Exhibit 2 - Special Provision for Maintaining Traffic.pdf
PDF 96 KB Posted
- Solicitation number
- RFP 591 260000002435 2
- Issued by
- Michigan
About this file
This is a Special Provision for Maintaining Traffic document issued by the Michigan Department of Transportation (MDOT) for bridge deck repairs at the I-75/I-69 Interchange in Genesee County, specifically on I-69 westbound from approximately 2.0 miles east of I-75 to I-75 in the city of Flint and Flint Township. The provision establishes comprehensive traffic management requirements for the project, including the utilization of specific maintaining traffic typicals (such as 100-GEN-KEY, 101-GEN-SPACING-CHARTS, 102-GEN-NOTES, and multiple framework configurations). The project involves staged construction with two primary phases: Stage 1 focuses on work on the northern half of the Ballenger Highway structure, Miller Road exit ramp structure, and structure over Swartz Creek, while Stage 2 addresses the southern half of the Ballenger Highway structure. Work zone speed limits are set at 60 miles per hour generally and 45 miles per hour where workers are present, with a maximum closure length of 0.75 miles on I-69 westbound. The contractor must submit an Internal Traffic Control Plan (Type A ITCP) at the preconstruction meeting, with the Engineer providing 7 calendar days for review and approval.
Traffic restrictions prohibit material delivery and lane closures during specified holiday periods (Labor Day) and special events (such as Bikes on the Bricks on September 12, 2026). The contractor must provide 7 calendar days' advance written notice to MDOT-Bay-Davison-LCRF@michigan.gov prior to implementing any lane closures or traffic shifts, with the Engineer having 4 calendar days to approve or request revisions. Traffic switch operations receive exemptions from lane rental and liquidated damage assessments for 8 hours per switch. The I-69 westbound exit ramp to I-75 northbound/Miller Road can be closed for up to 10 calendar days, while the I-69 westbound exit ramp to I-75 southbound can be closed for 5 calendar days. All temporary traffic control devices must comply with the Manual on Uniform Traffic Control Devices (MMUTCD) and ATSSA quality guidelines. Portable Changeable Message Signs (PCMS's) must be operational 7 calendar days prior to work initiation, and all traffic control devices must be removed from the project site within 14 calendar days of reopening. The contractor bears all costs associated with obtaining approved traffic control plans, providing and executing traffic control devices, and coordinating with emergency services, transit agencies, law enforcement, and schools.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit 1 - Log of Project.pdf | ||
| Schedule B - Pricing CORRECTED.xlsx | XLSX spreadsheet | |
| AMENDMENT 1 - Correction to Schedule B.pdf | ||
| Attachment A - Prevailing Wage Information & Rates for Genesee County.pdf | ||
| RFP 260000002435 - I-69 & I-75 bridge deck repairs.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MICHIGAN
DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
MAINTAINING TRAFFIC
DAV:SSP 1 of 7 APPR:Region:RJM:04-15-26
a. Description. This special provision consists of requirements and restrictions to maintain traffic on I-69 in the city of Flint, Flint Township, Genesee County.
b. General. Maintain traffic throughout the project in accordance with the standard specifications, typicals, and supplemental specifications in the contract and as described on the plans for this project.
c. Construction Influence Area (CIA). The CIA includes the right-of-way of the following roadways, within the approximate limits described below:
1. On I-69 westbound from approximately 2.0 miles east of I-75 to I-75.
2. In addition, the CIA includes the right-of-way of any designated detour route or alternate route, intersecting roads and ramps adjacent to the work zone for a distance of approximately 1/4 mile in advance of the work zone or as far as the construction or detour signing extends. The roads include but are not limited to I-75.
d. Traffic Restrictions. Maintain traffic in accordance with the Maintaining Traffic Typicals contained herein, except as noted below. Changes or adjustments to the Maintaining Traffic Typicals may be necessary to fit field conditions, subject to approval of the Engineer or as determined by the Engineer.
