QA__4__Replace_Bldg_1270_Chiller.docx

DOCX document 14 KB Posted

Attached to
REMOVE/REPLACE CHILLER, BLDG 1270 Federal contract opportunity
Solicitation number
FA2517-17-Q-5016
Issued by
Department of the Air Force Space Command

About this file

Q&A #4

View the file

Other files for this federal contract opportunity

Other files attached to REMOVE/REPLACE CHILLER, BLDG 1270, newest first.
File Type Posted
Q&A__3_-_Remove_Replace_Chiller_Bldg_1270.pdf PDF
TDKA141108-SOW_FINAL.docx DOCX document
Q&A_2.docx DOCX document
Question_&_Answers_B1270.docx DOCX document
SOW_Attachment_1_-_Drawings_(adobe_version).pdf PDF
Amendment_01.docx DOCX document
Combined_Synopsis-Remove-Replace_Chiller,_Bldg_1270.pdf PDF
SOW_Attachment_2_-_Generic_Chiller_Layout.pdf PDF
Attachment_2_Price_Template_Remove-Replace_Chiller_Bldg_1270.xlsx XLSX spreadsheet
Attachment_1_-_Remove-Replace_Chiller,_Bldg_1270_SOW_FINAL.pdf PDF
SOW_Attachment_1_-_Drawing.dwg DWG drawing
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace Bldg 1270 Chiller 12 May 17

Question 1: Based on revised SOW and Q&A dated 10 May 2017, there are additional items for clarification:

Paragraph 2.2 calls for new chiller to, “pass all available points through the BACnet controller to the Metasys system.” The integration guide for the chiller listed as the basis of design has approximately 98 points available. Are all of these required? If not, can a points list be provided?

Answer 1: The existing building does not have BACNet communications and to provide BACNet pass through of chiller points would require an overall building EMCS upgrade. The government requires BACNet capability for future HVAC renovations and not a pass through of points. The SOW has been updated to reflect this.

Question 2: Q&A received 10 May 2017, Answer 9 states, “new equipment needs to be run through the sequence of operation including using the Energy Management Control System (EMCS) to enable the unit, activating the stages of cooling and shutting down the unit.” The Contractor wants to ensure the new equipment is supplied in compliance with this requirement. Is a detailed sequence of operation available?

Answer 2: There is no detailed sequence of operation.

Question 3: On typical projects at PAFB, contractors are required to collect Colorado Springs city sales tax for material and equipment. Does this apply for this project?

Answer 3: This is NOT a tax exempt requirement.

Question 4: Is a project specific submittal register available?

Answer 4: No, a project specific submittal register is not available. Please refer to the SOW and solicitation document.