Exhibit_J_CO1_-_PCS-22-124_Homolovi_WWS.pdf
PDF 6 MB Posted
- Attached to
- Master Agreement AZ|CTR075666
- Contract number
- CTR075666
- Issued by
- Arizona
About this file
This document is a comprehensive set of change orders and contract amendments for the Homolovi Ruins State Park Water and Wastewater Infrastructure Upgrades project in Arizona. The primary parties involved are the Arizona Department of Administration (ADOA), Standard Construction Company, Inc. as the contractor, and Valentine Environmental Engineers, LLC as the design professional. The project is located at Homolovi Ruins State Park in Winslow, Arizona, and is being executed under contract number CTR075666.
The change orders detail several significant modifications to the original project scope, including consolidating existing waterlines around a campground restroom, replacing damaged septic distribution boxes, adjusting sewer pipe sizes, modifying waterline tie-ins, and adding weather protection for a booster pump station. The total contract value has increased from $1,619,323.91 to $1,722,046.02 through four change orders totaling $102,722.11. These changes were necessitated by unforeseen site conditions, such as discovering multiple waterlines, damaged infrastructure, and the need for additional equipment protections. The changes also extended the project timeline by 2 calendar days and involved detailed investigations and modifications to existing utility systems at the park.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit J
Construction Contract Change Order Summary No. ____
Contract No. Contract Amendment No:
Project Name: State Project No: Statutory Review No:
(if different from Project No.)
Design Professional: Contractor: State Project Manager:
ALL OTHER REQUIREMENTS, SPECIFICATIONS, TERMS AND CONDITIONS REMAIN UNCHANGED
ACKNOWLEDGEMENT AND AUTHORIZATION
This Change Order shall modify the Contract only upon the signed approval of the Contractor, Design Professional and State Procurement Officer as specified in the signature block. When signed by all parties, this Change Order becomes effective immediately and the Contractor shall proceed with the change(s) identified and approved.
Page | 1 of 1
1. Check box(es) below best describing the Construction Change Order to the Contract:
☐ Contractor cost increase to Contract due to Additional Work.
☐ Contractor cost reduction to Contract.
☐ Contractor to increase number of calendar days to date of Substantial Completion of the Project.
☐ Use of Contingency ☐ Other (Provide Description) _______________________________________________________________.
2. Contractor shall provide complete description of reduced or Additional Work, including documents in support of the Change Order (e.g., drawings, material substitution literature, cost reduction or increase detail including breakout of labor, materials, markup and tax). Contractor shall use the Construction Change Order Worksheet (Exhibit J1) to provide a detailed breakdown of any change to the Project Cost.
3. By signing and executing this Change Order, the Contractor and Agency agree to a price for the Additional Work, as detailed below. This price shall cover any and all Costs associated with the Additional Work including, but not limited to, Costs associated with delay of the Contractor's Work, if any.
Should the Additional Work impact the Schedule, the Agency and Contractor have agreed to extend the date for Substantial Completion as reflected below.
4. Contractor agrees that the payment authorized by this Change Order, if any, is in full settlement of any and all causes of action, including but not limited to, any claim resulting from delays to the time to Substantial Completion caused by this Change Order which Contractor or any of its Subcontractors, suppliers and the officers, agents, and employees of each of them, may now have or may assert in the future against the Agency, or its officers, employees and agents, arising out of, or associated with, this Construction Change Order.
5. Does this Change Order increase the Contract Amount by 25% or more? Yes No
In accordance with the terms of the Contract, the following detailed changes are proposed:
Original Contract Sum $
Previous Change Orders to Contract $
Net Change for this Change Order to Contract $
New Contract Sum $
Number of Calendar Days for Time Extended for Substantial Completion for this Change Order Days
Revised Substantial Completion Date Due to This Change Order
Contractor (Firm Name): Address: Authorized Signature and Date:
Design Professional (Firm Name): Address: Authorized Signature and Date:
State Procurement Officer Name: Agency Name and Address: Authorized Signature and Date:
Chief Compliance Officer Name: Agency Name and Address: Authorized Signature and Date:
State of Arizona General Services Division 1400 West Washington St
Phoenix, AZ 85007
Form 7/8/2024 r3
Homolavi Ruins State Park - WWS PCS-22-124 PCS-22-124
Valentine Standard Construction Company LLC Brandon Bergeron
See J!'s attached for COR #1, #2, #3 & #4
1,619,323.91
0.00
102,722.11
1,722,046.02
CTR075666
Docusign Envelope ID: 5351E188-B0EB-4FF6-93BB-C754B6096244
810 E Western Ave, Avondale, AZ, 85353Standard Construction Company, INC 26-Aug-25 | 10:54 AM PDT
27-Aug-25 | 7:50 AM MST15845 S 46th St, #144 Phoenix, AZ 85048Valentine Environmental Engineers, LLC
ADOA 27-Aug-25 | 2:15 PM MSTDustin Deason
Patrick Holt 27-Aug-25 | 3:56 PM MSTADOA
810 E. Western Avenue Avondale, AZ 85323 Office (623) 583-9500
ROC# 166948-A ROC# 230441-B04
July 15, 2025 Sent Via email to:
Brandon.Bergeron@azdoa.gov
Arizona Department of Administration General Services Division 1400 West Washington Street, B-200 Phoenix, Arizona, 85007 Attn: Brandon Bergeron, Sr. Project Manager
Re: Change Order Request #1 – Consolidation of Existing Waterlines Around CXT Homolovi Ruins State Park WWS
CTR075666
Dear Mr. Bergeron, During excavation and removal of the existing restroom building, Standard Construction discovered several unknown waterlines and waterline tie-ins that fed not only the building but the entire campground area. After further T&M investigation, Standard uncovered and found that there were 4 separate waterlines running around the existing restroom building serving separate purposes:
1. 2” Waterline that fed water to the restroom building
2. 2” Waterline that fed the west side of the campground
3. 2” waterline that fed the east side of the campground
4. 1” irrigation line that was no longer in use
These lines discovered appeared to all tie into each other, which complicated any necessary shutdowns for repairs. At an on-site meeting on 6/19/25, Standard Construction, ADOA, AZ Parks, and Valentine Engineering all observed the conditions and decided that it was necessary to consolidate the lines, add some additional shut-off valves to help isolate each individual line, and to remove any unnecessary lines or parts. Standard submitted RFI #15 proposing to install 3 New 2” valves to help isolate each waterline and remove unnecessary parts. The 3 new valves will be located in one meter box to protect the new valves.
Standard Construction herby requests that ADOA execute a change order in the amount of $12,838.73 to compensate for the changes related to RFI #15. This change order amount will compensate for the additional labor, materials, equipment, and general conditions as well as provides a credit for the 6” pipe parts that will now not be used per the plan. See attached change order breakdown and RFIs as backup for the changes to the existing waterline around the CXT.
