Attachment 18 Answers to Questions Received 2 16 pages dated 20 Jul 16
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA2521-16-B-0001
Demolish HLDD CX 17 Facilities
QUESTIONS AND ANSWERS #2
20 Jul 16
NOTE: The following response to question #24 from Attachment 12 has been revised as follows:
24. SOW/Technical Specification/Drawings paragraph/page 3, a thru f__ Question: What is the thickness of all concrete and asphalt and what is the exact location for removal.
Answer (REVISED): Thickness of rigid and flexible pavement can be found in Attachment 13 Additional As-builts for CX 17. The pavement demolition boundary is located in the second page of the aerial map of the demolition site. The title of the page is DBEH 8-1618 Demolition HLDD II CX 17B Launch Pad.
Answers to questions received continued from Attachment 12 as follows:
30. SOW/Technical Specification/Drawings paragraph/page 01000, pg 4, sec. 1.04, sub cat. B.__ Question: What license is required for the general demolition portion of the project for an out of state contractor?
Answer: Contractor must have out of state endorsement. To apply for licensure by endorsement, you must:
· Demostrate successful completion of a licensing examination that is substantially equivalent to the Florida examination; or
· Demonstrate that you have an out-of-state license, and that the license requirements were substantially equivalent to Florida’s current requirements.
31. SOW/Technical Specification/Drawings paragraph/page SOW page 3 sect. F.__ Question: 1) Is the entire site to be sod or seed when complete? 2) How long is the contractor to maintain the watering?
Answer: 1) Entire site will be sodded. 2) See Demolition Specification 1.11 Maintenance Service, section A. “Maintain sodded areas immediately after placement until grass is well established and exhibits a vigorous growing condition for three cuttings.”
32. SOW/Technical Specification/Drawings paragraph/page Drawings__ Question: Are there any available drawings for the following bldgs 28404, 28405, 28419, 28421, 28503, 28504, 36015?
Answer: All availabe drawings have been provided. There will be a second site visit available on 26 Jul 16 at 0900 should the site need to be revisited.
33. RFP Section Attachment 1 – SOW Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page ___Pages 2-3________ Question: The SOW for the various building groups reference that “CCAFS Asbestos Survey indicates the presence of Asbestos Containing Material at facility xxxx”. We have been unable to locate the CCAFS asbestos surveys referenced in the IFB package. Can these be provided, or are we only to bid on the sampling activities noted in the SOW and not on abatement?
Answer: See Attachment 14 Baseline ACM Survey for CX 17.
34. RFP Section Attachment 1 – SOW Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page ___Pages 2-3________ Question: The SOW for the various building says to “sample and abate for asbestos containing material, lead baase paint, and PCB’s. How is this to be handled for bid purposes and after award? Are we to bid the sampling only, and any hazardous abatement required based on the sampling will be handled as a change order after award? Note that the walkthrough was not sufficient to determine presence of hazardous materials as this often requires destructive testing to determine presence of asbestos in roofing, drywall, etc. Likewise, presence of lead or PCB in paint is not possible based solely on visual observation.
Answer: A baseline ACM survey has been provided. SOW does indicate to sample and test for ACM, LBP, and PCB. If found, after testing, they may result in a change order.
35. RFP Section Attachment 1 – SOW Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page ___Pages 2-3________ Question: Is PCB paint expected to be found on the MST’s or other facilities? Is there a percentage of steel structure on the MST’s that is known to have PCB’s?
Answer: PCB is likely present, but PCB % content on MST or other facilities is unknown.
36. RFP Section Attachment 1 – SOW Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page ___Pages 2-3________ Question: Is there a required sample frequency or protocol for PCB sampling on the Base?
Answer: All material containing PCB must be sampled within six months of disposal and handled in accordance to 40 CFR 761.
37. RFP Section Attachment 4 - Maps Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page ___Various________ Question: During the walkdown it was noted that surface and “shallow” pipes would need to be completely demolished (removed from the ground), but that “deeper” pipes could be capped and abandoned. Please clarify at what depth below grade piping can be capped and abandoned.
Answer: Above ground pipes identified to be demolished that transition to underground shall be capped at first elbow below grade.
