This document outlines the technical requirements for a rechargeable battery procurement. Key details include a five-year IDIQ contract for NSN 6140-01-534-3856 BB-2001A/U Rechargeable Batteries, with a first article test required. The contract minimum is $50,000 and maximum is $5,650,000. Technical data must be obtained from Boeing or Bren-tronics. The estimated quantity to be ordered over five years is 4,507 in year one increasing to 4,592 each year for a total of 22,960. The solicitation is set aside for small businesses and was issued by the Defense Logistics Agency Land and Maritime.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit A Page 1 of 47 Issue: November 24, 2021
TECHNICAL REQUIREMENTS
CSEL Reachargeable Battery BB-2001A/U
Exhibit A Page 2 of 47
TABLE OF CONTENTS
APPLICABLE DOCUMENTS
CONFIGURATION BASELINE
Configuration Change Process
Configuration
Application Management
Obsolescence Reporting
PACKAGING
Wood Packing Material
Military Packaging
SPECIALIZED TESTING
CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1
CDRL List
Individual CDRLs
Exhibit A Page 3 of 47
APPLICABLE DOCUMENTS
Military and Federal Standards MIL-STD-129R Military Marking for Shipment and Storage MIL-STD-130N Identification Marking of US Military Property
Military and Federal Specifications
Other Documents AG00000066 RevQ Special Packaging Instructions
Commercial Documents ISPM 15 International Standards For Phytosanitary Measures No. 15 4866112-007 Boeing Specification
Combat Survivor/Evader Locator System AN/PRQ-7 Hand-Held Radio Rechargeable Battery Performance Specification, Rev L dated 12 March 2009 with Change notices M01, M02, M03, M04, & M05
Security Documents
CONFIGURATION BASELINE
The applicable Configuration Baselines (CB), for the listed Configuration Item (CI) and/or Computer Software Configuration Item (CSCI), are as listed in the table below.
NSN Nomenclature Part Numbers/Drawings 6140-01-534-3856 BB-2001A/U Boeing Spec 4866112-007
W/CN M01, M02, M03,
M04, & M05
Configuration Change Process.
The awardee shall establish a system for managing the configuration changes to the item part number (IPN) baseline.
Exhibit A Page 4 of 47
Configuration.
Each CI, as developed/built and delivered, shall conform to the cited CB.
Application Management.
Application Management.
In performing Application Management, the Government must assess the impact of design changes to the Configuration Item. The Government is the Configuration Management authority on application management for all external applications and for all Major changes that affect the Commercial Item Part Number (CIPN) specified in paragraph 3.2.1. A Major change is defined as any change that will impact any of the following conditions of the IPN:
(a) Overall performance and Form, Fit, Function and Interface (F3I) Characteristics.
(b) Reliability, Maintainability and Survivability
(c) Electromagnetic Interference (EMI), air worthiness certification, or other pertinent requirement.
(d) Safety
(e) Support, operational and training requirements
(f) Impact on Technical Manuals, Repair Parts and Special Tools Lists (RPSTLs), DMWRs, Provisioning Parts List (PPL), etc.
(g) Impact on Cost and/or Schedule.
(h) Impact on test equipment, support equipment and associated software.
(i) Software.
Application Activity.
The Government is an Application Activity (AA) for changes that affect the Awardee ’s CIPN. The CSEL Project Office possesses document change authority over the changes affecting the IPN. Any changes that affect the conditions identified above shall be submitted for Government approval IAW the procedures outlined below. Configuration changes not directly affecting the configuration baseline conditions identified do not require Government approval.
Departures from CB.
Changes that affect the CIPN conditions shall be submitted for Government approval in accordance with this document and the DD Form 1423 for DI-MISC-80711A.
Changes from Boeing.
Changes directed by Boeing shall not require prior government approval. The Government shall be notified of any such changes with effectivity data.
Request For Change (RFC).
Exhibit A Page 5 of 47
The Request For Change (RFC) includes both the engineering change and the supporting documentation by which the change is described and suggested. An RFC describes changes to the CI and associated Contractor documents and data that are affected by the proposed engineering change. The RFC also describes a full impact analysis of the effect of the change on the logistics, interface, design, cost and schedule requirements of the
IPN.
RFCs could be generated as any of the following categories: Change Directive; Change Request; Engineering Change Package; Engineering Change Proposal; Engineering Change Request; Engineering Change Memo;
Engineering Change Notice.
RFCs shall contain the following elements as a minimum:
(a) A unique change identifier; identification of originating organization and responsible individual.
(b) Change classification,
(c) Identification of product(s) (including components and interfacing products) affected by the change.
(d) Change description and scope (including effects on performance, operation, maintenance, servicing, operation and maintenance training, repair parts, support and test equipment, cost, schedule, and any other effect on physical, functional, and logistics characteristics of the CIPN).
(e) Reason and justification for the change and consequences of not incorporating the change.