Docusign Envelope ID: 5351E188-B0EB-4FF6-93BB-C754B6096244 mailto:Brandon.Bergeron@azdoa.gov
Your immediate attention to this matter is appreciated, should you have any questions or if I can be of further assistance, please do not hesitate to contact me.
Best regards, STANDARD CONSTRUCTION COMPANY, INC.
Kyle Bowman Project Manager
COR No. 1 Date: 07/15/25
Does this require Statutory Review? No Yes
Schedule of Values Item No. Subcontractor Trades
Q ty
U ni ts
Unit Price Extension Q ty
U ni ts
Unit Price Extension Totals 1 -$ -$ -$
Install Waterline Pipe Material (See attached T&M Breakdown) 1 LS $6,564.13 6,564.13$ -$ -$ 6,564.13$
Remove Existing Waterline (See Attacehd T&M Breakdown) 1 LS $5,369.48 5,369.48$ -$ 5,369.48$
3 Credit for 6" Pipe Parts -$ 1 LS (2,151.27)$ (2,151.27)$ (2,151.27)$ 4 -$ -$ 5 -$ -$ 6 Discount -$ 1 LS (24.21)$ (24.21)$ (24.21)$ 7 -$ -$ -$ 8 -$ -$ -$ 9 -$ -$ -$
10 -$ -$ -$ 11 -$ -$ -$ 12 -$ -$ -$ 13 -$ -$ -$ 14 -$ -$ -$ 15 -$ -$ -$
9,758.13$ X Owner Request 12.00% 1,170.98$ X Hidden Condition 2.00% 195.16$
Prepurchase Materials 1.44% 140.52$ Omission in Construction docs Contractor's Fee 10.00% 975.81$ Transfer to/from Contingency 6.13% 598.12$ Other 12,838.73$
Approval of this Change Order Request will increase (decrease) the Schedule by: 2 Calendar Days
General Conditions Insurance Bond
Tranaction Tax Total Cost
Address Authorized Signature & Date
Address Authorized Signature & Date
Address Authorized Signature & Date
1400 W Washington Authorized Signature & Date
Design Professional:
Contractor:
Owner Representative:
Project Manager (ADOA)
The Contractor hereby requests a Change in the Contract Sum and/or Time, conforming to Article 1.2 of the Uniform Terms and Conditions, the Work described herein will not start until this Change Order Request has been signed by all parties.
Labor Material
Check the box best describing the Cause of this Change Subtotal
Exhibit J1 Change Order Request
State of Arizona General Services Division 1400 West Washington St
Phoenix, AZ 85007 Design Professional : Valentine Enviromental Engineering, LLC
Project Name: Homolovi Ruins State Park WWS Project No.: CTR075666Contractor: Standard Construction Company, INC
Docusign Envelope ID: 5351E188-B0EB-4FF6-93BB-C754B6096244
810 E Western Ave, Avondale, AZ, 85323 Standard Construction Company, INC 26-Aug-25 | 10:54 AM PDT
15845 S 46th St, #144 Phoenix, AZ 85048 27-Aug-25 | 7:50 AM MSTValentine Environmental Engineers, LLC
27-Aug-25 | 8:46 AM MST1110 W Washington #100, Phoenix AZ 85007 Thomas Kmetz
Brandon Bergeron 27-Aug-25 | 8:50 AM MST
Jason Joseph 27-Aug-25 | 2:12 PM MST
PROJECT: Homolovi Ruins State Park - Waste Water System DATE: - OWNER: Arizona Department of Administration SCCI JOB NO: 24-006
CONTRACT ID: CTR075666 ITEM NO: 1
DESCRIPTION - WORK PERFORMED:
QUANTITY: 3.00 EA
SCCI OWNED EQUIPMENT:
CODE: DESCRIPTION STAND-BY DAILY RATE TOTAL
Pickup Truck (x2) 1 $420.00 $420.00
SCCI EQUIPMENT SUBTOTAL $420.00
RENTAL EQUIPMENT:
CODE: DESCRIPTION STAND-BY DAYS RATE TOTAL
R228 Water Truck 1 $350.00 $350.00 R931 Mini Ex-18K 1 $595.00 $595.00
RENTAL EQUIPMENT SUBTOTAL $945.00
RENTAL EQUIPMENT HOURLY OPERATING COST:
CODE: DESCRIPTION STAND-BY HOURS Rate TOTAL R228 Water Truck 6 $23.15 $138.90 R931 Mini Ex-18K 6 $29.53 $177.18
RENTAL EQUIPMENT HOC SUBTOTAL $316.08
LABOR:
CODE: DESCRIPTION HOURS S/T HOURS O/T RATE TOTAL
Director of Field Ops/ Superintendent 6 128.42$ $770.52 Project Management 6 109.45$ $656.70 Assitant Superintendent 6 112.73$ $676.35 Water Truck Driver / Teamster 6 58.47$ $350.81 Operator 6 73.13$ $438.80 Skilled Labor (x2) 12 66.27$ $795.23
LABOR SUBTOTAL $3,688.40
MATERIAL:
CODE: DESCRIPTION QUANTITY UNIT PRICE TOTAL
Pipe 1 LS $1,194.65 $1,194.65
MATERIAL SUBTOTAL $1,194.65
SUBCONTRACTOR:
CODE: SUBCONTRACTOR QUANTITY UNIT PRICE TOTAL
SUBS SUBTOTAL $0.00
EQUIPMENT SUBTOTAL.................................................................................................................................... $1,365.00
0.00% MARK UP $0.00
TOTAL HOCs $316.08 TOTAL EQUIPMENT.................................................................................................................................... $1,681.08
LABOR SUBTOTAL.................................................................................................................. $3,688.40 0.00% MARK UP (Included in rates) $0.00
TOTAL LABOR.................................................................................................................................................. $3,688.40
MATERIAL SUBTOTAL....................................................................................................................... $1,194.65
0.00% MARK UP $0.00
TOTAL MATERIALS........................................................................................................................................... $1,194.65
SUBCONTRACTOR SUBTOTAL.......................................................................................................... $0.00
0.00% MARK UP $0.00
TOTAL SUBCONTRACTOR............................................................................................................................ $0.00 COST........................................................................................ $6,564.13 TAX (6.1295%)......................................................................... $0.00 BOND (1.8%)............................................................................ $0.00 TOTAL COST........................................................................... $6,564.13 UNIT COST............................................................................... $2,188.04
STANDARD CONSTRUCTION COMPANY, INC.
