About this file

FAtch06SampleTO1

View the file

Other files for this federal contract opportunity

Other files attached to Systems Engineering and Technical Assistance (SETA) IV, newest first.
File Type Posted
09R0004RFPQnA2.pdf PDF
09R0004RFPQnA1.pdf PDF
09R0004-0004.pdf PDF
09R0004-0002.pdf PDF
09R0004-0001.pdf PDF
FAtch07BCostWkbkCannon.xls XLS spreadsheet
FAtch07ACostWkbkHurlburt.xls XLS spreadsheet
FAtch03LaborCategories.doc DOC document
FAtch04AppCOCONUSLOA.doc DOC document
FAtch08PPQandCvrLtr.doc DOC document
FAtch04AppECDRLS.pdf PDF
FAtch12PPQRecipientList.doc DOC document
FAtch04AppECDRLSA017Add1.xls XLS spreadsheet
FAtch02 Education_Experience.doc DOC document
FAtch09RelevancyMatrix.doc DOC document
FAtch04AppFAcronyms.doc DOC document
FAtch01BLaborRateTableCannon.doc DOC document
FAtch06aSampleTO2.pdf PDF
FAtch05AWD2005-3034Rev9.doc DOC document
FAtch11PPConsentLtr.doc DOC document
09R0004QnASet2.pdf PDF
09R0004QnASet1.pdf PDF
SETAIVIndustryDayAttendeesFinal.pdf PDF
IndustryDaySETAIVSlidesFinal.pdf PDF
Industry Day RSVP List.xls XLS spreadsheet
RSVP Industry Day and DRFP Release Notice.pdf PDF
D1Atch03LaborDescriptions.doc DOC document
D1Atch04AppDAdd07.doc DOC document
D1Atch04AppDAdd03.doc DOC document
D1Atch07BCostWkbkCannon.xls XLS spreadsheet
D1Atch04AppFAcronyms.doc DOC document
D1Atch05BWD2005-2517.doc DOC document
D1Atch05AWD2005-3034.doc DOC document
D1Atch04AppDAdd01.doc DOC document
_DRFP09F0004.doc DOC document
D1Atch04AppEA017Add1.xls XLS spreadsheet
D1Atch04AppEA014Add1.xls XLS spreadsheet
D1Atch12PPQRecipientList.doc DOC document
D1Atch01ALaborRatesHurlburt.doc DOC document
D1Atch04AppDDDFM254.doc DOC document
D1Atch07ACostWkbkHurlburt.xls XLS spreadsheet
D1Atch04AppBLOIBlank.doc DOC document
D1Atch01BLaborRatesCannon.doc DOC document
D1Atch04AppAMissDesc.doc DOC document
D1Atch04AppCOCONUSLOA.doc DOC document
D1Atch06aSampleTO2.pdf PDF
D1Atch11PPConsentLtr.doc DOC document
D1Atch04AppDAdd08.doc DOC document
D1Atch09RelevancyMatrix.doc DOC document
Transmittal Letter for SETA IV Industry Day.doc DOC document
Show all 50

Systems Engineering and Technical Assistance (SETA) IV has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation FA0021-09-R-0004 05 June 2009

Attachment 6

SAMPLE TASK ORDER 1

Performance Work Statement

For Joint Small Unmanned Aircraft Systems (SUAS) Training Center Support

21 April 2009

1.0 DESCRIPTION OF SERVICE

1.1 GENERAL TASK DESCRIPTION. This Performance-based Work Statement (PWS) describes Contractor support to the Air Force, USSOCOM, and AFSOC training/sustainment program development and technical training support. This concept proposes creation of Joint SUAS Training Center-East (JUTC-E) on the Eglin AFB range complex under HQ AFSOC/A3. This center will primarily be for Groups 1-3 “Small” Unmanned Aircraft Systems (UAS) (as identified in Joint Concept of Operations for Unmanned Aircraft Systems, November 2008) but may be used for larger systems and secondary effects training. The stand up of the JUTC-E is based on a three phased approach. Phase one will have an annual student throughput of 250 and ramping up to 500 students in phase three.

Class size is projected to be approximately 10 students a class. There is also a requirement for a deployable Mobile Training Team (MTT). It is envisioned that contract support will augment three existing full time government employees.