(f) Estimated cost increase or savings.
(g) Change implementation (and effectivity) and impact on delivery schedule.
(h) Criteria, if any, for retrofitting products.
Awardee -approved changes that adversely impact any of the IPN conditions listed may require re-evaluation by the Government of the IPN. Re-evaluation may include operational testing re-assessment or re-assessment of the logistics impact of the proposed change. The government has the right to review any configuration changes and determine if a new First Article Test (FAT) and/or Safety Assessment Report (SAR) is necessary; the awardee must follow the directon of the government. An approved change to the design of the IPN must be verified to ascertain that the IPN has achieved the functional attributes and requirements specified in the baselined Product Definition Information and that it is adequate for its intended purposes. The Government is not obligated to accept any IPNs that no longer meet the Government’s requirements as established by the IPN at the time of contract award.
Obsolescence Reporting In addition to the above, the awardee shall notify the Government of obsolescence issues only if they require configuration changes leading to a new FAT/SAR or a stop in production. Reporting method should be in accordance with the relevant requirements of DI-MGMT-81941.
Exhibit A Page 6 of 47
PACKAGING
Wood Packing Material Wood packing material includes pallets. See DLAD 52.247-9012 Requirements for Treatment of Wood Packaging Material (WPM).
Military Packaging DS7029 and/or DS7033 Preservation, Packing and Marking Instructions
MIL- STD- 2073-1
Special packaging AG00000066
DS7029 - DS7033 LEGEND
Qty Quantity Prot Req Protection Required PKG-REF Packaging Reference (Military/Federal Specification or Standard) SPI Special Packaging Instruction LPK Level of Packing QUP Quantity per Unit Pack ICQ Intermediate Container Quantity Pkg Reqmt Codes Packaging Requirement Codes when PKG-REF cites MIL-STD-2073-1 The below codes are for special markings:
PC Project Code WG Warranty/Guarantee SL Shelf Life BC Bar Code FMS Foreign Military Sales
Exhibit A Page 7 of 47
DS7029 - DS7033
NSN Prot Req PKG-REF or SPI LPK QUP ICQ Special Markings
Pkg J. J J J J J J J J J Reqmt I. II. III. IV. V. VI. VII. VII.a IX X Codes (MP) (CD) (PM) (WM) (CD) (CT) (UC) (IC) (PK) (SM) 6140-01-534-3856 Military AG00000066 B 001 n/a n/a n/a n/a n/a n/a n/a n/a/ n/a n/a
SPECIALIZED TESTING
DLADS 52.247-9012 Sampling shall be IAW Boeing specifications 4866112-007.
AN/PRQ-7 Battery Functional Testing
AN/PRQ-7 Battery Functional Testing as described by 4866112-717 shall be performed by Boeing. The awardee is responsible for making arrangements with, and funding Boeing to perform this test. The POC at Boeing is:
Dave Wallace Boeing Contracts Phone: 714-421-9810 Email: david.e.wallace2@boeing.com
Additionally, the awardee will need to obtain an AN/PRQ-7 (battery test variant with no GPS and VUM module) with the 4866112-040 Battery Test Software preloaded (called out in 4866112-040 para 4.8.19.2). This radio can be obtained from Boeing, there is no additional cost for this service.
BB-2001A/U 4866112-007 paragraph 3.5.12 BATTERY PACK CHARGING
The Government does not currently posess the information to adequetly describe the battery to charger interface. A charger and adapters will be available as Government Furnished Equipment (GFE) if required for the awardee to meet this requirement. All items provided as GFE shall be returned at the conclusion of the contract in the condition provided both visually and mechanically. The cost of any item not able to be returned in this form shall be incurred by the awardee .
The battery to charger interface shall be provided to the Government as part of this contract and as part of the Tech Data Package IAW CDRL C001 DI-SESS-80776A. The Government shall have full rights to this data and can openly share it with other vendors in the procurement of batteries and chargers.
First Article Testing (FAT)
FAT is required for a new battery or one that underwent a configuration change compared to the previous version.
FAT samples are tested by the awardee, Boeing (AN/PRQ-7 battery functional testing, see above), the Army and the Navy. For the Army, batteries shall be tested at the US Army C5ISR RTI Power Division laboratory. All FAT samples are selected from the same minimum quantity of 50 batteries that have passed Group A Inspection (see further explanation below):
1. Awardee responsibilities:
a. Point of Contact at C5ISR – Sergio Mancilla, sergio.f.mancilla.civ@army.mil mailto:david.e.wallace2@boeing.com
b. C5ISR Test Plan – The awardee shall request from C5ISR within 15 DAC a test plan for the C5ISR testing to be included in the FAT Plan. C5ISR requires 15 days to prepare the plan and send it to the awardee.