T&M Rate Sheet
Install New 2" Valves and Water Pipe
SUMMARY
CONTRACT ID: CTR075666 ITEM NO: 1
DESCRIPTION - WORK PERFORMED:
QUANTITY: 1.00 LS
SCCI OWNED EQUIPMENT:
CODE: DESCRIPTION STAND-BY DAILY RATE TOTAL
Pickup Truck 1 $420.00 $420.00
SCCI EQUIPMENT SUBTOTAL $420.00
RENTAL EQUIPMENT:
CODE: DESCRIPTION STAND-BY DAYS RATE TOTAL
R228 Water Truck 1 $350.00 $350.00 R931 Mini Ex-18K 1 $595.00 $595.00
RENTAL EQUIPMENT SUBTOTAL $945.00
RENTAL EQUIPMENT HOURLY OPERATING COST:
CODE: DESCRIPTION STAND-BY HOURS Rate TOTAL R228 Water Truck 6 $23.15 $138.90 R931 Mini Ex-18K 6 $29.53 $177.18
RENTAL EQUIPMENT HOC SUBTOTAL $316.08
LABOR:
CODE: DESCRIPTION HOURS S/T HOURS O/T RATE TOTAL
Director of Field Ops/ Superintendent 6 128.42$ $770.52 Project Management 6 109.45$ $656.70 Assitant Superintendent 6 112.73$ $676.35 Water Truck Driver / Teamster 6 58.47$ $350.81 Operator 6 73.13$ $438.80 Skilled Labor (x2) 12 66.27$ $795.23
LABOR SUBTOTAL $3,688.40
MATERIAL:
CODE: DESCRIPTION QUANTITY UNIT PRICE TOTAL
MATERIAL SUBTOTAL $0.00
SUBCONTRACTOR:
CODE: SUBCONTRACTOR QUANTITY UNIT PRICE TOTAL
SUBS SUBTOTAL $0.00
EQUIPMENT SUBTOTAL.................................................................................................................................... $1,365.00
0.00% MARK UP $0.00
TOTAL HOCs $316.08 TOTAL EQUIPMENT.................................................................................................................................... $1,681.08
LABOR SUBTOTAL.................................................................................................................. $3,688.40 0.00% MARK UP (Included in rates) $0.00
TOTAL LABOR.................................................................................................................................................. $3,688.40
MATERIAL SUBTOTAL....................................................................................................................... $0.00
0.00% MARK UP $0.00
TOTAL MATERIALS........................................................................................................................................... $0.00
SUBCONTRACTOR SUBTOTAL.......................................................................................................... $0.00
0.00% MARK UP $0.00
TOTAL SUBCONTRACTOR............................................................................................................................ $0.00 COST........................................................................................ $5,369.48 TAX (6.1295%)......................................................................... $0.00 BOND (1.8%)............................................................................ $0.00 TOTAL COST........................................................................... $5,369.48 UNIT COST............................................................................... $5,369.48
STANDARD CONSTRUCTION COMPANY, INC.
T&M Rate Sheet
Remove Exisiting Water Pipe
Standard Construction Company, Inc - Labor & Equipment Rates for Time & Material Work Homolovi State Park WWS Improvments
LABOR RATES*
Classification Straight Time Rate
($/Hour) Over Time Rate
($/Hour) Director of Field Ops/ Superintendent 128.42$ 164.64$ Project Management 109.45$ 140.32$ Assitant Superintendent 112.73$ 144.52$ Field Engineer 112.73$ 144.52$ Safety Specialist 121.41$ 155.66$ Security Services 98.64$ 175.38$ Water Truck Driver / Teamster 58.47$ 113.12$ Operator 73.13$ 126.33$ Skilled Labor 66.27$ 113.12$ Unskilled Labor 58.02$ 97.28$
* Rates shown include Labor Burden, Per Diem, and Hotels
EQUIPMENT RATES
Classification Daily Rate
Pickup Truck 420.00$
* Rates do not include mobilization.
Rental Equipment Rates will be calculated using the below equation:
[Rental invoice x 1.10] + HOC
15850 Dallas Pkwy Dallas, TX 75248 Payment Inquiries 704-788-9800
INVOICE INVOICE NUMBER: 6971131
BILL OF LADING:
INVOICE DATE: 7/10/25
DUE DATE: 8/08/25
Please Remit Payment To:
Fortiline, Inc PO Box 744053 Atlanta, GA 30374-4053 Federal Tax ID# 57-0819190 Warehouse:
FORTILINE FLAGSTAFF
5585 DARK SKY DR
SUITE A
FLAGSTAFF, AZ 86001
Telephone: 928-255-4385
SOLD TO
STANDARD CONSTRUCTION COMPANY
810 E WESTERN AVE
AVONDALE AZ 85323-2013
SHIP TO
Customer Pickup
BRANCH NO
FROM CONTRACT
6817238
ORDER NO
6971131
SHIPPING METHOD
Pickup
CUSTOMER NO
221698
TERMS
NET 30 DAYS
PO NO
24006-P07
JOB NAME
HOMOLOVI PARK
JOB NO
HOMOLOV
SLS
KJO
DUE DATE
8/08/25
SHIP DATE
7/07/25
PRODUCT NO
2DR11IPSMA
2B20200N
2B20283N
26BN
2S4CHH
2S4THH
2S4AHM
2A236008EPDM
OAT30894
OAT30758
DESCRIPTION
2" DR11 HDPE MIPT ADAP IPS
C/O LINE # 02610
2" BALL VLV FIPXFIP B-20200N
LOW LEAD
C/O LINE # 02646
2" BALL VLV FIPXFIP B-20283N
LOW LEAD
C/O LINE # 02647
2"X6" BRASS NIPPLE
C/O LINE # 02648
2" SCH40 PVC CPLG HXH
C/O LINE # 02649
2" SCH40 PVC TEE HXH
C/O LINE # 02650
2" SCH40 PVC ADPT HXM
C/O LINE # 02651
2" THD GV O/L A2360-08 EPDM
C/O LINE # 02652
QUART RAIN-R-SHINE MED CEMENT
OATEY
C/O LINE # 02653
QUART PURPLE PRIMER
C/O LINE # 02635
UOM
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
ORDERED
SHIPPED
BACK
ORDERED
UNIT PRICE
62.6400
380.1100
376.5200
35.9600
1.0300
2.1200
1.1000
489.6700
26.2600
14.1600
EXTENDED PRICE
375.84
380.11
753.04
107.88
8.24
4.24
6.60
489.67
26.26
14.16
AMOUNT DUE $2,166.04
TAX $0.00
FREIGHT $0.00
OTHER $0.00
TOTAL DUE $2,166.04
NO RETURNS ACCEPTED WITHOUT PRIOR AUTHORIZATION. AUTHORIZED RETURNS ARE SUBJECT TO RESTOCKING FEES.
SPECIAL ORDER ITEMS ARE NOT RETURNABLE. ALL CLAIMS MUST BE FILED WITH THE CARRIER.