Curriculum will include but is not limited to:

1) General aerodynamic, including effects of controls

2) System overview

3) Aircraft and Ground Control Station (GCS) and performance

4) Base mission planning

5) Map/chart reading

6) Navigation

7) Weather considerations

8) Emergency and system malfunction procedures

9) FAA Airspace/Airfield Operations to include, but not limited to: Air Traffic Control (ATC) radio procedures, Visual Flight Rules (VFR), and airspace/frequency coordination/deconfliction procedures

10) Safety of Flight requirements

11) Operational Risk Management (ORM)

12) Hands-on flight operations

13) Maintenance appropriate to the specific UAS

14) Ground safety requirements

15) SOF-specific TTP

16) SOF-specific all-source analysis fusion production TTP

17) SOF-specific security requirements and releasability to foreign nationals

18) Flight and Sensor operations

1.2 REFERENCE. Headquarters Air Force Special Operations Command (HQ AFSOC/A7KQ), Statement of Work, Appendix A, paragraph 1.4, HQ AFSOC/A3, for HQ AFSOC Systems Engineering and Technical Assistance Services (SETA IV) Contract.

1.3 APPLICABLE STATEMENT OF WORK PARAGRAPHS. This task order invokes the provisions of paragraphs 1.3.1., Management and Professional Support Services.

1.4 SPECIFIC TRAINING SUPPORT REQUIREMENTS

1.4.1 The contractor shall provide HQ AFSOC/A3 with specific technical training to support USSOCOM/AF develop, maintain and teach a comprehensive training program for AFSOC Operations and Sustainment of AFSOC SUAS platforms.

1.4.2 The contractor shall be knowledgeable of USSOCOM/AF owned SUAS systems (Raven B, Wasp III, Scan Eagle, Puma, etc), to include both airborne and ground control components. The contractor shall possess a general knowledge of all DOD owned UAS capabilities and organizations.

1.4.3 The contractor shall be familiar with USSOCOM, AF, and AFSOC SUAS organizations, capabilities, and responsibilities. Contractor shall understand SUAS Tactics, Techniques, and Procedures (TTP) and associated security procedures, including Operations Security.

1.4.4 The contractor shall have experience and familiarity with full motion video and Imagery Intelligence

(IMINT).

1.4.5 The contractor shall be knowledgeable of SUAS sustainment, capabilities, policy and procedures.

1.4.6 The contractor shall be knowledgeable of the Instructor System Development (ISD) process and posses academic instructor experience. Contractor shall be knowledgeable in the development of visual instruction aids.

1.4.7 The contractor shall develop a training program and create courseware for training of USSOCOM/AF SUAS Operations and Sustainment in accordance with AFMAN 36-2234 (Instructional System Development). The contractor shall coordinate with the AFSOC/A3 in the development, update, and implementation of a robust and professional USSOCOM/AF SUAS operations and sustainment training program. As a minimum, POIs will include the items listed in paragraph 1.1. CDRLs A001 - Draft Work Plan; A001 – Work Plan; A003 - SUAS Training Curriculum, SUAS POIs, SUAS Visual Instruction Aids)

1.4.8 Contractor shall maintain and update a comprehensive Work Plan, Training Curriculum, and Plan of Instruction (POI) for SUAS training. These deliverables shall be reviewed and updated as required (CDRLs A001 - Draft Work Plan; A001 – Work Plan; A003 - SUAS Training Curriculum, SUAS POIs, SUAS Visual Instruction Aids)

1.4.9 The contractor shall coordinate schedules and record all formal training for the SUAS mission. (CDRL A001

– Monthly Status Report; CDRLs A001 - Draft Work Plan; CDRLs A001 - Work Plan)

1.4.10 The contractor shall maintain FAA Class II Flight Physical in order to instruct and evaluate Groups 1 through 3 SUAS and fulfill the certification requirements for: Basic SUAS Qualification (BUQ), Initial Qualification Training (IQT), Mission Qualification Training (MQT), and Instructor Upgrade Training (IUT).

1.4.11 The contractor shall instruct personnel from across USSOCOM/AF to include mission partners from worldwide locations using the contractor-developed curriculum and training materials.