The request shall include:
Subject: Contract ______, Request for C5ISR Test Plan
Contract reference directing you to request a test plan _________
Contract Estimated time samples will be shipped - _________
Forward the test plan to __________________
c. C5ISR Testing Samples
(1) The number of samples required is 8 batteries. The batteries shall be selected by the Government Quality Assurance Representative (QAR) taken from a minimum quantity of 50 batteries that have passed Group A Inspection. The samples shall be shipped NLT 180 DAC to C5ISR at the awardee’s expense.
(2) All samples shall be complete unaltered batteries.
(3) The samples shall be shipped with a DD-Form-1222.
(4) Shipping address:
C5ISR RTI Power Division ATTN: Sergio Mancilla (443-395-4399) Building 5100, Room 132 6631 Cyber Street
APG, MD 21005-1852
d. Test Report – C5ISR will require 60 days to complete testing and prepare the report. The C5ISR’s report will be provided to the awardee NLT 240 DAC. A copy of the report will be included in the FAT Report.
e. Retesting - The government will fund the testing of the initial set of samples. Any retesting shall require funding from the awardee .
f. Disposition of Samples – C5ISR will determine disposition of batteries to include disposal or retention for additional analysis except for any failure batteries that the awardee has requested in writing to be returned. The awardee shall arrange for the return of any samples.
2. C5ISR responsibilities:
a. Provide the Contracting Officer with a POC for the testing.
b. Provide the awardee with a C5ISR approved test plan for the required C5ISR testing. Test plan shall include approval signatures, document number, awardee name, contract number, and NSN.
c. Perform the required testing.
d. Provide the awardee with a C5ISR approved test report. Report shall include approval signatures, document number, awardee name, contract number, and NSN.
3. Awardee Testing samples
a. The number of samples required is 6 single cells and 24 batteries. The batteries shall be selected by the
Government Quality Assurance Representative (QAR) taken from a minimum quantity of 50 batteries that have passed Group A Inspection. The single cells shall also be selected by the QAR taken from a minimum quantity of 10 single cells that have gone through the awardee’s standard incoming cell inspection during regular production.
b. The batteries and single cells are tested at the awardee’s facility location (testing at external test facilities is allowed), however certain tests are typically performed at Boeing due to the nature of the specialized equipment involved. Boeing typically conducts the AN/PRQ-7 Battery Functional Testing at Boeing’s facility. As mentioned above in the AN/PRQ-7 Battery Functional Testing section, the awardee will need to obtain, and Boeing will provide, special variant AN/PRQ-7 radios to perform the EMI testing as part of the Additional Environmental Requirements testing.
c. The awardee will have to provide Boeing with the 12 batteries that are needed for the AN/PRQ-7
Battery Functional Testing. These batteries are samples 1-12 taken from the group of 24. The batteries are typically shipped ground with regulations for lithium-ion batteries. Once the batteries have completed the Functional testing, Boeing will ship them back to the awardee to continue on with FAT testing.
d. All samples shall be complete and unaltered.
Navy Testing (FAT):
Batteries must attain approval under Lithium Battery Safety Program per Naval Sea Systems Command
S9310-AQ-SAF-010.
1. The awardee shall be solely responsible for arranging with the Navy for the required testing.
2. Awardee responsibilities:
a. Quote for bid/proposal - During the solicitation phase of the acquisition, the company shall contact by email the following POC’s with a request for a quote for the Navy testing. The cost for the Navy testing shall be included in the price proposal.
Julie Simmons, julie.a.simmons18.civ@us.navy.mil
Mark Tisher, mark.t.tisher.civ@us.navy.mil
The following information shall be provided in the request (include “Request for Quote” in subject line):
(1) Solicitation number
(2) Battery nomenclature and NSN
(3) Duration of contract to be awarded; include option periods
The Navy will provide the quote and a POC, and specify the location for the testing. If the company is awarded the contract, the POC provided by the Navy will be the POC for all Navy testing actions related to this solicitation/contract.
b. Test Services Agreement (TSA) or Cooperative Research and Development Agreement (CRADA)
In order for the Navy to test batteries for awardee , a TSA or CRADA, depending on the testing location, will be required.
(1) TSA
(1)a In order for the Navy to test batteries for aawardee , a TSA between the awardee and the
Navy must first be in place in accordance with Title 10, United States Code, Section 2539b (Availability of Samples, Drawings, Information, Equipment, Materials, and Certain Services). The awardee shall contact the Navy NLT 15 DAC to initiate the process of establishing the agreement.
(1)b The TSA will apply to the contract and all battery types to be tested.
(1)c The agreement has an expiration date. The awardee shall request an agreement that will be in effect for the life of the contract.
(2) CRADA – The TSA requirements above also apply to a CRADA
c. Navy Test Plan – The awardee shall request from the Navy within 15 DAC a test plan for the Navy testing to be included in the FAT Plan. A navy test plan is required for each battery type to be tested.