For TERMS and CONDITIONS of sale, please visit http://www.fortiline.com
Page 1 of 1TO VIEW AND PAY ONLINE: Fortiline.com USE THIS ENROLLMENT TOKEN: SWF BSV VQP http://Fortiline.com
Project: PCS-22-124 ARPA - Homolovi Ruins State Park - WWS (PCS-22-124)
HCR 63, Box 5, I-40 Exit 257, 1.5 mi. N on Hwy 87 Winslow, Arizona
RFI #15: Consolidation of Existing Waterlines at Restroom/CXT
Status Open
To Kaley Yazzie (Valentine Environmental Engineers) Jazlyn Acosta (Valentine Environmental Engineers)
From Kyle Bowman (Standard Construction Company)
Date Initiated Jun 23, 2025 Due Date Jun 24, 2025
Location Project Stage
Cost Impact Yes (Unknown) Schedule Impact TBD
Spec Section Cost Code
Drawing Number M6.0 Reference
Linked Drawings
Received From Chris Defiese (Standard Construction Company)
Copies To Brandon Bergeron (ADOA / GSD), Kyle Bowman (Standard Construction Company), Chris Defiese (Standard Construction Company)
Activity
Question Question from Kyle Bowman Standard Construction Company on Monday, Jun 23, 2025 at 03:38 PM MST As discussed during an on-site meeting on 6/19. Standard proposes the attached solution to consolidate and simplify the existing waterlines discovered around the campground restroom.
Standard proposes installation of 3 EA - 2" valves to isolate each line and remove unnecessary sections of the existing waterline. This will allow the park staff to isolate each line as they deem necessary without causing major disruptions to the rest of the campgrounds.
Attachments RFI #15 - Waterline Consolidation Mockup.pdf
Official Response Response from Jazlyn Acosta Valentine Environmental Engineers on Friday, Jun 27, 2025 at 05:06 PM MST See attached response.
RFI#015 Response.pdf
All Replies Response from Jazlyn Acosta Valentine Environmental Engineers on Friday, Jun 27, 2025 at 05:06 PM MST See attached response.
RFI#015 Response.pdf
Page 1 of 1 Printed On: Jun 30, 2025 04:06 PM MST https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/6526/01JYFES477YCYXBJ2K1H5RRZHD?companyId=6256&projectId=1895799&sig=f2d3e17e51b5d1e4852fb5a33aafa1b75c769688fe4a81cc2365bffe5a0bf511 https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/6526/01JYSXPF2YPP5QFM3BTG7YNFFT?companyId=6256&projectId=1895799&sig=6ce22325addb86c277bec885e51d2b455a68142488ead2038fe847752f45a9b2 https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/6526/01JYSXPF2YPP5QFM3BTG7YNFFT?companyId=6256&projectId=1895799&sig=6ce22325addb86c277bec885e51d2b455a68142488ead2038fe847752f45a9b2
Valentine Environmental Engineers, LLC Page 1 of 1 Request for Information (RFI) Date: 6/27/2025
Request for Information (RFI) Response
Owner: AZ State Parks/Arizona Department of Administration (ADOA) Project: Homolovi Water & Wastewater Infrastructure Upgrades Contractor: Standard Construction Company Engineer: Valentine Environmental Engineers, LLC
RFI No.: 015
Date Received - Returned: 6/23/2025-6/27/2025
Drawing Number: M6.0
Description: Consolidation of Existing Waterlines at Restroom/CXT
Contractor RFI:
As discussed during an on-site meeting on 6/19. Standard proposes the attached solution to consolidate and simplify the existing waterlines discovered around the campground restroom.
Standard proposes installation of 3 EA - 2" valves to isolate each line and remove unnecessary sections of the existing waterline. This will allow the park staff to isolate each line as they deem necessary without causing major disruptions to the rest of the campgrounds.
RESPONSE:
Valentine agrees to Standard’s proposal for installation of three (3) – 2-inch valves to isolate each line that feed the campsites, the line to the rest of the park, and the line going straight to the restroom building.
Valentine requests that Standard carefully track all as-builting for the demo work and the existing components that were discovered in field.
Standard indicated on-site that shut down time for the tie-ins to take place may result in a day.
Please coordinate with the Park & residents accordingly.
July 15, 2025 Sent Via email to:
Brandon.Bergeron@azdoa.gov
Arizona Department of Administration General Services Division 1400 West Washington Street, B-200 Phoenix, Arizona, 85007 Attn: Brandon Bergeron, Sr. Project Manager
Re: Change Order Request #2 – Changes to Ranger Residence Booster Pump Homolovi Ruins State Park WWS
CTR075666
Dear Mr. Bergeron, On 5/23/25, Standard Construction submitted RFI #6, requesting clarification on the weather protection for the Ranger Residence Booster Pump Skid. The plans and specifications did not specify any weather protection for the system, but the pump manufacturer was concerned about having the skid system exposed to the elements. Over the next several weeks, both Standard Construction and Valentine Engineering had conversations with the manufacturer which ended up with a recommendation of an insulated enclosure for the skid with an exhaust fan and thermostat-controlled space heater. This would protect the skid package from the weather in both the extreme summer heat and the low temperatures of winter.
Valentine Engineering provided an official response to RFI #6 on 6/9/25 which included Field Directive #1, with final updated electrical drawings being provided on 6/27/25. With these RFI responses, the following changes were included:
• Widening the re-enforced concrete pad by 30 SF
• Additional 10 LF of Fencing around the Booster Pump
• Addition of an insulated enclosure for the booster pump skid package with vent fan and space heater
• Changes to the electrical tie in and power supply to the skid package to compensate for the exhaust fan and space heater inclusions
Due to these changes to the booster pump system, Standard could not get the boost pump package with changes approved and into production until 7/2/25. Per the manufacturer, there will be a 10–12-week lead time for production and delivery. Standard is projecting to be complete will all other contract work by the beginning of August, meaning a separate mobilization of crew and equipment to install the booster pump once it is ready will be necessary. An additional mobilization of the electrical subcontractor will also be necessary once the skid package is installed to connect and energize power to the system.
Standard Construction requests that ADOA execute a change order in the amount of $36,000 to compensate for the changes related to Ranger Residence Booster Pump System and Enclosure. This change order amount will compensate for the additional mobilizations, labor, materials, equipment, and general conditions. See attached change order breakdown and RFIs as backup for the changes to the booster pump skid package.
Your immediate attention to this matter is appreciated, should you have any questions or if I can be of further assistance, please do not hesitate to contact me.