1. Utilize the following Maintaining Traffic Typicals:
A. 100-GEN-KEY
B. 101-GEN-SPACING-CHARTS
C. 102-GEN-NOTES
D. 103-GEN-SIGN
E. 104-GEN-AB
F. 203-FW-1LC-(R)
G. 205-FW-1LC-(R)-SHIFT
H. 230-FW-ExR-C
V4.0
EXHIBIT 2
https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=67f64e52-8d1e-43fa-80c6-67291cc005a2&fileName=100-GEN-KEY.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=6dfdabdf-c842-4cf5-8187-5f7d8565fd86&fileName=101-GEN-SPACING-CHARTS.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=10487024-3ab5-4ed6-a61c-90479a9b3abb&fileName=102-GEN-NOTES.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=65bd8527-32ef-4479-91bd-f5489d67b8d9&fileName=103-GEN-SIGN.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=db492f06-7ee8-450f-9850-a28522ea2ebd&fileName=104-GEN-AB.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=6cf42ca1-aaca-4b4d-aaf4-635545204691&fileName=203-FW-1LC-(R).pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=f425d28e-349a-4e35-a40b-6c57b77c183d&fileName=205-FW-1LC-(R)-SHIFT.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=46c0a247-3e95-497c-99c2-56ce8efd4891&fileName=230-FW-ExR-C.pdf
DAV:SSP 2 of 7 04-15-26
I. 300-SP-AW-2MILE
J. WZD-100-A
K. WZD-125-E
2. Do not deliver material, or close lanes (other than approved stage closures) during the holiday periods as defined in Table 1. Cover or remove “45 where workers present” signing during the holiday periods as defined in Table 1.
Table 1: 2026 Holiday Periods
Holiday Start Date and Time End Date and Time
Labor Day 3:00 p.m. Thursday, September 3rd 6:00 a.m. Tuesday, September 8th
3. Do not deliver material, or close lanes (other than approved stage closures) during the Special Events as defined in Table 2. Cover or remove “45 where workers present” signing during the Special Event periods as defined in Table 2.
Table 2: 2026 Special Events
Local Event Start Dates and Time End Date and Time
Bikes on the Bricks 6:00 a.m. Saturday, September 12th 6:00 p.m. Sunday, September 12th
4. Perform work and lane closures within the allowable time frames as shown in Tables 3 and 4, unless otherwise approved by the Engineer. Traffic switch operations on freeways may take place within the allowable times listed below in the traffic restriction tables and/or as otherwise approved by the Engineer. Additional lane, ramp, and/or roadway closures and shifts may be implemented during maintaining traffic stage and traffic switch operations with prior Engineer approval.
5. Traffic switch operations are exempt from lane rental assessments or liquidated damage assessments for 8 hours for each traffic switch. Perform traffic switch operations within the allowable “traffic restriction tables” as shown below.
A. A traffic switch is defined as a change in the existing (original or staged) traffic configuration which requires multiple (more than one) lane lines and/or edge lines to be relocated in a new location and the old lines to be removed either between construction stages, or maintenance of traffic stages.
https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=889440ce-9be7-4230-b0f4-1b7669b77cf0&fileName=300-SP-AW-2MILE.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=fc81bf1d-94e9-401c-9f92-ffac23f11ca2&fileName=WZD-100-A%20-%208in.pdf https://mdotjboss.state.mi.us/TSSD/getTSDocument.htm?docGuid=dde79207-ba89-41d8-b425-c7483d1bd9ea&fileName=WZD-125-E%20-%208in.pdf
DAV:SSP 3 of 7 04-15-26
Table 3: I-69 Westbound to I-75 Northbound Ramp Traffic Restrictions
Closure Type Start Time
End Time
M Tu W Th F Sa Su
Shoulder Closure with Shift (Miller Road Exit Ramp from I-75 NB)
00:00 24:00 5 5 5 5 5 5 5
Single Lane Closure on WB I-69 (with Detour for NB I-75 Ramp Traffic)
00:00 24:00 5 5 5 5 5 5 5
# = The number of times closures can take place during the project timeframe
Table 3: I-69 Westbound to I-75 Southbound Ramp Traffic Restrictions
Closure Type Start Time
End Time
M Tu W Th F Sa Su
Single Lane Closure with shift on WB I-69 (with Detour for SB I-75 Ramp Traffic)
00:00 24:00 10 10 10 10 10 10 10
# = The number of times closures can take place during the project timeframe.
6. The maximum closure length is 0.75 miles on I-69 westbound.
7. Close any dedicated lanes (exit, ramp, turn, etc.) prior to the location under construction.
8. When a lane is closed, place channelizing devices at cross streets and major drives to form a radius that clearly defines the approaches to the through and turning traffic.
9. Close the ramps below during a time frame that does not conflict with holidays or special events.
A. The following ramp can be closed for up to 10 calendar days.
(1) I-69 westbound exit ramp to I-75 northbound/Miller Road.
B. The following ramps can be closed for 5 calendar days.
(1) I-69 westbound exit ramp to I-75 southbound.
10. Unless otherwise directed by the Engineer, close entrance and exit ramps when working in the vicinity of the ramp(s).
e. Traffic General.
1. For any lane open to traffic, provide a minimum lane width of 11 feet with 2 feet of shy distance on both sides unless identified otherwise on plans.