1.4.12 The contractor shall keep the AFSOC Functional Area Chief (FAC), Contracting Officer’s Representative (COR), and others as designated by the FAC, informed of task status and progress by regular correspondence or meetings. (CDRL A001 – Monthly Status Report)

1.5 DELIVERABLES: The contractor shall provide the following:

CDRL TITLE DATE of 1st Submission As of Date

Date of Subsequent Submission

DIST Copies

A001 Draft Work Plan 20 days after award A/R* N/A A3OU, COR 1 each

A001 Work Plan 20 days after draft approval A/R 20 days after request

A3OU,

COR 1 each

A001 Monthly Status Report 10 duty days after initial full month

End of each month

10th duty day of each month

COR,

A7KQ 1 each

A002 Trip Reports 10th duty day after return

Completion of trip

10th duty day after return

COR,

A7KQ 1 each

* A/R – As required.

1.5.1 CDRL A001 Draft Work Plan. The contractor shall deliver a draft Work Plan outlining the objectives for this PWS within 20 days of award. If any subsequent draft Work Plan revisions are required, they shall be delivered within 10 working days after request. AFSOC/A3 will provide feedback for draft Work Plan within 5 working days.

1.5.2 CDRL A001 Final Work Plan. The contractor shall deliver a final Work Plan outlining the objectives for this PWS within 20 days of Draft Work Plan approval, (5 days for AFSOC/A3 to review, 10 days to finalize). If any subsequent Work Plan revisions are required, then the revised plans shall be delivered by the contractor within 20 days of request.

1.5.3 CDRL A001 Monthly Status Reports. Monthly Status Reports will be on contractor letterhead, and will list previous month’s accomplishments, identified problems/solutions, planned TDY or vacation, etc. Report will also include a summary of activity regarding the draft, update, and approval of deliverables as outlined in Table 1.5

1.5.4 CDRL A002 Trip Reports. Trip Reports will include a list of attendees for meetings, agenda items, and a summary of discussions held are due within 10 days after completion of trips.

1.5.5 CDRL A003 SUAS Training Curriculum, SUAS Plans of Instruction, SUAS Visual Instruction Aids. The contractor shall deliver updates to the SUAS Training Curriculum, SUAS Plans of Instruction, and SUAS Visual Instruction Aids as required. SUAS Visual Instruction Aids topics will include all items listed in paragraph 1.1 of this document to support SUAS training plans. The contractor shall review SUAS Visual Instruction Aids quarterly and update as required. Contractor will adhere to SOF-specific security and releasability requirements for training materials with respect to foreign nationals. Contractor will apply appropriate security markings and adhere to proper handling procedures for training curriculum, SUAS Plans of Instruction, and SUAS Visual Instruction Aids materials.

1.5.6 All CDRLS. HQ AFSOC/A3 shall review and respond with comments or approval of the submittals within 5 workdays of submission for draft and subsequent submissions of deliverables outlined in Table 1.5.

2.0 SERVICE DELIVERY SUMMARY (SDS)

2.1 The service requirements for this Task Order are summarized into performance outcomes that relate directly to mission essential items. The performance thresholds describe the minimum acceptable levels of service. These thresholds are critical to mission success and acceptable (satisfactory) performance. Invoicing is covered in the Management Level SDS.

SDS # Performance Objective PWS Para

Performance Threshold (to receive Satisfactory Rating)

SDS 1

Contractor performance met specifications of the Contract and TO

PWS.

1.3 – 1.11, or identified in TO

Contractor received no more than two (2) written customer complaints for year for basic contractor or per each TO period of performance. Customer complaints were successfully resolved within five (5) workdays of notification, 100% of the time.

SDS 2 Complied with all Security Requirements.

1.4, 1.4.2 –

1.4.10 or identified in

TO

100% of employee clearances are submitted to COR and CO prior to performance start date.

All security requirements must be met and maintained 100% of the time. Zero security violations identified during TO performance.

A003

Update SUAS Training Curriculum, SUAS POIs, SUAS Visual Instruction Aids

A/R A/R 10 days after request A3OU 1 copy

SDS # Performance Objective PWS Para

Performance Threshold (to receive Satisfactory Rating)

SDS 3

Contractor met required delivery schedule. This element applies to contract performance including timely submission of all deliverables identified in the TO.

1.5.10.2 or identified in

TO

No more than one late deliverable semi-annually and no more than five days late. No more than one set of corrections/edits for accuracy or agreed to format quarterly; with all corrections accomplished within two working days.