COR No. 2
Does this require Statutory Review? No Yes
Schedule of Values Item No. Subcontractor Trades
Q ty
U ni ts
Unit Price Extension Q ty
U ni ts
Unit Price Extension Totals 1 -$ -$ -$ 2 Additional Crew Mobilization 1 LS 1,400.00$ 1,400.00$ 1 LS -$ -$ 1,400.00$ 3 Booster Pump Changes 1 LS 9,763.98$ 9,763.98$ 1 LS 11,940.00$ 11,940.00$ 21,703.98$ 4 Electrical Changes 1 LS 1,064.00$ 1,064.00$ 1 LS 1,260.00$ 1,260.00$ 2,324.00$ 5 Concrete Changes 1 LS 1,817.26$ 1,817.26$ 1 LS 208.72$ 208.72$ 2,025.98$ 6 -$ -$ -$ 7 -$ -$ -$ 8 Rounding Adjustment -$ (92.01)$ (92.01)$ 9 -$ -$ -$
10 -$ -$ -$ 11 -$ -$ -$ 12 -$ -$ -$ 13 -$ -$ -$ 14 -$ -$ -$ 15 -$ -$ -$
27,361.96$ X Owner Request 12.00% 3,283.43$
Hidden Condition 2.00% 547.24$ Prepurchase Materials 1.44% 394.01$
X Omission in Construction docs Contractor's Fee 10.00% 2,736.20$ Transfer to/from Contingency 6.13% 1,677.15$ Other 36,000.00$
Approval of this Change Order Request will increase (decrease) the Schedule by: 2 Calendar Days
Form 7.5.2024 rev r7
Exhibit J1 Change Order Request
State of Arizona General Services Division 1400 West Washington St
Phoenix, AZ 85007 Design Professional : Valentine Enviromental Engineering, LLC
Project Name: Homolovi Ruins State Park WWS Project No.: CTR075666Contractor: Standard Construction Company, INC
The Contractor hereby requests a Change in the Contract Sum and/or Time, conforming to Article 1.2 of the Uniform Terms and Conditions, the Work described herein will not start until this Change Order Request has been signed by all parties.
Labor Material
Check the box best describing the Cause of this Change Subtotal
Design Professional:
Contractor:
Owner Representative:
Project Manager (ADOA)
Construction Services Manager Jason Joseph 1400 W Washington Authorized Signature & Date
General Conditions Insurance Bond
Tranaction Tax Total Cost
Address Authorized Signature & Date
Address Authorized Signature & Date
Address Authorized Signature & Date
1400 W Washington Authorized Signature & Date
Docusign Envelope ID: 5351E188-B0EB-4FF6-93BB-C754B6096244
Standard Construction Company, INC 810 E Western Ave, Avondale, AZ, 85323 26-Aug-25 | 10:54 AM PDT
15845 S 46th St, #144 Phoenix, AZ 85048Valentine Environmental Engineers, LLC 27-Aug-25 | 7:50 AM MST
27-Aug-25 | 8:46 AM MST1110 W Washington #100, Phoenix AZ 85007 Thomas Kmetz
27-Aug-25 | 8:50 AM MSTBrandon Bergeron
27-Aug-25 | 2:12 PM MSTJason Joseph
CONTRACT ID: CTR075666 ITEM NO: 1
DESCRIPTION - WORK PERFORMED:
QUANTITY: 1.00 LS
SCCI OWNED EQUIPMENT:
CODE: DESCRIPTION STAND-BY DAILY RATE TOTAL
Pickup Truck 2 $420.00 $840.00
SCCI EQUIPMENT SUBTOTAL $840.00
RENTAL EQUIPMENT:
CODE: DESCRIPTION STAND-BY DAYS RATE TOTAL
R228 Water Truck 2 $350.00 $700.00 R931 Mini Ex-18K 2 $595.00 $1,190.00
RENTAL EQUIPMENT SUBTOTAL $1,890.00
RENTAL EQUIPMENT HOURLY OPERATING COST:
CODE: DESCRIPTION STAND-BY HOURS Rate TOTAL R228 Water Truck 12 $23.15 $277.80 R931 Mini Ex-18K 5 $29.53 $147.65
RENTAL EQUIPMENT HOC SUBTOTAL $425.45
LABOR:
CODE: DESCRIPTION HOURS S/T HOURS O/T RATE TOTAL
Director of Field Ops/ Superintendent 10 128.42$ $1,284.19 Project Management 4 109.45$ $437.80 Assitant Superintendent 20 112.73$ $2,254.51 Water Truck Driver / Teamster 20 58.47$ $1,169.38 Operator 20 73.13$ $1,462.66
LABOR SUBTOTAL $6,608.53
MATERIAL:
CODE: DESCRIPTION QUANTITY UNIT PRICE TOTAL
MATERIAL SUBTOTAL $0.00
SUBCONTRACTOR:
CODE: SUBCONTRACTOR QUANTITY UNIT PRICE TOTAL
SUBS SUBTOTAL $0.00
EQUIPMENT SUBTOTAL.................................................................................................................................... $2,730.00
0.00% MARK UP $0.00
TOTAL HOCs $425.45 TOTAL EQUIPMENT.................................................................................................................................... $3,155.45
LABOR SUBTOTAL.................................................................................................................. $6,608.53 0.00% MARK UP (Included in rates) $0.00
TOTAL LABOR.................................................................................................................................................. $6,608.53
MATERIAL SUBTOTAL....................................................................................................................... $0.00
0.00% MARK UP $0.00
TOTAL MATERIALS........................................................................................................................................... $0.00
SUBCONTRACTOR SUBTOTAL.......................................................................................................... $0.00
0.00% MARK UP $0.00
TOTAL SUBCONTRACTOR............................................................................................................................ $0.00 COST........................................................................................ $9,763.98 TAX (6.1295%)......................................................................... $0.00 BOND (1.8%)............................................................................ $0.00 TOTAL COST........................................................................... $9,763.98 UNIT COST............................................................................... $9,763.98
STANDARD CONSTRUCTION COMPANY, INC.