38. RFP Section Attachment 4 - Maps Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page ___Various________ Question: There was some discussion at the pre-bid walkdown regarding extent of site asphalt removal on each pad. This was focused mostly on the Pad B asphalt to the west of the launch structure and was not entirely clear with regards to some of the small spur roads to the east of the pads. Can a map be provided similar to those already in the IFB showing extent of asphalt removal desired at each pad and between the pads?
Answer: See attached map (incorporated into the solication as Attachment 19):
39. RFP Section Attachment 4 - Maps Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page __SOW Page 2/Pad A MST Map__ Question: On pad A, is the umbilical tower to remain when the MST is demolished? The UT is attached to the top/rear of the launcher building and may be difficult to remove without damaging the launcher building. However, it appears that during HURCON conditions the MST was pulled back around the UT and it is unclear if the UT was designed to remain by itself. If the UT does need to be replaced, does it need to be removed by crane to avoid damaging the launcher building?
Answer: Please review SOW under 3. Description of Work, tab a. and c. for demolition of mobile service tower. It includes demolishing the umbilical tower. Ensure that during the demolition of the umbilical tower the launch pad is not subject to damage.
40. RFP Section Attachment 4 - Maps Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page ___Pad A MST Map________ Question: To demolish the MST without damaging the launcher building, the most efficient method would be to roll the MST to the west stops and dismantle it. Does the pavement under that area then need to be protected and/or replaced, or can damaged pavement be cut neatly back and removed?
Answer: Any and all Government property not part of the demolition contract must be protected and repaired if damaged.
41. RFP Section Attachment 4 - Maps Paragraph Various_ SOW/Technical Specification/Drawings paragraph/page ___Pad B MST Map________ Question: On Pad B, there is a cable tunnel descending from the end of the cable chase (the southeast end of the orange strip on the map) to below the launcher building. The tunnel is tall enough for a technician to walk in and 4-5 feet wide, putting the bottom of the tunnel approximately 8-10 feet below grade. Does this entire tunnel structure need to be removed with the Pad B Launcher Building work?
Answer: Demolish the tunnel six feet below grade per demolition specifications section 3.2 Demolition Requirements.
42. RFP Section IFB Section I__ Paragraph Clauses Incorporated by Reference _ SOW/Technical Specification/Drawings paragraph/page ___IFB Page 9 of 39________ Question: Based on the wage rates included, it appears that this IFB is being released as a service contract. Please verify that FAR 52.219-3 Paragraph (d)(1) stating “(1) Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other HUBZone small business concerns;” applies to this solicitation, or if another percentage is applicable.
Answer: This demolition is being treated as a service contract and FAR 52.219-3(d)(1) does apply.
43. RFP Section N/A Paragraph N/A _ SOW/Technical Specification/Drawings paragraph/page ___ ________ Question: Would the Government consider an extension to the IFB date based to allow time to act on any additional information provided in response to Q&A?
Answer: The solicitation was extended to 29 Jul 16 from its original due date of 22 Jul 16. No further extensions are anticipated at this time.
44. RFP Section _SF1442_________ Paragraph __10_______ Question: IAW 13 CFR 125.6 - What is the prime HUBZone contractor’s self-performance requirements for this specific requirement?
Answer: This demolition is being treated as a service contract and FAR 52.219-3(d)(1) states “Services (except construction), at least 50 percent of the cost of personnel for contract performance will be spent for employees of the concern or employees of other HUBZone small business concerns.”
45. RFP Section ___02060__ Paragraph __3.2.F & O SOW/Technical Specification/Drawings paragraph/page Pg 2 para b & d, and pg 3 para e & f Question: Confirm all the foundations for all structures to be demolished are removed to a depth of 6 feet below grade.
Answer: Per the Demolition Specifications section 3.2 Demolition Requirements tab C. “Building Demolition: Remove foundation walls, footings, pile foundations, etc. to a minimum of six feet below finished grade.”
46. SOW/Technical Specification/Drawings para./page Pg 2 para a, b, c, & d, and pg 3 para e & f Question: Will water available to the contractor?
Answer: Yes, water fill stations will be available for contractor.
47. SOW/Technical Specification/Drawings para./page Pg 2 para a, b, c, & d, and pg 3 para e & f Question: Confirm the contractors are responsible for the survey of the HazMat (ACM, LBP, PCB, etc.). If there is HazMat, will it be addressed as a change order?