Navy requires 15 days to prepare the plan and send it to theawardee .
d. Safety Data Package Requirements (SDPR) – The awardee shall submit to the Navy within 15 DAC a SDPR (form included in this document) completed to the maximum extent possible for each battery type to be tested. The completed form shall be updated as additional data becomes available and an updated form will be submitted to the Navy. A fully completed form shall be submitted with the FATP.
e. Navy Testing Samples
(1) The number of samples per battery will be 15. The batteries shall be selected by the Government
Quality Assurance Representative (QAR) taken from a minimum quantity of 50 batteries that have passed Group A Inspection. The samples shall be shipped NLT 180 DAC to the Navy at the awardee’s expense.
(2) The fifteen (15) samples shall be as follows:
Three (3) complete unaltered batteries Six (6) unsealed batteries allowing access to cells and circuitry Six (6) unsealed batteries with a bypass for battery management circuitry, to allow for direct over-charging and over-discharging of the cell pack
(3) The samples shall be shipped with a DD-Form-1222 and the SDPR. Each battery type is to be packaged in a separate box. Mark each box as follows:
Samples for Navy Safety Testing Battery XXX
Shipping address will be provided in the Navy test plan.
f. Test Report - The Navy will require 60 days to complete testing and prepare the report. The Navy’s report will be provided to the awardee NLT 240 DAC. A copy of the report will be included in the FAT Report.
g. Funding - The awardee shall provide to the Navy the required funding for the testing NLT 150 DAC.
Testing shall not start until the required funding has been received at the Navy. Additionally, the TSA must be in place in order for the Navy to accept the funding.
h. Retesting – The quote by battery type provided by the Navy shall cover the initial testing of 15 samples. Any retesting shall require additional funding from the awardee .
i. Disposition of Samples – The Navy will dispose of the samples 30 days after the test report is issued to the awardee except for any failure batteries that the awardee has requested in writing to be returned.
The awardee shall arrange for the return of any samples.
3. Navy responsibilities:
a. Provide the company with a quote, POC and location for testing.
b. Assist the awardee to establish testing agreements.
c. Provide the awardee with a Navy approved test plan for the required Navy testing. Test plan shall include approval signatures, document number, awardee name, contract number, NSN, and battery type.
d. Include shipping instructions for the samples in the test plan.
e. Perform the required testing.
f. Provide the contractor with a Navy approved test report. Report shall include approval signatures, document number, awardee name, contract number, NSN, PIN and BA number.
Group B Inspection (Production):
Group B inspections as described by 4866112-007/M 01, para. 4.6.2 shall be performed by the awardee.
The responsibilities of the awardee are as follows:
1. Group B inpections shall consist of the tests specified in Table 7 of 4866112-007/M 01 in the order shown. Sample size shall be eight (8) randomly selected samples (by the government QAR) which have been subjected to and passed Group A Inspection as described in 4866112- 007/M 01. These tests are not satisfied by First Article Inspection.
2. The Group B samples shall be selected after a minimum of 300 battery packs have been produced from the first month’s scheduled production quantities. Group B inspections shall continue to be performed every 3 months from that point, while in production of any given contract lot. Any new order will require restart of the Group B inspection IAW requirements stated above.
3. If any battery fails any Group B inspection, the shipment lot will be rejected. Failures due to operator or test instrumentation error shall be recorded and new sample units, selected by the government QAR, that have passed Group A Inspection can be used to rerun the test. Re-testing shall start at the beginning of the test in which the operator/test instrumentation error failure occurred.
Group C Inspection (Production, Annual Inspection):
Group C Inspection as described by 4866112-007/M 01, para. 4.7 shall be performed by the awardee.
The responsibilities of the awardee are as follows:
1. Group C inspection shall consist of the tests specified in Table 8 of 4866112-007/M 01 in the order shown. These tests shall be performed between 8 to 12 months after successful completion of First Article Inspection and shall be repeated every 12 months thereafter until contract completion.
2. The test shall be conducted on samples that have passed Group A Inspection as described in
4866112-007/M 01 from the current month’s production lot. Group C samples shall be selected after a minimum of ten percent of the current month’s scheduled production is completed. The required number of samples is 12 and shall be selected by the government QAR.
3. The Cycle Life test samples shall be subjected to the cycle life inspection for 28 cycles.
4. Failures due to operator or test instrumentation error shall be recorded and new sample units, shall be selected by the government QAR, that have passed Group A Inspection can be used to rerun the test. If any battery fails any Group C inspection, the current shipment lot will be rejected.
(Draft) 28 August 2008
Safety Data Package Requirements References:
S9310-AQ-SAF-010, 1.2.2.1 & 1.4.2
BATTERY PIN: TYPE
DESIGNATION:
MFGR PART
NUMBER:
ELECTROCHEMISTRY:
PREPARED BY: (MFGR) (CAGEC)
ADDRESS:
Assessment POC: (Name) (Title)
(Phone) (e-mail)
NSN:
Contract Number:
INSTRUCTIONS:
Complete form in accordance with the schedule established by the contract or purchase order.
