Attch_1_Demo_HLDII_SOW.pdf

PDF 191 KB Posted

Attached to
Demolish Heritage Launch Deactivation Delta II Complex 17 (HLDD II CX 17) Federal contract opportunity
Solicitation number
FA2521-16-B-0001
Issued by
Department of the Air Force Space Command

About this file

Attachment 1 Statement of Work - Demo HLDD II Facilities CX-17 7 pages dated 26 May 16 PDF file format

View the file

Other files for this federal contract opportunity

Other files attached to Demolish Heritage Launch Deactivation Delta II Complex 17 (HLDD II CX 17), newest first.
File Type Posted
Record_of_Attendance.pdf PDF
Abstract_of_Bids.pdf PDF
Attch_21_Pre-bid_Site_Visit__2_Attendance_Log.pdf PDF
Attch_1_Demo_HLDII_SOW_Revised_27_Jul_16.pdf PDF
Attch_20_Questions_and_Answers__3.docx DOCX document
FA2521-16-B-0001-0004_IFB_Demo_HLDD_II_CX_17_Facs_Amendment_4.pdf PDF
Pages_91-100_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_11-20_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_101-110_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_151-160_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_181-190_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_161-170_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_31-40_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_171-180_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_131-140_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_191-199_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_71-80_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_61-70_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_41-50_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_51-60_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_121-130_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_111-120_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_141-150_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_81-90_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_21-30_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Pages_1-10_from_Attch_13_Additional_As-builts_for_CX_17.pdf PDF
Attch_19_CX_Concrete_and_Asphalt_Boundary.pdf PDF
Attch_18_Questions_and_Answers__2.docx DOCX document
FA2521-16-B-0001-0001_IFB_Demo_HLDD_II_CX_17_Facs_Amendment_3.pdf PDF
Attch_15_CX_17_MV_Power_Distro_As-builts.pdf PDF
Attch_17_CX_17_Sanitary_Sewer_As-builts.pdf PDF
Attch_16_CX_17_Fire_Water_As-builts.pdf PDF
Attch_14_Baseline_ACM_Survey_for_CX_17.pdf PDF
Attch_12_Questions_and_Answers.docx DOCX document
FA2521-16-B-0001-0001_IFB_Demo_HLDD_II_CX_17_Facs_Amendment_2.pdf PDF
FA2521-16-B-0001-0001_IFB_Demo_HLDD_II_CX_17_Facs_Amendment_1.pdf PDF
Attch_11_Pre-bid_Site_Visit_Attendance_Log.pdf PDF
Attch_9_GPP_Certification.pdf PDF
Attch_2_Demo_HLDII_Specs.pdf PDF
Attch_7_CECC_Form_3052.xls XLS spreadsheet
Attch_8_Question_and_Answer_Template.docx DOCX document
Attch_10_Badge_Request_45_SFS_Form_V9.pdf PDF
Attch_4_Maps.pdf PDF
FA2521-16-B-0001_IFB_Demo_HLDD_II_CX_17_Facs.pdf PDF
Attch_5_FLSA_WD_05-2117_Rev__18.pdf PDF
Attch_3_Floor_Plans_ _Dwgs.zip ZIP file
Attch_6_Haz_Waste_Form.doc DOC document
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CAPE CANAVERAL AIR FORCE STATION

Statement of Work

For Demolish HLDD II Facilities at CX 17

DBEH 08-1616 Demolish HLDD II CX 17A MST, Fac. 28416 DBEH 08-1618 Demolish HLDD II CX 17B Launch Pad, Fac. 28402 DBEH 08-1619 Demolish HLDD II CX 17B MST, Fac. 28417 DBEH 08-1626 Demolish HLDD II Misc. Group 3 DBEH 08-1630 Demolish HLDD II Misc. Group 6 DBEH 13-1500 Demolish HLDD II Misc. Group 10