Answer: Yes, contractor is responsible for ACM, LBP, PCB survey. A baseline ACM survey has been provided. If hazmat is found after testing it may result in a change order.
48. RFP Section _02060____ Paragraph _________ SOW/Technical Specification/Drawings para./page Pg 2 para a, b, c, & d, and pg 3 para e & f Question: Is there any hydraulic fluids in the towers? If yes, who will responsible for removing and disposing it?
Answer: Hydraulic fluid has been removed from the mechanical components.
49. RFP Section ___02223_______ Paragraph ___2.1___ Question: Can we used crushed concrete for backfill?
Answer: No. Only soil material shall be used for backfill process.
50. SOW/Technical Specification/Drawings paragraph/page Page 2 para b Question: Do we have to remove both the asphalt and base, or just the asphalt?
Answer: Remove asphalt and base.
51. RFP Section __02060___ Paragraph __1.3____ Question: Will the demolition plan have to be stamped by a licensed engineer?
Answer: No
52. RFP Section _13285____ Paragraph _________ Question: Will the government perform the air monitoring during abatement?
Answer: No. It is the contractor’s responsibility to conduct air monitoring per demolition Specification section 1.04 Quality Assurance tab A-D
53. RFP Section ___01000__ Paragraph ___3.14__ Question: Will the government salvage any items from the structures after the site visit? Will all the structures/items that was shown during the site visit remain?
Answer: No, the government will not salvage any items from the structures. Review the Demolition Specification section 3.14 Recycled and Salvaged Material.
54. Other (Specify) __Water in pits_________ Question: Will water, that is or could be in the pits be removed prior to the contractor mobilization? If contractor’s responsibility, where can we pump it out to? Does the water have to be tested or sampled prior to dewatering?
Answer: It is preferred to have the contractor empty out the pits when the project starts. There is no guarantee that the pits will remain dry by the time the project starts. The pits contain rain water and/or water that came out of the fire water pipes during capping procedures.
55. RFP Section __01000______ Paragraph _____3.15____ Question: Do we have to have a dedicated on site safety officer, or can they be dual hatted?
Answer: The site safety officer can be dual hatted.
56. RFP Section _02060_________ Paragraph ___3.2.A______ Question: Who is responsible for the disconnects of the utilities?
Answer: Contractor is responsible for utility disconnects. All utilities will be marked by government.
57. Other (Specify) __Road/bridges restrictions_______ Question: Is there any weight/size restrictions for roads/bridges?
Answer: The weight and size restriction for the installation are the same as those of the FDOT.
58. RFP Section ___01000__ Paragraph ___3.14__ Question: Do all the metal from this project have to be DeMil’ed?
Answer: No, the site has already been cannibalized and militarized equipment already been removed.
59. Other (Specify) __Foreign nationals_______ Question: Do all the personnel working onsite have to be US citizens? Can foreign nationals work onsite?
Answer: Non-US citizens can work onsite as long as personnel can legally work in the US. All personnel regardless of nationality will be subject to background check in order to obtain access to the installation.
60. Other (Specify) __Dig days_______ Question: Is this project affected by no dig days?
Answer: Yes approximately 120 days.
61. Other (Specify) __Explosives_______ Question: Can we use shape charge explosives to drop the two (MST) Mobile Service Towers?
Answer: Shape charge explosions may not be used.
62. SOW/Technical Specification/Drawings paragraph/page __Page 2 para b_________ Question: Is the water line to be removed Transite?
Answer: No the water lines are direct burry cast iron pipes.
63. RFP Section __01000___ Paragraph ____3.07 Question: Does the Air Force have an approved Landfill for the concrete or C&D materials or will they have to be hauled off-site at contractors cost?
Answer: The CCAFS no longer has a landfill available for collection of construction debris. Contractor must haul all construction debris off base to an approved landfill site.
64. Other (Specify) __SWMU______________________ Question: Is this site considered a (SWMU) Solid Waste Management Unit?
Answer: No the site has not been used as a SWMU in the past.
65. RFP Section ___02223_______ Paragraph ___2.1___ Question: Does the Air Force have a Borrow Pit for backfill material or will the contractor have to import material as backfill?
Answer: The AF has a borrow pit but the material has already been spoken for. There are two berms between Launch Pad A and B that can be utilized for backfill. All soil material for backfill needs to be provided by the contractor.