T&M Rate Sheet
Changes to Booster Pump, Fence, and Electrical per Updated M10.0
PROJECT: Homolovi Ruins State Park - Waste Water System DATE: 06/18/2025 OWNER: Arizona Department of Administration SCCI JOB NO: 24-007
CONTRACT ID: CTR075666 ITEM NO: 1
DESCRIPTION - WORK PERFORMED:
QUANTITY: 1.00 LS
SCCI OWNED EQUIPMENT:
CODE: DESCRIPTION STAND-BY DAILY RATE TOTAL
Pickup Truck 1 $420.00 $420.00
SCCI EQUIPMENT SUBTOTAL $420.00
RENTAL EQUIPMENT:
CODE: DESCRIPTION STAND-BY DAYS RATE TOTAL
R228 Water Truck 1 $350.00 $350.00
RENTAL EQUIPMENT SUBTOTAL $350.00
RENTAL EQUIPMENT HOURLY OPERATING COST:
CODE: DESCRIPTION STAND-BY HOURS Rate TOTAL R228 Water Truck 2 $23.15 $46.30
RENTAL EQUIPMENT HOC SUBTOTAL $46.30
LABOR:
CODE: DESCRIPTION HOURS S/T HOURS O/T RATE TOTAL
Director of Field Ops/ Superintendent 1 128.42$ $128.42 Project Management 0 109.45$ $0.00 Assitant Superintendent 2 112.73$ $225.45 Water Truck Driver / Teamster 2 58.47$ $116.94 Skilled Labor (x4) 8 66.27$ $530.15
LABOR SUBTOTAL $1,000.96
MATERIAL:
CODE: DESCRIPTION QUANTITY UNIT PRICE TOTAL
ABC 0.99 TON $22.00 $21.78
Concrete 0.69 CY $190.00 $131.94 Rebar 1 LS $55.00 $55.00
MATERIAL SUBTOTAL $208.72
SUBCONTRACTOR:
CODE: SUBCONTRACTOR QUANTITY UNIT PRICE TOTAL
SUBS SUBTOTAL $0.00
EQUIPMENT SUBTOTAL.................................................................................................................................... $770.00
0.00% MARK UP $0.00
TOTAL HOCs $46.30 TOTAL EQUIPMENT.................................................................................................................................... $816.30
LABOR SUBTOTAL.................................................................................................................. $1,000.96 0.00% MARK UP (Included in rates) $0.00
TOTAL LABOR.................................................................................................................................................. $1,000.96
MATERIAL SUBTOTAL....................................................................................................................... $208.72
0.00% MARK UP $0.00
TOTAL MATERIALS........................................................................................................................................... $208.72
SUBCONTRACTOR SUBTOTAL.......................................................................................................... $0.00
0.00% MARK UP $0.00
TOTAL SUBCONTRACTOR............................................................................................................................ $0.00 COST........................................................................................ $2,025.98 TAX (6.1295%)......................................................................... $0.00 BOND (1.8%)............................................................................ $0.00 TOTAL COST........................................................................... $2,025.98 UNIT COST............................................................................... $2,025.98
STANDARD CONSTRUCTION COMPANY, INC.
T&M Rate Sheet
Additional Concrete Work to Expand Pad per Updated Plan Sheet M10.0
LABOR RATES*
Classification Straight Time Rate
($/Hour) Over Time Rate
($/Hour) Director of Field Ops/ Superintendent 128.42$ 164.64$ Project Management 109.45$ 140.32$ Assitant Superintendent 112.73$ 144.52$ Field Engineer 112.73$ 144.52$ Safety Specialist 121.41$ 155.66$ Security Services 98.64$ 175.38$ Water Truck Driver / Teamster 58.47$ 113.12$ Operator 73.13$ 126.33$ Skilled Labor 66.27$ 113.12$ Unskilled Labor 58.02$ 97.28$
* Rates shown include Labor Burden, Per Diem, and Hotels
EQUIPMENT RATES
Classification Daily Rate
Pickup Truck 420.00$
* Rates do not include mobilization.
Rental Equipment Rates will be calculated using the below equation:
6023 N. Yorktown Avenue Tulsa, OK 74130
918-346-6312
RFI RESPONSE
DATE: 02-24-25
QUOTE#: PF-066743-r1
JOB: ADOA Homolovi State Park
CUSTOMER: Arrowhead
PREMIERflow, LLC is pleased to offer the following:
In response to outdoor rated booster system.
1. To convert control panel from NEMA 1 to NEMA 3R outdoor protected which would include vent covers and HMI Screen
Cover your total net adder $1,585.00
2. To convert control panel from NEMA 1 to NEMA 4 with panel mounted A/C unit for temp control and HMI Screen cover
Your total net adder $7,215.00
3. Option to heat trace with thermostat complete package your total net adder $1,640.00
4. Option to add a fiberglass enclosure complete with exhaust fan and louver, 3 kva power supply, GFCI, and unit space heater to enclose complete package and storage tank. Your total net adder $11,940.00
Respectfully Submitted:
PREMIERflow, LLC
Keith Pirtle Sales
CHANGE PROPOSAL REQUEST
4020 N 16th St Phoenix, Arizona 85016 Telephone: 6028094652 Contact: Brady Belskus E-mail: bbelskus@cannon-wendt.com
CPR # 1
Date: 7/2/2025 Project Name: Homolovi Ruins State Park - Waste Water System Project Number: 24-006 Page Number: 1
Client Address:
Standard Construction Company, Inc 810 E Western Ave Avondale, AZ 85323 Telephone: 6235839500 Contact: Diane Sutton E-mail: dsutton@standardaz.com
Site Address:
Homolovi Ruins State Park
AZ-87
Winslow, AZ 86047
Work Description P101 Changed from #6 CU THHN to #4THHN
New 3/4" conduit to PT103 with wire and connection.
We reserve the right to correct this quote for errors and omissions.
This quote covers direct costs only and we reserve the right to claim for delays, disruption, inefficiency and consequential costs.
This price is good for acceptance within 10 days from the date of receipt.
We request a time extension of 3 days.
We will supply and install all materials, labor and equpment as per you instructions on CPR #1.
Notwithstanding any provision herein to the contrary, in the event that, during the performance of this proposal, the price of steel, copper, pvc, aluminum, concrete and/or any other necessary commodities significantly increases, through no fault of Cannon & Wendt Electric Co., Inc., the price of any materials, components, or goods to be furnished under this proposal shall be equitably adjusted by an amount reasonably necessary to cover any such significant price increases. As used herein, a significant increase shall mean any increase in price exceeding five percent (5%) experienced by Cannon & Wendt Electric Co., Inc. from the date of the submission of this proposal. Such price increases shall be documented through commercial quotes, invoices, receipts or other such documentation. Where the delivery of materials, components, or goods required under this agreement is delayed, through no fault of Cannon & Wendt Electric Co., Inc., as a result of the shortage or unavailability of commodities, raw materials, components and/or products, Cannon & Wendt Electric Co., Inc.
shall not be liable for any additional costs or damages associated with such delay(s).
Itemized Breakdown
Description Qty Total Mat. Total Hrs.
3/4 EMT 10 27.08 0.75
3/4 EMT INS STL SS CONN 2 4.72 0.30
3/4 EMT STL SS CPLG 1 2.21 0.07
3/4 EMT STRUT CLAMP 1 2.19 0.04
1/2 SEALTITE 3 5.83 0.27
1/2 ST INS STR CONN 1 10.99 0.18
1/2 ST INS 90D CONN 1 18.90 0.18
#6 THHN CU -143 -2,058.68 -2.57
#4 THHN CU 143 3,150.36 3.00
#12 THHN CU STR GREEN 16 47.46 0.14
RC10-6F #12-#10 NYL INSUL FORK 1 2.49 0.20
#451 YELLOW WIRE NUT 4 0.63 0.16
4SQ BOX 1-1/2"D 1/2"&3/4"KO 1 26.95 0.40
4SQ BLANK COVER 1 10.02 0.10
GROUND SCREW W/INSUL #12 LEAD 1 0.76 0.03
#8-10 x 7/8" PLASTIC ANCHOR 2 0.08 0.45 #10x 3/4" S-TAP SCREW P/H 2 0.41 0.48
ORIGINAL
CHANGE PROPOSAL REQUEST
Cannon & Wendt Electric 4020 N 16th St Phoenix, Arizona 85016
CPR # 1
Date: 7/2/2025 Project Name: Homolovi Ruins State Park - Waste Water System Project Number: 24-006 Page Number: 2
Site Address:
Homolovi Ruins State Park
AZ-87
Winslow, AZ 86047
Description Qty Total Mat. Total Hrs.