DAV:SSP 4 of 7 04-15-26
2. Do not close lanes or utilize traffic regulation sequences where work can be accomplished with a shoulder closure. Do not occupy any part of the active traffic lane with personnel or equipment when utilizing a shoulder closure. Place lane closures and traffic regulation operations only in areas as show on the plans unless otherwise directed by the Engineer.
3. Prior to shifting traffic onto shoulders or opening any lanes/shoulders and/or ramps, remove, by sweeping all accumulated debris that has collected within the shoulder and/or within the closed lane/shoulder.
4. A speed reduction will be used. Set the work zone speed limit on I-69 westbound to 60 miles per hour (mph) and 45mph where workers are present.
5. Develop and submit to the Engineer an Internal Traffic Control Plan (ITCP) per subsection 104.11.B of the Standard Specifications for Construction. The requirements listed herein are the requirements for a Type A ITCP. Submit the Type A ITCP at the preconstruction meeting. The Engineer will have 7 calendar days to review the ITCP for approval or provide comments for revisions required to obtain approval. Include in the ITCP, at a minimum, the proposed ingress/egress locations for construction equipment and vehicles, traffic control devices that will be utilized to warn the motoring public of ingress/egress locations, and measures that will be taken to ensure compliance with the ITCP. Ensure that the ITCP minimizes conflicts between construction vehicles and motorists and maintains overall safety and mobility within the work zone. No work may begin prior to approval of the ITCP. Additional time required to obtain an approved ITCP will not be cause for delay or impact claims. All costs associated with obtaining an approved ITCP, providing and executing all parts of the approved ITCP including required traffic control devices, or resolving an incomplete or unacceptable ITCP will be borne by the Contractor.
6. Upon approval of the ITCP, notify the Engineer in writing 7 calendar days prior to the implementation of any lane closures or traffic shifts. The email address for this is MDOT-Bay- Davison-LCRF@michigan.gov. If this criterion is not met, no lane closures or traffic shifts will be allowed. The Engineer will have 4 calendar days to review the lane closure request for approval or provide comments for revisions required to obtain approval. Do not implement a lane closure prior to approval by the Engineer. In addition, notify the Engineer when the lane closure is removed or cancelled. The Lane Closure Notification/Request Form may be found at MDOT LANE CLOSURE NOTIFICATION/REQUEST FORM (state.mi.us) and will also be supplied to the Contractor at the preconstruction meeting.
7. Protect the work area at the end of each day. Close all open access points on the project to traffic with Type III barricades or other devices approved by the Engineer.
8. The Engineer will be responsible for notifying emergency services, transit agencies, law enforcement and schools prior to any lane closures, detours or major traffic shifts. In addition, the Contractor will be responsible for working with and complying with any coordination that is necessary with the Department and emergency services, transit agencies, law enforcement and schools. All costs associated with these coordination efforts will be considered included in the pay item “Minor Traf Devices”.
9. Obtain all necessary permits from local governments within areas of local jurisdiction, including noise/dust ordinance waivers when required, prior to placing construction signing on local roads.
https://mdotjboss.state.mi.us/SpecProv/specBookHome.htm mailto:MDOT-Bay-Davison-LCRF@michigan.gov mailto:MDOT-Bay-Davison-LCRF@michigan.gov mailto:MDOT-Bay-Davison-LCRF@michigan.gov https://mdotjboss.state.mi.us/webforms/GetDocument.htm?fileName=0561.pdf https://mdotjboss.state.mi.us/webforms/GetDocument.htm?fileName=0561.pdf
DAV:SSP 5 of 7 04-15-26
A. The Department will reimburse permit costs in accordance with subsection 107.02.A of the Standard Specifications for Construction. Adhere to all requirements made by local maintaining agencies regarding placement of traffic control devices prior to closing lanes on roadways not under MDOT jurisdiction.
10. Remove all temporary traffic control devices from MDOT right-of-way during any shut down periods unless needed for directly maintaining or channelizing traffic. No additional payment will be made for removal and/or redeployment of these devices except for in the case of an approved extension of time.
11. Cover or remove construction signing that refers to work zone speed when work at a location is planned to be inactive for a period greater than 2 days, unless otherwise specified on the plans or as directed by the Engineer.
12. Once work is initiated that includes any lane restrictions, that work must be continued daily until completed. A lack of work activity for more than 3 days will require the removal of lane closures at no expense to the Department.
f. Stage Construction. Maintain traffic in accordance with the restrictions listed in section
d. Traffic Restrictions and the sequence of operations contained herein. Use of an alternate traffic control plan is subject to review and approval by the Engineer.
1. Stage 1- Work on the northern half of Ballenger Hwy structure, Miller Road exit ramp structure and structure over the Swartz Creek.
A. Close the right lane of I-69 westbound. Continue this lane closure into the ramps to I-75. Close the ramp to I-75 northbound/Miller Road.
