Attch_20_Questions_and_Answers__3.docx

DOCX document 20 KB Posted

Attached to
Demolish Heritage Launch Deactivation Delta II Complex 17 (HLDD II CX 17) Federal contract opportunity
Solicitation number
FA2521-16-B-0001
Issued by
Department of the Air Force Space Command

About this file

Attachment 20 Questions and Answers 3 2 pages dated 26 Jul 16

View the file

Other files for this federal contract opportunity

Other files attached to Demolish Heritage Launch Deactivation Delta II Complex 17 (HLDD II CX 17), newest first.
File Type Posted
Record_of_Attendance.pdf PDF
Abstract_of_Bids.pdf PDF
Attch_21_Pre-bid_Site_Visit__2_Attendance_Log.pdf PDF
Attch_1_Demo_HLDII_SOW_Revised_27_Jul_16.pdf PDF
FA2521-16-B-0001-0004_IFB_Demo_HLDD_II_CX_17_Facs_Amendment_4.pdf PDF
Pages_91-100_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_11-20_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_101-110_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_151-160_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_181-190_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_161-170_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_31-40_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_171-180_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_131-140_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_191-199_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_71-80_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_61-70_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_41-50_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_51-60_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_121-130_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_111-120_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_141-150_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_81-90_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_21-30_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_1-10_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Attch_19_CX_Concrete_and_Asphalt_Boundary.pdf PDF
Attch_18_Questions_and_Answers__2.docx DOCX document
FA2521-16-B-0001-0001_IFB_Demo_HLDD_II_CX_17_Facs_Amendment_3.pdf PDF
Attch_15_CX_17_MV_Power_Distro_As-builts.pdf PDF
Attch_17_CX_17_Sanitary_Sewer_As-builts.pdf PDF
Attch_16_CX_17_Fire_Water_As-builts.pdf PDF
Attch_14_Baseline_ACM_Survey_for_CX_17.pdf PDF
Attch_12_Questions_and_Answers.docx DOCX document
FA2521-16-B-0001-0001_IFB_Demo_HLDD_II_CX_17_Facs_Amendment_2.pdf PDF
FA2521-16-B-0001-0001_IFB_Demo_HLDD_II_CX_17_Facs_Amendment_1.pdf PDF
Attch_11_Pre-bid_Site_Visit_Attendance_Log.pdf PDF
Attch_9_GPP_Certification.pdf PDF
Attch_2_Demo_HLDII_Specs.pdf PDF
Attch_7_CECC_Form_3052.xls XLS spreadsheet
Attch_8_Question_and_Answer_Template.docx DOCX document
Attch_10_Badge_Request_45_SFS_Form_V9.pdf PDF
Attch_4_Maps.pdf PDF
FA2521-16-B-0001_IFB_Demo_HLDD_II_CX_17_Facs.pdf PDF
Attch_5_FLSA_WD_05-2117_Rev__18.pdf PDF
Attch_3_Floor_Plans_ _Dwgs.zip ZIP file
Attch_1_Demo_HLDII_SOW.pdf PDF
Attch_6_Haz_Waste_Form.doc DOC document
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA2521-16-B-0001

Demolish HLDD CX 17 Facilities

QUESTIONS AND ANSWERS #3

26 Jul 16 NOTE: The following response to question #94 from Attachment 18 has been revised as follows:

94. Other (Specify) __SOW_________________________ Question: Please clarify what buildings are not in contract.

Answer (REVISED): Attachment #4 Maps lists the buildings to be demolished. The only exception to this is Facility 28420 (listed on page 6 of the attachment) which was identified during the site visit on 08 Jul 16 as no longer to be demolished/included in the contract. The Statement of Work, revised 27 Jul 16 (Attachment #1), also lists the facilities to be demolished (See sec. 3.A.a through f., pages 2-3).

Answers to questions received continued from Attachment 18 are as follows:

95. Other (Specify) __Responses to Questions and Answers_____________ Question: _In reference to the answers provided for question #20, #40, and #66 about protecting pavement / repairing concrete. Since it was assumed the pavement areas might get worse after demolition and they eventually are going to be removed, do we still have to repair? What would be considered damaged if it is going to be removed eventually? It can be assumed most Contractors will be using track equipment / excavators and some cosmetic damage could occur.

Answer: The scope of work for this project does not include the demolition of building 28501, therefore the need to protect the building and any other facility not intended for demolition is a must. The Air Force occasionally repurposes facilities currently included in the Demolition Program. This enables other DoD agencies and commercial launch customers to reutilize them for specific missions.

96. Other (Specify) __Responses to Questions and Answers_____________ Question: Does the asbestos that was identified already in the baseline survey have to be removed or will that be also included in the change order for any remaining such materials?

Answer: All construction material shall be sampled for ACM and abated if present.

97. Other (Specify) __Responses to Questions and Answers_____________ Question: It was stated the Contractor has to perform all utility disconnects. Would the overall scope for the actual disconnects be expounded on? Even with the layout of utilities, it still remains unclear where and how the utilities need to be disconnected and at what points. Do some utilities on site need to remain active?

Answer: See section 3.2 Demolition Requirements:

· Tab A. “Building Demolition: Disconnect, remove or cap, and identify designated utilities a minimum of five feet from building perimeter; remove. Disconnect aerial utilities and remove to source. Remove exterior mechanical/electrical equipment and associated foundations.”

· Tab G. “Misc. Utility Demolition: Remove abandoned above ground piping (steam, chilled water, fuel, etc.), 1/2 to 12 diameter. Remove pipe supports, support bases, and all associated hardware.”

· Tab H. “Misc. Utility Demolition: Underground utilities beyond five feet from building perimeter:

a. Remove designated utility lines and associated valves, fittings, etc. in their entirety. Cap within 18 inches from mains which have been designated to remain.

· Tab I. Misc. Utility Demolition: conform to the requirements of the Standard Plumbing Code (SBCCI).

The utilities will be located and marked by the Government. Utilities outside of the project boundary shall remain active.

No further questions will be answered.

File details come from the government source that posted it. Updated .