#14-#10 TERMINATION 2 0.00 0.48
# 12 WIRE TERM-POWER 2 0.00 0.50
Totals 51 1,252.38 5.17
Summary
General Materials 1,252.38
Material Total 1,252.38 GENERAL FOREMAN (ST) (0.78 Hrs @ $100.59) 78.46 FOREMAN (ST) (0.78 Hrs @ $87.42) 68.19 JOURNEYMAN (ST) (5.17 Hrs @ $75.11) 388.32 TRAVEL TIME (3.00 Hrs @ $75.00) 225.00 Overhead (@ 10.000 %) 201.24 Markup (@ 5.000 %) 110.68
Subtotal 2,324.27 Adjustment #2 (@ -0.012 %) -0.27
Final Amount $2,324.00
CONTRACTOR CERTIFICATION
Name:
Date:
Signature:
CLIENT ACCEPTANCE
CPR # 1
Final Amount: $2,324.00
Name:
Date:
Signature:
Change Order #:
I hereby accept this quotation and authorize the contractor to complete the above described work.
ORIGINAL
RFI #6: Ranger Residence Outdoor Booster Pump Protections
Status Closed on 06/30/25
To Jazlyn Acosta (Valentine Environmental Engineers) (Response Required) Kaley Yazzie (Valentine Environmental Engineers) (Response Required)
Date Initiated May 23, 2025 Due Date May 26, 2025
Cost Impact Yes (Unknown) Schedule Impact Yes (Unknown)
Spec Section Cost Code
Drawing Number Reference
Linked Drawings
Received From
Copies To Jazlyn Acosta (Valentine Environmental Engineers), Brandon Bergeron (ADOA / GSD), Kyle Bowman (Standard Construction Company), Chris Defiese (Standard Construction Company), Kaley Yazzie (Valentine Environmental Engineers)
Question Question from Kyle Bowman Standard Construction Company on Friday, May 23, 2025 at 10:49 AM MST Standard's Booster Pump Skid manufacturer/supplier (PremierFlow) has brough up concerns over weather protection of booster pump skid that is currently (as per the plans) to be outdoors. The plans and specifications call out for the bladder tank at that location to be heat traced and insulated. However, the plans and specifications currently do not contain anything in regards to heat or cold weather protections for the booster pump skid.
Based on the current "approved as noted" submittal, PremeirFlow has offered the following suggestions:
• If unit is outdoor rated in AZ, panel would need to be a minimum NEMA 3R or NEMA 4 with panel mounted A/C unit as the VFD are mounted inside of the enclosure and the temp extreme heat would be a problem.
• On unit located outside it is recommended to have HMI screen cover
• Another option for Outdoor system is a fiberglass enclosure to protect the system from the elements and which could be heated to protect the tank and system
Will any heat or cold weather protections need to be taken for the exposed piping as part of the booster pump skid?
Please review and provide direction or updated plans/specifications that would protect the booster pump skid from weather damage.
Official Response Response from Jazlyn Acosta Valentine Environmental Engineers on Monday, Jun 9, 2025 at 08:27 AM MST Please see attached response after coordinating with ADOA and Parks.
ADOA Homolovi State Park RFI#006 Response.pdf
Page 1 of 2 Printed On: Jun 30, 2025 03:58 PM MST https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/6526/01JXAMV78H4DKB44NJ4Y7WQZDY?companyId=6256&projectId=1895799&sig=b5a588cbdcaf31baed23bda231b60d224c760fee10938638c919b2a9ca4fa16c
All Replies Response from Kaley Yazzie Valentine Environmental Engineers on Friday, Jun 27, 2025 at 08:50 AM MST Please see the revised electrical drawings which now includes the enclosure. These drawings were also included in the recent response to Submittal #5 - Booster Pump dated 6/25/25
Jensen Review Submittal SCCI #5 Rev3 Booster Pump Enclosure.pdf
Response from Jazlyn Acosta Valentine Environmental Engineers on Monday, Jun 9, 2025 at 08:32 AM MST Note that we are awaiting any revisions from electrical for any required power to the enclosure but wanted to get the response over to Standard for pricing. We will follow up once we receive revised electrical.
Response from Jazlyn Acosta Valentine Environmental Engineers on Monday, Jun 9, 2025 at 08:27 AM MST Please see attached response after coordinating with ADOA and Parks.
ADOA Homolovi State Park RFI#006 Response.pdf
Response from Kyle Bowman Standard Construction Company on Friday, May 30, 2025 at 09:51 AM MST Premierflow has asked Standard to send the attached suggestions and associated adders to Valentine in regards to this RFI.
Please note these are direct material costs to Premierflow and do not account for labor, equipment, or overhead costs Standard may incur for installation.
PREMIERFLOW RFI RESPONSE.pdf
Response from Jazlyn Acosta Valentine Environmental Engineers on Friday, May 30, 2025 at 08:44 AM MST Valentine is investigating the cost implications of these protections and will present to Parks for a decision. We will respond again once a decision has been reached.
RFI #6 - Ranger Residence Outdoor Booster Pump Protections Project: PCS-22-124 ARPA - Homolovi Ruins State Park - WWS (PCS- 22-124)
Page 2 of 2 Printed On: Jun 30, 2025 03:58 PM MST https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/6526/01JYS1AYP89AXW24PDP64GHG19?companyId=6256&projectId=1895799&sig=a0cdbdd4947229f7904cb3e8cab3eb9f12ed3631d709e845583cf833c5a4cc71 https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/6526/01JXAMV78H4DKB44NJ4Y7WQZDY?companyId=6256&projectId=1895799&sig=b5a588cbdcaf31baed23bda231b60d224c760fee10938638c919b2a9ca4fa16c https://storage.procore.com/api/v5/files/us-east-1/pro-core.com/companies/6526/01JWH1MST0910CVYN3S0JCFQTS?companyId=6256&projectId=1895799&sig=ad9873551a6b68583e4e68784d482a1cb36ce79f4906511540cecd1bea602b41
Jensen Engineering, LLC 6525 East Willow Springs Lane
Cave Creek, Arizona 85331
(480) 595-9342
(480) 237-9723 Fax
Electrical / Instrumentation / Control Engineering and Consulting – Jensen Engineering
S U B M I T T A L R E V I E W
PROJECT ADOA Homolovi State Park W&WW Upgrades
DATE REVIEWED June 25, 2025
SUBMITTAL NUMBER SCCI Submittal #5 Rev 2 Booster Pump Skid Enclosure
REVIEWED BY Dane E. Jensen
Review is for general compliance with the contract electrical plans and specifications. No responsibility is assumed for correctness of dimensions or details. The Contractor shall assume full responsibility for deviations from contract requirements not specifically indicated on this submittal.