B. When needed, close the shoulder of the I-75 northbound exit ramp to Miller Road.
Shift ramp traffic as needed during work operations on this structure.
C. Using PCMS boards, detour westbound I-69 to northbound I-75 traffic to northbound I-475 to I-75. A secondary detour should be posted as well that takes traffic onto southbound I-75 to the Bristol Road interchange.
2. Stage 2- Work on the southern half of the Ballenger Hwy structure.
A. Close the right lane of I-69 westbound. Continue this lane closure into the ramps to I-75 and shift traffic. Close the ramp to I-75 southbound.
B. Using PCMS boards, detour westbound I-69 to southbound I-75 traffic to southbound I-475 to I-75. A secondary detour should be posted as well that takes traffic onto northbound I-75 to the M-21 interchange.
g. Detours.
1. Do not detour traffic until all proposed contract work on the detour route is completed, inspected, and approved by the Engineer.
2. Using PCMS boards, detour traffic as outlined in the section f. Stage Construction.
https://mdotjboss.state.mi.us/SpecProv/specBookHome.htm
DAV:SSP 6 of 7 04-15-26
h. Bridge Work.
1. Use Mobile Attenuators (MAs) on all roadways for false decking and other work as directed by the Engineer. Placement of MA’s will be as directed by the Engineer. Relocating MAs will be included in the payment for this item. Remove MAs from the roadway when not in use. If the Contractor elects to work at more locations than can be protected with the MAs provided, the Contractor must supply the additional MAs at their expense.
i. Traffic Control Devices. Ensure all traffic control devices are in accordance with the MMUTCD and must meet the “acceptable” criteria as defined in the ATSSA publication entitled “Quality Guidelines for Temporary Traffic Control Devices and Features” at the time of initial deployment and after each major stage change.
1. During non-working periods, place applicable advance signs and channelizing devices at specific locations, as directed by the Engineer, at no additional cost to the Department.
2. Notify the Engineer 24 hours in advance of when traffic control devices are being delivered to the project site, to allow for initial inspection of devices to take place.
3. Remove from the project site all traffic control devices (including detour signing) no longer needed for a particular operation and equipment for construction within 14 calendar days of reopening the shoulder/lane/roadway.
4. Channelizing Devices.
A. Ensure all devices have sufficient ballast to prevent moving or tipping. If moving or tipping occurs, place additional ballast, as directed by the Engineer, at no additional cost to the Department. No more than two ballasts are allowed on each channelizing device.
B. Do not use caution tape on channelizing devices for traffic control and/or pedestrian traffic control on this project.
C. Space channelizing devices at 50 feet for tapers and 100 for tangents or tighter as directed by the Engineer.
5. Temporary Signs.
A. Additional W20-1 (ROAD WORK AHEAD) signs are included in the quantities to be placed on all intersecting or adjacent roads where construction activities may be encountered.
B. Fabricate, install, and remove temporary sign overlays on existing signs with the pay item for Sign, Type B, Temp, Prismatic, Furn. Attach the overlay in accordance with subsection 812.03.D.2 of the Standard Specifications for Construction.
6. Portable Changeable Message Signs (PCMS’s). Use PCMS’s to warn traffic of upcoming and changing traffic control during the life of the project. Obtain approval from the Engineer for all sign locations.
https://mdotjboss.state.mi.us/TSSD/getCategoryDocuments.htm?categoryPrjNumbers=1403854,1403855&category=MMUTCD
DAV:SSP 7 of 7 04-15-26
A. Install PCMS’s and make them operational a minimum of 7 calendar days prior to the start of work, unless otherwise directed by the Engineer. Messages displayed on the PCMS’s must conform to MDOT’s policy on PCMS’s. Notify the Engineer if displaying a different message than those listed below for the project.
B. Do not leave PCMS’s with a blank screen within the clear zone of any roadway at any time. Remove the PCMS or display flashing dots in each corner of the screen when there is no message to display. Update the PCMS messages at the end of each work period to reflect current traffic lane restrictions.
C. Display the following two messages 7 days prior to work.
D. Display the following two messages during work.
j. Mobile Attenuators.
1. Mobile attenuators (MA’s) have been included in this project.
k. Measurement and Payment. Payment will be in accordance with the standard specifications unless otherwise specified. No additional payment will be made for the following activities:
1. Transporting traffic control items from site to site.
2. Providing sufficient vehicles and staff to make changes as-needed on site during work.
3. Providing sufficient vehicles and staff to remove closures from the roadway.
RAMP TO
I-75 NB
CLOSING
STARTING
XX/XX/XX
AT 6AM
RAMP TO
I-75 NB
CLOSED
USE
I-475 NB
TO I-75