Complete all blanks exclusive of the revision block. All applicable data is required.
Unless specifically asked for a minimum (MIN) or maximum (MAX) value, use nominal or average values for numeric entries.
To change status of a checkbox: Right click on the empty box; select “Properties” from the pull-down menu; Select “Checked”; the status block for “Not Checked” will automatically deselect.
This template is provided in Microsoft Word format; when completed, the form shall be saved in Read Only format, PDF or Microsoft Word.
Once completed, the form shall be provided in accordance with the delivery requirements of the contract or purchase order.
REVISION BLOCK
REV. DESCRIPTION DATE APPROVED
PARAMETER CELL BATTERY
Electrode Type or Alignment (i.e., Bobbin, spirally wound, etc…):
N/A
MAX Open circuit voltage:
MIN Open circuit voltage:
MAX Closed circuit1 voltage:
MIN Closed circuit1 voltage:
Ampere-Hour1 rating:
Watt-Hour1 rating:
MAX Continuous
Discharge Rate (MCDR):
MAX Weight of lithium:
Cell quantity: N/A
Series/Parallel2 configuration:
N/A
Cell type(s)3 or P/N(s): N/A Hermetically sealed (Y/N): N/A Cell Shape (Cylindrical or
Prismatic):
N/A
Describe any additional cell feature designed to prevent electrolyte leakage.
N/A
NOTES:
1For closed circuit voltage, capacity, and energy ratings, use a C/10 discharge load at 70ºF (21ºC). The value “C” is the rated ampere-hour capacity.
2Series/Parallel configurations shall be designated as xS/xP; i.e., a battery with 5 cells in series and no parallel cell strings will be designated 5S/1P. A battery with 4 cells in series and 3 parallel strings will be designated 4S/3P. A single-cell battery will be designated 1S/1P.
Multi-section batteries will be designated as xS/xP+xS/xP, i.e., a two-section battery with a single cell string of 5 cells in each section will be designated as 5S/1P+5S/1P.
3If more than one cell type will be used for this battery, provide rationale below and describe any additional safety features required as a result if any (add more lines if necessary):
DD Form 1423-1, DI-NDTI-81307
CELL RATIONALE ADDITIONAL SAFETY FEATURES
BATTERY DIMENSIONS (inches) VOLUME GEOMETRY1 WEIGHT Height Width Depth DIA In cubic inches Cylindrical Rectangular lbs.
Other (Specify): grams
COMPONENT DESCRIPTION (Part number, materials, dimensions, weight, certifications, flammability rating, temperature range, as applicable)
Connector:
Terminals:
Enclosure:
IF Used: POTTING FILLER Material
(include MSDS if applicable):
Flammability rating (cured):
Temperature range (cured):
Controls (see S9310, 1.4.1.3):
CHARACTERISTIC DESCRIPTION
Storage Temperature
Range:
Operating Temperature Range:
Barometric Pressure Range (if applicable):
Features employed to prevent water intrusion during testing:
Shelf Life:
Functional Life (Hours): MCDR: 10% MCDR: 1% MCDR:
Intermittent operation (C/30 discharge rate, 8 hours on, 16 hours off):
Operation in extreme2 cold:
Operation in extreme2 hot:
Use outside3 of pressure range (if applicable):
1Include an oblique, cabinet projection pictorial drawing as defined by ASME Y14.4, to include details showing all battery enclosure seams and effects of any draft angles used.
2Extreme conditions are those outside of the listed ranges.
SAFETY FEATURES BATTERY CELL
Short circuit (Internal):
Short circuit (Accidental; see S9310, 1.4.2.5):
Over-current protection: FUSE:
Slow-Blow Medium Blow Fast Blow
Positive Temperature Coefficient
(PTC)
Other (Specify):
Part Number:
Trip/Open Rating:
Where located1 in battery circuit? N/A Over-temperature (thermal) protection:
Type: P/N:
Trip/Open Rating:
Where located1 in battery circuit? N/A
Vent Mechanisms
Charge Protection (If applicable, specify how charge protection will be accomplished):
Cell/Battery Yield Pressure (See S9310, para. 1.2.2.1.12)
What design features are employed (if any) to assure that the battery will not be adversely affected by changes in barometric pressure?
What design features are employed to prevent fragmentation of the battery enclosure during testing in accordance with 4.6.3?
Interchangeability – What design features are employed (if any) to assure that the battery will not be interchangeable with commercial batteries used in consumer products?
1Include an electrical diagram of the battery using graphic symbols as defined by IEEE Std. 315 (ANSI Y32.2).