66. Other (Specify) ___Floor protection_________________ Question: Will floor protection be required for the demolition of tower 2 to protect the existing asphalt and concrete that remains?
Answer: Launch Pad A pavements need to be protected.
67. Other (Specify) ___Weight of structures_______________ Question: What is the weight of each mobile launch structure 17a and 17b, just the steel mobile structure.
Answer: The approximate weight of the mobile service towers is as follows:
· MST A (Bldg 28416) weighs approximately 800 Tons
· MST B (Bldg 28417) weighs approximately 980 Tons
68. RFP Section ___02060_______ Paragraph ___3.2.C___ Question: Do footings for structures need to be taken out if they are deeper than 6 feet? At the site visit it was stated that footers had to be completely removed but the specs say only to a depth of 6 feet.
Answer: No, 6 feet below grade as per the specs is correct.
69. RFP Section ___02090_______ Paragraph ______ Question: Have any surveys for lead paint been performed? If so, are they available for review?
Answer: LBP and PCB surveys are not available.
70. RFP Section ___13285_______ Paragraph ______ Question: Have any surveys for asbestos been performed? If so, are they available for review?
Answer: Yes, see Attachment #14 Baseline ACM Survey for CX 17.
71. Other (Specify) ACM survey Question: The Documents reference the presence of asbestos-regulated materials that will require abatement compliant with Federal and state regulations. However, we find no survey information on the presence and locations of referenced materials. Please provide the comprehensive survey information that s requisite under NESHAPS prior to demolition being conducted.
Answer: Comprehensive ACM survey is not available. Attachment #14 Baseline ACM Survey for CX 17 serves as a baseline to identify locations where ACM is present.
72. Other (Specify) ACM survey Question: The Documents reference the Contractor will be responsible for PCB, Lead and Asbestos sampling. Yet, there is no protocol or frequency discussed. Also, there is no cost item for this in the bid form. Has the Air Force conducted a survey? Are the results available for bidders? Will the identification of regulated materials result in a negotiated change of conditions and price adjustment?
Answer: LBP and PCB surveys are not available. Baseline ACM survey provided as Attachment #14 indicates facilities that contain such material.
73. RFP Section _3.A.a______ Paragraph Statement of work Question: The launch pad structure and pavement adjacent to MST 28416 are not included in the removal scope of work. Will the Contractor be required to protect these structures from incidental damage that may occur during the course of demolition of MST 28416?
Answer: All government property not included in the demolition contract shall be protected.
74. RFP Section _02060_________ Paragraph _3.2.K________ Question: The specifications call for the full removal of wood friction piles. Please provide drawings showing the location and depth of these piles so pricing may be provided.
Answer: The project scope of work does not include the demolition of wood friction piles. There aren’t any present at the project site.
75. RFP Section _02060_________ Paragraph __3.2.C_______ Question: The specifications call for the removal to a depth of 6 ft of all MST foundations. Please provide structural foundation drawings so that pricing may be provided.
Answer: Structural drawings have been provided. This information can be found in Attachment #13 Additional As-builts for CX 17.
76. RFP Section _02223______ Paragraph _2.1.B_____ Question: May concrete resulting from the demolition be crushed on site and used as fill?
Answer: Crushed concrete may not be used for backfill material. Only soil material is permitted. Fill material shall conform to the definition of satisfactory soil material as defined in AASHTO M 145, Soil Classification Groups A-1, A-2-4, A-2-5 and A-3. In addition, fill material shall be free from roots and other organic matter, trash, debris, frozen materials, and stones larger than 2 inches in any dimension.
Proposed fill material must be sampled and tested by an approved soil testing laboratory, as follows:
· Soil classification, AASHTO M 145
· Moisture-density relations, AASHTO T 180, Method B or D
77. Other (Specify) __SF1442 block 10_________________________ Question: Are total small businesses eligible to submit proposals?
Answer: This acquisition is set-aside for HUBZone small business concerns. Reference FAR clause 52.219-3 for information/details.
78. Other (Specify) __SF1442 block 10_________________________ Question: Due to the magnitude of the project, can the requirement for bidders be moved total small business set-aside?
Answer: No.
79. Other (Specify) __SF1442 block 10_________________________ Question: Due to the magnitude and cost of the project, can the NAICS code be moved to a larger size standard such as 236220.