STATEMENT OF WORK

DEMOLISH HLDD II FACILITIES AT CX 17

DATE: 6 May 2016

1. OVERVIEW

a. The work to be accomplished under the contract is located at Complex 17 (CX 17), Cape Canaveral Air Force Station (CCAFS), Florida. The work involves the demolition of 21 facilities, associated structures, pavement, and site restoration.

b. The contractor shall provide all planning, including work plans and testing, labor, materials, equipment, design and supervision necessary for the Demolition and/or deconstruction of Buildings/ Facilities/ Infrastructure under the Building Demolition contract at Cape Canaveral Air Force Station (CCAFS). All work shall be done in accordance with the requirements contained in the original contract specifications and any drawings that will be attached as required.

c. No alterations, additions, or deletions shall be made unless approval by the Contracting officer is obtained. The contractor shall thoroughly review the request for constructability and advice of possible problem areas prior to negotiations.

d. All work must be IAW Demolition Specifications unless expressed written permission is received from the Contracting Officer for any deviations. Under no circumstances is the Contractor to begin any work on the Delivery Order until the Contracting Officer issues a "Notice to Proceed".

e. Verify all quantities and dimensions. Note any deficiencies in the Government and customers drawings to the Contracting Officer.

f. The Air Force is committed to effective environment compliance and stewardship activities for the Air Force lands to maintain access to the air, land, and water needed to maintain and improve Air Force mission capability. This commitment is accomplished by complying with federal, state, and local environmental statutes and regulations.

Compliance is accomplished under many Air Force programs.

2. SCOPE

The work under this contract consists of furnishing all labor, materials, and equipment and performing all operations in connection with the Building Demolition Contract.

Demolition and/or deconstruction work includes removal, transportation and disposal of all items to be demolished, as well as restoration of site demolition as indicated in specifications.

3. DESCRIPTION OF WORK

A. Demolition and/or deconstruction of indicated facility structures in its entirety including building structures, launch complex structures and other industrial facilities. Demolition and/or deconstruction of indicated facilities shall not be limited to load and non-load bearing walls, floor slabs, interior and exterior stairs, windows, exterior doors and roof systems. Demolition of interior wall assemblies, floor, wall and ceiling finishes, interior door assemblies special construction and building infrastructure. Removal and disposal of hazardous construction materials including but not limited to asbestos-containing materials, lead base paint, and PCBs. Facility demolition and/or deconstruction work shall also include electrical equipment, fire alarm and communication systems as well as mechanical systems, where applicable.

a. DBEH 08 1616 Demolish HLDD II CX 17A MST, Fac 28416:

i. Perform demolition, and removal of approximately 26,482 square feet of steel MST structure. Demolition includes utility disconnects, demolition of underground electrical and umbilical. Sample and abate for asbestos containing material, lead base paint, and PCBs. Permit Required

b. DBEH 08-1618 Demolish HLDD II CX 17B Launch Pad, Fac. 28402:

i. Perform demolition, removal, and site restoration at facility 28402 with associated structures and pavement. Demolition includes utility disconnects, demolition of underground electrical, demolition of foundations, associated pavement, demolition of 6 fire hydrants and associated water valves, demolition of approximately 1700 linear feet of 20 inch fire water line and associated valves, demolition of 4 poles, and demolition of skim pond. Sample and abate for asbestos containing material, lead base paint, and PCBs. Permit Required

c. DBEH 08-1619 Demolish HLDD II CX 17B MST, Fac. 28417:

i. Perform demolition, and removal of approximately 26,482 square feet of steel MST structure. Demolition includes utility disconnects, demolition of underground electrical and umbilical. Sample and abate for asbestos containing material, lead base paint, and PCBs. Permit Required

d. DBEH 08-1626 Demolish HLDD II Misc. Group 3:

i. Facility 28414, Facility 28421, Facility 28423 - Perform demolition, removal, and site restoration of miscellaneous facilities. Demolition includes utility disconnects, demolition of underground electrical, demolition of 2 RP-1 tanks, demolition of foundations and concrete slabs, and demolition of associated structures. CCAFS Asbestos Survey indicates the presence of Asbestos Containing Material at facility 28414.