PRODUCT SAFETY IN PRODUCT REALIZATION & MANUFACTURING:
Lessons Learned DESIGN PROCESS Contaminants in basic cell components
Electrolyte mixing process
Minimum amount of carbon
Balance in active materials
Electrode alignment
Avoiding use of tapes or sealing methods on electrode core wind
Providing strong weld adhesion of positive cell tab
Cell closure processes
Weld burrs on top-shells
Assurance for heat-shrink materials
Sealing process for battery enclosures (Watertight Integrity)
NOTES
1Process controls may include requirements applied to purchase orders for purchased materials or components.
SPECIAL CONTROLS OR PRECAUTIONS. Describe any controls or precautions that may be necessary or are recommended, if any, in the listed areas.
Fire Fighting1
Transportation1
Storage1
Use1
Disposal1
Exposure to toxic substances1 in the event of leakage, venting, rupture explosions, or fires.
NOTES
1Include a Material Safety Data Sheet (MSDS) or Product Safety Data Sheet (PSDS), as applicable. If any of the information required above is provided in the MSDS or PSDS, cite the page and section or paragraph reference on the sheet rather than repeating the information here.
PREPARER’S SIGNATURE BLOCK:
Name: Title: Date:
Phone: E-mail:
ATTACHMENTS. Please list any attachments to this file - including pictorial drawings, electrical diagrams & MSDS/PSDS - and where applicable, include the file name in the description of the attachment.
NO. DESCRIPTION
CONTRACT DATA REQUIREMENT LIST (CDRL) DD 1423-1
CDRL List
CDRL
Data Line No. DID Identification Title A001 DI-MISC- 80711A Scientific and Technical Reports – Configuration Management A002 DI-MGMT- 81941 Obsolescence Alert Notice B001 DI-NDTI- 80566A Test Plan – Group B Inspection Plan B002 DI-NDTI- 81307A First Article Qualification Test Plan – FAT Plan B003 DI-SAFT- 80102C Safety Assessment Report (SAR) - SAR Plan B004 DI-NDTI- 80566A Test Plan – Group C Inspection Plan C001 DI-NDTI- 80809B Test/Inspection Report - Group B Inspection Report C002 DI-NDTI- 80809B Test/Inspection Report – First Article Test Report C003 DI-SAFT- 80102C Safety Assessment Report (SAR) - SAR C004 DI-NDTI- 80809B Test/Inspection Report - Group C Inspection Report D001 DI-SESS- 80776A Technical Requirements -Battery to charger interface
Individual CDRLs:
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Original Form Approved OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP X TM OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
BA-2001A/U Rechargeable Battery
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
A001 Scientific and Technical Reports Configuration Management
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MISC-80711A Technical Requirements FCDD-ISR-HFF INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
LT ASREQ NLT 7 DAYS b. COPIES
SECT. B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Draft Final
ASREQ
Reg
Repro
16. REMARKS: Data Item Description DI-MISC-80711A: follow instructions in this contract for departures from the configuration baseline
Once the contractor identifies a necessary change to the configuration baseline, notify the government immediately/NLT 7 days.
Government requires 30 days to review and comment on the submission of change.
Data shall be submitted and exchanged electronically in Microsoft Office 2016 or later suite of applications (MS Word, Excel, Power Point, PDF). Attachments exceeding email system limits shall be delivered via DoD SAFE https://safe.apps.mil. Alternate formats may be allowed subject to Government review and approval.
FCDD-ISR-HFF
ACO
PCO
QAR
15. TOTAL 4
G. PREPARED BY H. DATE I. APPROVED BY J. DATE
Laura Cristo
Electronics Engineer
Mark Caringi
Chief, Power & Environmental Control Readiness Branch https://safe.apps.mil/
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP X TM OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
A002 Obsolescence Alert Notice Configuration Management
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-MGMT-81941 Technical Requirements FCDD-ISR-HFF INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
LT ASREQ NLT 7 DAYS b. COPIES
SECT. B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Draft Final
ASREQ
16. REMARKS:
Data Item Description DI-MGMT-81941: Follow instructions in the Requirements Section as relevant to the obsolescence issue.
Once the contractor identifies an obsolescence issue, notify the government immediately/NLT 7 days. Note: Only obsolescence issues that would affect the configuration baseline need be reported.
Government requires 30 days to review and comment on the notice.
Data shall be submitted and exchanged electronically in Microsoft Office 2016 or later suite of applications (MS Word, Excel, Power Point, PDF). Attachments exceeding email system limits shall be delivered via DoD SAFE https://safe.apps.mil. Alternate formats may be allowed subject to Government review and approval.
Laura Cristo
Form Approved
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER NDTI
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
B001 Test Plan Group B Inspection Plan
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-NDTI-80566A Technical Requirements FCDD-ISR-HFF INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD ONE/R 30 DAC b. COPIES
SECT. B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Draft Final
A SEE ITEM 16
Government requires 30 days for review/comments/approval of all submissions.