Approved
Make Corrections. See Notes
Revise and Resubmit
Rejected
Comments:
1. See revised electrical drawings for changes on the electrical connections for the updated submittal.
X
Environmental Engineers, LLC 15845 South 46th Street, Suite 144 Phoenix, Arizona 85048 Phone: (480) 283 - 8991 Fax: (480) 283 - 0082
Jensen Engineering, LLC Est. 1988
Cave Creek, Arizona
(480) 595-9342
7/ 11
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6" W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6SS
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
6"W
Environmental Engineers, LLC 15845 South 46th Street, Suite 144 Phoenix, Arizona 85048 Phone: (480) 283 - 8991 Fax: (480) 283 - 0082
Jensen Engineering, LLC Est. 1988
Cave Creek, Arizona
(480) 595-9342
7/ 11
N
Valentine Environmental Engineers, LLC Page 1 of 2 Request for Information (RFI) Date: 6/9/2025
RFI No.: 006
Date Received - Returned: 5/23/2025-6/9/2025
Drawing Number: M10.0
Description: Ranger Residence Outdoor Booster Pump Protections
Standard's Booster Pump Skid manufacturer/supplier (PremierFlow) has brough up concerns over weather protection of booster pump skid that is currently (as per the plans) to be outdoors.
The plans and specifications call out for the bladder tank at that location to be heat traced and insulated. However, the plans and specifications currently do not contain anything in regards to heat or cold weather protections for the booster pump skid.
Based on the current "approved as noted" submittal, PremeirFlow has offered the following suggestions:
If unit is outdoor rated in AZ, panel would need to be a minimum NEMA 3R or NEMA 4 with panel mounted A/C unit as the VFD are mounted inside of the enclosure and the temp extreme heat would be a problem.
On unit located outside it is recommended to have HMI screen cover Another option for Outdoor system is a fiberglass enclosure to protect the system from the elements and which could be heated to protect the tank and system Will any heat or cold weather protections need to be taken for the exposed piping as part of the booster pump skid?
Please review and provide direction or updated plans/specifications that would protect the booster pump skid from weather damage.
RESPONSE:
The Contractor provided the quote summary from PremierFlow and Valentine confirmed the quote with the manufacturer. The quote included the cost differences between the two above options of either upgrading the panels or adding an enclosure to house all equipment. Please see attached document herein. Note that Standard indicated that these are direct material costs to
Valentine Environmental Engineers, LLC Page 2 of 2 Request for Information (RFI) Date: 6/9/2025
Premierflow and do not account for labor, equipment, or overhead costs Standard may incur for installation.
Considering the net price of the options attached, PremierFlow items 1-3, which include the NEMA 4 with A/C mounted unit, HMI screen cover, and heat tracing, the total price would amount to approximately $10,440.
The fiberglass enclosure is summarized in Premierflow Item 4 at $11,940. This option would house the booster pumps and bladder tank and provides weather protection. Valentine confirmed with PREMIER Flow that the enclosure’s exhaust fan would be sufficient enough to protect the booster pump system against standard 100°F temperatures seen in the area of Winslow. The pumps are not big enough to generate large heat loads and the exhaust fan would be sized to withstand said temperatures.
Valentine requested the cutsheet for the proposed fiberglass enclosure, Dyer Fiberglass Model D303, which is also included herein, in order to gauge the general footprint of the enclosure over the booster pump system. Please see attached Field Change Drawing No. 1 showing the proposed enclosure over the booster pump station. Note that this option requires an enlarged concrete pad and modifications to the surrounding fencing for minimum clearance.
Valentine presented this information to Parks and Parks prefers to move forward with the fiberglass enclosure.
Environmental Engineers, LLC 15845 South 46th Street, Suite 144 Phoenix, Arizona 85048 Phone: (480) 283 - 8991 Fax: (480) 283 - 0082
6023 N. Yorktown Avenue Tulsa, OK 74130
918-346-6312
RFI RESPONSE
DATE: 02-24-25
QUOTE#: PF-066743-r1
JOB: ADOA Homolovi State Park
CUSTOMER: Arrowhead
PREMIERflow, LLC is pleased to offer the following:
In response to outdoor rated booster system.
1. To convert control panel from NEMA 1 to NEMA 3R outdoor protected which would include vent covers and HMI Screen
Cover your total net adder $1,585.00
2. To convert control panel from NEMA 1 to NEMA 4 with panel mounted A/C unit for temp control and HMI Screen cover
Your total net adder $7,215.00
3. Option to heat trace with thermostat complete package your total net adder $1,640.00
4. Option to add a fiberglass enclosure complete with exhaust fan and louver, 3 kva power supply, GFCI, and unit space heater to enclose complete package and storage tank. Your total net adder $11,940.00
Respectfully Submitted:
PREMIERflow, LLC
Keith Pirtle Sales
July 22, 2025 Sent Via email to:
Brandon.Bergeron@azdoa.gov
Arizona Department of Administration General Services Division 1400 West Washington Street, B-200 Phoenix, Arizona, 85007 Attn: Brandon Bergeron, Sr. Project Manager
Re: Change Order Request #3 – Changes to Ranger Residence Sewer Line, Replacement of Damaged
Distribution Boxes, and HydroVac Cleaning Homolovi Ruins State Park WWS
CTR075666
Dear Mr. Bergeron, Per ADOA’s request, Standard Construction is submitting the following change order for design changes and existing conditions discovered over the course of the project to date. The following changes are described in further detail below:
1. HydroVac Cleaning of Existing Septic Fields:
a. During construction, Standard discovered that the existing pipes and septic fields outside of the project scopes were filled with dirt and sand. The dirt and sand discovered were preventing the sewage from flowing properly and in some case causing backups.
Standard proposes to flush and clean out the existing pipes and septic fields to restore the fields to their full capacity.
2. Replace Damaged Septic Diverter Boxes:
a. Upon excavation, Standard discovered that the 4 existing septic distribution boxes (1 @
Campground and 3 @ Ranger Residence) were damaged or completely collapsed.
Standard submitted RFI #9 requesting direction as to either replace or leave the damaged boxes in place. As part of the RFI #9 response, Standard was directed by the engineer to replace the damaged Distribution Boxes to restore the septic systems to their full capacity.
3. Changes to the Sewer Pipe Sizes and Parts to Match existing conditions:
a. Per plan, Standard was to install all 6” pipe around the Ranger Residence Septic Field and Sewer service. During excavation, Standard discovered that there were sections of 8” pipe and the existing sewer service was 4”.