Sample and abate for asbestos containing material, lead base paint, and PCBs. Permit Required.

e. DBEH 08-1630 Demolish HLDD II Misc. Group 6:

i. Facility 28403, Facility 28404, Facility 28405, Facility 28408, Facility

28409, Facility 28410, Facility 28413, Facility 28419 28422, Facility 28502, Facility 28503, and Facility 28504 - Perform demolition, removal, and site restoration of miscellaneous facilities. Demolition includes utility disconnects, demolition of underground electrical, demolition of foundations and concrete slabs, demolition of associated structures, pipes, 1 fire hydrant/valves, and 4 poles. CCAFS Asbestos Survey indicates the presence of Asbestos Containing Material at facility 28403, facility 28409, and facility 28502. Sample and abate for asbestos containing material, lead base paint, and PCBs. Permit Required.

f. DBEH 13-1500 Demolish HLDD II Misc. Group 10

i. Facility 28420, Facility 36004, Facility 36015- Perform demolition, removal and site restoration of miscellaneous facilities. Demolition includes utility disconnects, demolition of underground electrical, demolition of foundations and concrete slabs, demolition of associated structures. CCAFS Asbestos Survey indicates the presence of Asbestos Containing Material at facility 36004. Sample and abate for asbestos containing material, lead base paint, and PCBs. Permit Required.

B. Ensure asbestos containing material, lead base paint, and PCBs sample results are submitted to the contracting officer.

C. Disconnect and cap utilities and communication conduit 5 feet from building perimeter.

D. Remove all electrical connections back to transformer. Coordinate outage and remove wires to low voltage side of transformer.

E. Contractor shall back fill with compactable materials all holes and other depressions resulting from demolition and/or deconstruction of buildings. Material shall be compacted per demolition specifications.

F. Site restoration: sodding is required for disturbed areas.

G. Demo Location(s) may require special clearance to access; the General Contractor, assigned to that specific project will escort and obtain work clearance.

NOTE: The above general outline of features of the work does not in any way limit the responsibility of the contractor to perform all work and furnish all labor, materials, and equipment required by the plans and specifications.

4. SALVAGE AND DISPOSAL RECORD KEEPING

Contractor shall maintain and submit quarterly and at the completion of the project to the contracting officer a Disposal Log of all materials removed from the job site. This inventory shall include waste materials disposed in landfills and materials reused on the job, sold for salvage and recycled. At a minimum the Contractor shall identify the type of materials, material weight, disposition (landfill or recycle), receiving facility (name, address and phone number). Contractor will take possession of all recyclable material and provide the Government with weight slips for such material.

5. SITE INSPECTION

Contractors are expected to visit the areas of work and verify all conditions and dimensions prior commencement of any demolition work.

6. STORM PROTECTION

Should warnings of high winds or lightning be issued, the contractor shall take every practical precaution to minimize danger to persons, to the work, and to adjacent property.

These precautions shall include closing all openings, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

7. INTERFERENCE WITH STATION OPERATIONS

Permission to interrupt any utility, communication, operational or traffic service or pattern shall be requested in writing at least 3 working days prior to the date of the desired interruption. The Contractor shall receive approval in writing from the Contracting Officer before the requested interruption may be put into effect. Any power outage shall be approved by the Contracting Officer in writing.

8. SAFETY

The Contractor shall perform all excavation according to Occupational Safety and Health Administration 1926 Subpart P.

9. SCHEDULING

The Contractor shall submit a schedule of proposed work to the Contracting Officer using AF Form 3064 for approval. The schedule shall show the proposed activities, including locations where work is planned and planned shutdown of equipment. All work sequencing and phasing is subject to the approval of the Contracting Officer.

10. SUBMITTALS

Five (5) copies of submittal information (or electronic PDF files of the submittal package) for all listed items must be submitted on AF Form 3000. Material submittals must be submitted as a complete package for each specification section, ready for the Contracting Officer's approval (Page 110-111 Demolition Specifications).

10. SITE LOCATION

CX 17 Cape Canaveral Air Force Station, Florida