Answer: No.
80. Other (Specify) __SF1442 block 10_________________________ Question: Can the NAICS code be changed to Service Disabled Veteran Owned Small Business (SDVOSB)?
Answer: No.
81. Other (Specify) __General_________________________ Question: Will there be a second site visit?
Answer: Yes, a second site visit has been scheduled for 26 Jul 16 at 0900. Reference Amendment 2 for details. This second site visit is not mandatory for bidders who attended the first site visit on 08 Jul 16.
82. Other (Specify) __General_________________________ Question: Is there a phasing schedule for any of the work?
Answer: No, there isn’t a phasing schedule but it is recommended to demolish the mobile service tower 28417 before building 28402.
83. Other (Specify) __Schedule_________________________ Question: Is there a schedule available for days we will not be allowed to work? (i.e. launch schedule, schedule of activities or important events, etc.)
Answer: There are 120 non-work days assigned to this project. At this time it would be difficult to predict future commercial launch activities or provide such a schedule.
84. Other (Specify) __SOW_________________________ Question: Please provide section detail for each MST railway and foundation. The intent is to determine depth of concrete?
Answer: Attachment #13 Additional As-builts for CX 17 has been provided with such details.
85. Other (Specify) __SOW_________________________ Question: Will concrete crushing be allowed?
Answer: No, concrete crushing operations take up too much space at the site and require extensive dust mitigation. All concrete debris must be disposed of off-base by the contractor.
86. Other (Specify) __Salvage_________________________ Question: Are there any items, materials, buildings, equipment, etc. that are to be removed by contractor and stored or salvaged and returned to owner?
Answer: No, contractor shall take posession of all material destined for demolition. Please review Demolition Specifications section 3.14 Recycled and Salvaged Material tab A-E
87. Other (Specify) __SOW_________________________ Question: Please confirm the intent for buried piping and cabling within the project limits. Is the contractor required to remove and backfill?
Answer: The only underground piping to be demolished is a 24” cast iron fire water pipe. All pipes within the project boundary that are either above ground or in trenches must be demolished. This includes cables as well.
88. Other (Specify) __Sodding_________________________ Question: Please elaborate on the type of sod and watering requirements, if any.
Answer: Entire site will be sodded. See Demolition Specification section 02938 Sodding where it states Argentine Bahia Grass. Section 1.11 Maintenance Service, section A indicates “Maintain sodded areas immediately after placement until grass is well established and exhibits a vigorous growing condition for three cuttings.”
89. Other (Specify) __SOW_________________________ Question: Are there any tunnels or underground structures/voids present? If so, please indicate the location and details for removal or advise if not in scope.
Answer: There is a tunnel that starts at the launch pad B and heads towards the already demolished blockhouse. This tunnel is identified by the orange line in the site maps provided as Attachment #4 in the IFB package. The tunnel is 7’ wide by 7’-6” deep with a wall/floor thickness of 12”
90. Other (Specify) __SOW_________________________ Question: Please provide specifications for SWPP or erosion control measures, if any.
Answer: See Demolition specification section 01000 3.12 Digging/Excavation Requirements. There will be no discharge of excavation ground water to the sanitary sewer, storm drains, or to the river without prior specific authorization in writing from the Contracting Officer. Discharge of hazardous substances will not be permitted under any circumstances. Construction site runoff will be prevented from entering any storm drain or the river directly by the use of best management practices from the Florida Stormwater Erosion and Sedimentation Control Inspector’s Manual.
91. Other (Specify) __SOW_________________________ Question: Please clarify what concrete and asphalt paving sections are to remain in place.
Answer: See Attachment #19 CX 17 Concrete and Asphalt Boundary. Areas highlighted in blue indicate concrete and asphalt that will be demolished. All other areas will remain.
92. Other (Specify) __SOW_________________________ Question: Please clarify the height of each MST.
Answer: The height of each mobile service tower is 173’-10”
93. Other (Specify) __SOW_________________________ Question: Please clarify the weight of each MST.
Answer: MST A (Bldg 28416) weighs approximately 800 Tons. MST B (Bldg 28417) weighs approximately 980 Tons.
94. Other (Specify) __SOW_________________________ Question: Please clarify what buildings are not in contract.
Answer: Please review Attachment #4 Maps for a list of the buildings to be demolished.