Submit final within 30 days of receipt of Government comments, via DD-250.
Item 13. Revisions – After the inspection plan has been initially approved, a revised inspection plan shall be submitted for review and approval (with DD250) when procedure or design changes affect the PLTP.
Each submission shall be delivered in PDF format on email attachment or CD ROM/DVD and shall include the contractor’s approval signatures. Attachments exceeding email system limits shall be delivered via DoD SAFE https://safe.apps.mil. The plan shall include the following:
SEE CONTINUATION PAGE
Laura Cristo
Chief, Power & Environmental Control
DD Form 1423-1, 1 Jun 90 PAGE 1 OF 2
CDRL B001 Block 16 Continuation Page:
1. The delineation and allocation of tests to be performed for each production lot and the order of such tests (this may be prescribed in applicable technical data).
2. Step-by-step test procedures for each test and the data sheets to be employed to document the results of testing.
3. Identification of required test facilities, equipment and personnel.
4. A table which cross references the paragraph number of the specification to the associated paragraph numbers of the Production Lot Inspection Plan.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER NDTI
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
B002 First Article Qualification Test Plan and Procedures
First Article Test Plan
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-NDTI-81307A Technical Requirements FCDD-ISR-HFF INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD ASREQ 30 DAC b. COPIES
SECT. B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Draft Final
Government requires 30 days for review/comments/approval of all submissions.
Submit final within 30 days of receipt of Government comments, via DD-250.
Item 13. Revisions – After the test plan has been initially approved, a revised test plan shall be submitted for review and approval (with DD250) when procedure or design changes affect the PLTP.
Each submission shall be delivered in PDF format on email attachment or CD ROM/DVD and shall include the contractor’s approval signatures. Attachments exceeding email system limits shall be delivered via DoD SAFE
Laura Cristo
Chief, Power & Environmental Control
DD Form 1423-1, 1 Jun 90 PAGE 1 OF 2
CDRL B002 Block 16 Continuation Page:
1. The delineation and allocation of tests to be performed for each production lot and the order of such tests (this may be prescribed in applicable technical data).
2. Step-by-step test procedures for each test and the data sheets to be employed to document the results of testing.
4. A table which cross references the paragraph number of the specification to the associated paragraph numbers of the First Article Test Plan.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
BA-2001A/U Rechargeable Battery
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
B003 Safety Assessment Report (SAR) SAR Plan
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE
18. ESTIMATED
TOTAL PRICE
DI-SAFT-80102C SEE BLOCK 16 CECOM Safety Office INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED 10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD ASREQ
45 DAYS
AFTER
ORDER
b. COPIES
SECT.
B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE
Draft Final
A LEAVE BLANK
Delete the Requirements instructions entirely of the DI- SAFT-80102C and follow instructions below.
Submit SAR via DD-250. Government requires 30 days to review and approve/disapprove.
The plan shall be delivered as an email attachment or CD ROM/DVD. Attachments exceeding email system limits shall be delivered via DoD SAFE https://safe.apps.mil. It will have the contractor’s approval signatures and shall be delivered in Adobe PDF format.
The SAR Plan will include the following:
SEE CONTINUATION SHEETS
PCO
CECOM SAFETY
15. TOTAL 0 5 0
Laura Cristo
DD Form 1423-1, 1 Jun 90 PAGE 1 OF 2
CDRL B003 Block 16 Continuation Page:
Safety Assessment Report (SAR) Test Plan. The awardee shall prepare a SAR Test Plan IAW the CDRL for DI-NDTI-80566A below. The SAR Test Plan shall include the following information:
(1) Cover page that includes contract number, awardee’s’s name, address, cage code, place of manufacture and assembly, date of submittal, signature blocks and signatures of author and approval authority and document version.
(2) Introduction and objectives.
(3) List of tests performed in tabular format, including references, length of time to perform tests, test milestone schedules.
(4) Identification of required test facilities and locations.
(5) Identification of equipment, (including serial numbers, calibration dates).
(6) Title of the test to be conducted, (the tests listed in Table 3 must be included as a minimum).
(7) Purpose of each test.
(8) Test and validation procedures for each test.
(9) Test parameters.
(10) Test requirements and test pass/fail criteria.
(11) Data sheets.
(12) The test plan shall also reference the approved FAT procedures used to perform the tests identified IAW Paragraph 4.2.2 of MIL-PRF-49080E and shall also include a brief summary of the FAT procedures mentioned above.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER NDTI
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
B004 Test Plan Group C Inspection Plan
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-NDTI-80566A Technical Requirements FCDD-ISR-HFF INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED
10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD ONE/R 180 DAC b. COPIES
SECT. B
8. APP CODE N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Draft Final
Government requires 30 days for review/comments/approval of all submissions.
Submit final within 30 days of receipt of Government comments, via DD-250.