SDS 4

Contract employee(s) were clearly identified as such while in Government facilities or when representing the contractor during performance of duties outside Government facilities. Check-out procedures were followed.

1.4.1 100% compliance.

SDS 5

Contract employee is customer-oriented and displays a professional and cooperative attitude while performing service for the Government.

1.5.4 100% of the time.

SDS 6 Costs for reimbursable items were accurately estimated and managed.

1.7 & 1.8 or identified in

TO

Costs were managed in a cost-effective manner. Costs incurred were consistent with estimated costs. Cost documentation was adequate and easy to track.

SDS 7

Invoicing is timely and accurate to include submission of supporting documentation required for certification. TOs are promptly closed out after completion.

Section G, Para G–

Invoices were rejected no more than three times in TO period of performance for non-compliance with submission of invoice backup requirements. Final certification delivered 120 days after TO end of performance 100% of the time.

3.0 GOVERNMENT FURNISHED PROPERTY

3.1 Government Provided Equipment/Office. The government shall provide five desks, workspace, utilities, electrical power hookups, personal computers, telephone access, administrative supplies, and all audiovisual projection equipment for on-site personnel. Contractor personnel must follow the standard facility rules and regulations required of government personnel.

3.2 Title of Documentation. The Government will furnish or make available to the contractor any documentation deemed necessary by the Government to accomplish this task. Where access is determined necessary to other government activities or agencies, HQ AFSOC/A3 will resolve access issues to assist in the task accomplishment.

4.0 GENERAL INFORMATION

4.1 SCHEDULE. The contractor shall perform this task from 01 Dec 09 through 30 Nov 14, with a one-year base period and four one-year options.

4.2 DATA. The Government has unlimited rights to all deliverables of this Task Order. Specific contract efforts and accomplishments under this Task Order shall be included in the applicable CDRL(s) listed above.

4.3 MANAGEMENT

4.3.1 Functional Director (FD). The FD for this Task Order is AFSOC/A3, Hurlburt Field, FL 32544. Telephone:

Commercial (850) 884-XXXX or DSN: 579-XXXX.

4.3.2 Contracting Officer Representatives (CORs). The following individuals will perform Primary and Alternate COR duties as assigned by the FD. The contractor’s Program Manager shall take reasonable steps to allow CORs unrestricted and unhampered access to contractor employees accomplishing duties associated with this Task Order.

4.3.2.1 Primary COR: Mr. Bradley Pufpaff., AFSOC/A3OU, 100 Bartley St, Suite 113W Hurlburt Field, FL 32544. Telephone: Commercial: (850) 884-1546 or DSN: 579-1546.

4.3.2.2 Alternate COR: Mr Marcus Dieters, AFSOC/A3OU, 100 Bartley St, Suite 113W Hurlburt Field, FL 32544.

Telephone: Commercial: (850) 884-1545 or DSN: 579-1545.

4.4 TRAVEL. Travel outside the local area may be required to support the requirements of this task order. All travel must be directed and approved in advance by the COR, and shall not exceed the travel line item funding for this requirement. Travel shall be reimbursed in accordance with the requirements of Special Contract Requirement H-0012, Allowable Travel Cost. Contractor personnel are not authorized to travel on Government invitational travel orders. Trip reports will be provided as required in paragraph 1.5, Deliverables.

4.5 SECURITY INSTRUCTIONS. Contractor personnel will have a minimum of a SECRET clearance at the start of performance. The contractor shall have the ability to qualify for and maintain eligibility for access to TS/Sensitive Compartmented Information (SCI); or possess a single scope background investigation (SSBI) within the last five years; or currently be indoctrinated for SCI. Refer to the DD Form 254 prepared for this requirement for additional security requirements

4.6 DUTY INFORMATION. In accordance with the Basic SETA IV Contract, paragraphs 4.1 and 4.2, the contractor's work hours and place of performance are listed below.

4.6.1 Place of Performance: Eglin Air Force Base range complex. Telephone: Commercial: (850) 884-XXXX or

DSN: 579-XXXX.

4.6.2 Duty Hours: Normal duty hours are Monday - Friday 0730-1630. On occasion, the training schedule will require alternate work days and work hours. In such cases, compensatory time will be utilized as to not exceed a normal 40-hour work week.

4.7 ESSENTIAL SERVICES. The services under this task order are not essential for performance during crisis according to DODI 3020.37.