drawings paragraph/page ____PWS 1.1.3.1_______
Question 9: Excluding Front End Load Containers at permanent scheduled locations, how many additional FEL Containers will the contractor need to have on hand to handle Special Event
Placements during peak requirements?
Answer 9: Approximately 10. Historically 8 CY containers are used for special events. The
Contractor shall determine the most efficient size/quantity of containers needed for each event.
This is just an estimate as these containers are needed when special requests are made by the customer. The government will make every effort to provide the contractor with as much notice as possible to coordinate special events.
SOW/Technical Specification/Drawings paragraph/page ___________
Other (Specify) ___________________________
Question 10: The section contains no question.
RFP Section SF 1449 Box 10 and Section L. Paragraph L-1
Question #11: Box 10 of the SF1449 indicates that this acquisition is set aside for HUBZone
Small Business, Section L Para L-1 Pg. 96 states “It is set-aside for competition among small businesses” but does not mention HUBZone. Please confirm that this is a HUBZone Small
Business set aside?
Answer #11: Section L – Instructions to Bidders: L-1, Type of Acquisition: This section has been corrected to read: This acquisition is being conducted under FAR Part 14, Sealed Bidding, procedures. It is a 100% HUBZone Set-Aside competition among small businesses under NAICS
562111, with a size standard of $38,500,000.00.
RFP Section 52.209-7 pg. 41 & 52.209-7 pg. 75 Paragraph _________
Question #12: Clause 52.209-7 is included in the solicitation twice, it is on page 41 and page 75.
Answer #12: Clause 52.209-7 has been deleted from Section K. Clause 52.209-7 is applicable in Section I of this solicitation.
RFP Section _52.212-3 Pg. 45 & 52.212-3 pg.77 Paragraph _________
Question #13: Clause 52.212-3 is included in the solicitation twice, it is on page 45 and page 77.
Answer #13: Clause 52.212-3 has been deleted from Section I. Clause 52.212-3 is applicable in
Section K of this solicitation.
RFP Section 52.212-5 pg.61 & 52.212-5 pg. 63. Paragraph _________
Question#14: Clause 52.212-5 is included in the solicitation twice, it is on page 61 and again on page 63.
Answer #14: Clause 52.212-5(DEV) has been deleted from Section K. Clause 52.212-5 is applicable in Section I of this solicitation.
RFP Section 52.216-1 pg. 66 Paragraph _________
Question #15: The fill in is blank, could you please add the type of contract that the Government contemplates awarding.
Answer #15: The Clause is updated to reflect that this is a Firm Fixed Price contract.
RFP Section _52.217-9 Paragraph (c)
Question #16: Please complete the fill in for the total duration of the contract.
Answer #16: The Clause has been update to reflect this contract has a 5 year ordering period.
RFP Section 52.204-7007 pg.93 Paragraph _________
Question #17: Clause 252.204-7007 Alternate A, Annual representations and certifications, could you please advise whether we are required to complete this clause as well as 52.212-3 Offeror representations and certifications, commercial items, as these seem very similar and both reference the SAM representations and certifications?
Answer #17: Please complete 52.212-3 Offeror Representations and Certifications – Commercial
Items.
RFP Section L pg. 96 Paragraph L-4, 4 c.
Question #18: Paragraph L-4, 4c requires us to provide a Bid Guarantee in accordance with FAR
52.228-1. Per 52.228-1 could you please advise the amount of the Bid Guarantee that is required to be submitted with the proposal?
In addition, We noted that clause 52.228-1 has not been included in Section I of the contract.
Answer#18: Paragraph L-4 Bid Submission, 4c. Attachment 3: Bid Guarantee has been removed in its entirety. FAR 52.228-1 has been deleted.
Amendment #1 shows this as Attachment 3: Section K provisions filled in with ALL required information.
RFP Section L Paragraph L-4, 4e
Question #19: L-4, 4e refers to Attachment 5 “Refuse Collection IDIQ Pricing Sheet (IFB
Attachment 5)” However, Attachment 5 to the IFB is the “Cape Map”. The only pricing sheet attached to the IFB is Attachment 14 “FOUO Pricing Schedule Bid Form” We could not find the referenced Refuse Collection IDIQ Pricing Sheet. Please confirm that we are only required to complete and submit Attachment 14 “FOUO Pricing Schedule Bid Form” or, if this is not the case could you please post the Refuse Collection IDIQ Pricing Sheet?
Answer #19: Attachment #14, Price Schedule Bid Form Rev 1 is the price sheet Section J has been updated as follows:
RFP Section _________ Paragraph ___________
Other (Specify) Attachment 14 FOUO Pricing Schedule Bid Form
Question #20: The CLIN numbers (column A) used in the excel file for all out years (FY 20, 21, 22, and 23) are all the same, 1,6,11,16,21,26 and 31, and do not reference the correct CLIN numbers in Section B of the bid document.
Answer #20: All CLINS and Section B have been reconciled. See Amendment #1.
Attachments Description # of Pages Date
1. Performance Work Statement 12 03 Apr 18
2. SCA WD15-4555 Rev 6 11 11 Jul 18
3. Appendix A, Table A-2/Frequency & Location 4 N/A
4. Patrick AFB Map w/Facilities Numbers 1 Jul 09
5. Cape Canaveral AFB Map w/Facilities Numbers 1 N/A
6. JDMTA Annex Location Map 1 19 Apr 06
7. Malabar Annex Location Map 1 17 Jun 03
8. Patrick AFB Container Storage Area Map 1 N/A
9. Cape Canaveral AFB Container Storage Area Map 1 N/A
10. Cape Canaveral South Gate Area Map 1 N/A
11. Patrick AFB Truck Inspection Gate Map 1 N/A
12. 45 SFS Badge/Visitor Paperwork 1 N/A
13. Green Procurement Forms 3 N/A
14. Pricing Schedule Bid Form Rev 1 1 Spreadsheet N/A
15. Hazardous Materials Form 1 N/A
16. Identified Locations for Performance 1 N/A
17. Question and Answer Template 1 N/A
18. Answers to Questions 1 to 21 7 N/A
RFP Section _________ Paragraph ___________
SOW/paragraph/page: SOW, paragraph 1.1.7, pg.3
Question #21: 1.1.7 States:
“1.1.7. Cubic Yard Capacity. The contractor should assume 8CY containers are needed at all dumpster locations in Appendix A, Table A-2. The contractor is encouraged to identify changes to the capacity of containers and/or pickup frequency to improve the overall efficiency of MSW removal..”
There are some locations at PAFB and CCAFS where other than 8CY capacity containers are currently in service, and over the last several years these have proven to be the most efficient for
MSW removal. Understanding that Performance Objective number 1 of the Service Summary requires the contractor utilize appropriately sized containers to ensure that their capacity is not exceeded, any unnecessary increase in container size at these locations would result in un-used capacity and unnecessarily increase the price of service to the Government. Could you please confirm that it is not the intent of this clause that all containers will have to be 8CY and that the currently sized containers will continue to be acceptable.
Answer #21: 8 CY containers are not required if, smaller, adequately sized containers can meet the capacity and pickup requirements for each specific location as described throughout the
PWS. The intent is to meet the capacity needs for each location. Paragraph 1.1.7 states, the contractor is encouraged to identify changes to the capacity of containers and/or frequency to improve overall efficiency.