Item 13. Revisions – After the inspection plan has been initially approved, a revised inspection plan shall be submitted for review and approval (with DD250) when procedure or design changes affect the PLTP.
Each submission shall be delivered in PDF format on email attachment or CD ROM/DVD and shall include the contractor’s approval signatures. Attachments exceeding email system limits shall be delivered via DoD SAFE
Laura Cristo
DD Form 1423-1, 1 Jun 90 PAGE 1 OF 2
CDRL B004 Block 16 Continuation Page:
1. The delineation and allocation of tests to be performed and the order of such tests (this may be prescribed in applicable technical data).
2. Step-by-step test procedures for each test and the data sheets to be employed to document the results of testing.
4. A table which cross references the paragraph number of the specification to the associated paragraph numbers of the Production Lot Inspection Plan.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuing Contracting Officer for Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:
TDP TM OTHER NDTI
D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR
BA-2001A/U Rechargeable Battery
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 17. PRICE GROUP
C001 Test/Inspection Report Group B Inspection Report
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTIMATED
TOTAL PRICE
DI-NDTI-80809B Technical Requirements FCDD-ISR-HFF INSERT
7. DD 250 REQ 9.DIST STATEMENT
REQUIRED 10. FREQUENCY 12. DATE OF FIRST
SUBMISSION 14. DISTRIBUTION IN
DD ASREQ 14 DAYS
AFTER TEST
b. COPIES SECT. B
8. APP
CODEONE/P N/A 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Draft Final
A
Delete Block 10 of DI-NDTI-80809B instructions entirely and follow instructions below.
Government requires 30 days for review/comments/approval of all submissions.
Submit final within 30 days of receipt of Government comments, via DD- 250.
The report shall be delivered as an email attachment or CD ROM/DVD.
Attachments exceeding email system limits shall be delivered via DoD SAFE https://safe.apps.mil. It shall have the contractor’s approval signatures and shall be delivered in PDF format.
The report shall be complete, accurate, and readable and shall provide sufficient data to determine that the hardware item meets all the requirements delineated in the contract. The report shall include the following:
Laura Cristo
Chief, Power & Environmental Control
DD Form 1423-1, 1 Jun 90 PAGE 1 OF 3
CDRL C001 Block 16 Continuation Page:
1. General Data.
a. Awardee 's name, address and CAGE code.
b. Contract number, delivery order and CLIN
c. Nomenclature, type number and (if assigned) stock number of item represented by the First Article.
d. Name and address of plant where First Article was fabricated and assembled.
e. Place and date of performance of tests.
f. Identification (including date) of applicable equipment specifications, associated amendments, exceptions to specifications and any waivers.
g. Identification of the approved inspection plan
h. report number
i. table of contents
j. awardee ‘sapproval blocks with signatures
k. name and address of requiring Government activity
l. report date
m. Date code and serial number of both awardee and Government FAT units.
2. Summary. For each test state the number of samples tested, results, dates, failures, corrective action, location of data and any other pertinent information.
3. Cross Reference. A table which cross-references the plan procedures and the data presented in the report.
4. Test Results. Complete test results showing actual or quantitative observations and all required calculations. Allowable tolerances for each parameter shall be presented. ‘GO/NOGO’ data shall be avoided wherever possible. Test data should also include the date that the test was performed, name of tester, name and signature of the Government verifier/witness (if applicable) and serial number of the equipment.
5. Failures. The report shall list all requirements not complied with during testing. If none, this should be explicitly stated. For each requirement not met, a failure analysis report shall be prepared for each failure and included in the Group B inspection report. As a minimum the failure analysis shall include the identification of the failed battery, description of the failure based on the specification, findings, root cause, corrective action, retest and the impact of the failure on other tests. A corrective action to remove the noncompliance will be proposed. This corrective action must include retest or other verification that the corrective action does remedy the problem/failure. The corrective action will address changes in design or manufacturing process which will preclude this deficiency in subsequent production units.
Verified corrective action must be implemented prior to awardee entering into production. A copy of the failure analysis reports shall be included in the report. The impact of the failure on the entire lot will be evaluated by the Government and a partial test, including tests that passed, or a full test may have to be repeated at no additional cost to the Government and at the sole discretion of the Government based on the failure analysis report.
6. FAT/Production Discrepancies. Any Government approved difference between the parts, materials and processes used to manufacture FAT samples and production units shall be documented in the inspection report. If there will be no difference between FAT and production, this shall be explicitly stated in the
7. Plan Deviations. Although the awardee is required to submit changes to the inspection plan to the
Government for approval prior to testing, if a deviation from the plan is discovered after testing, such deviations shall be clearly discussed in the report with their impact on the results. If no such deviations exist, then the report should state that the inspection plan was followed without any deviations. Any deviations from the inspection plan may result in a new, partial or full testing at the awardee ‘s expense as determined by the Government.
Public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA. 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .