This document is a Standard Form of Agreement Between Owner and Design-Builder - Cost Plus Fee with an Option for a Guaranteed Maximum Price, created by the Design-Build Institute of America (DBIA) for a state and local government contract opportunity.
The agreement outlines the terms and conditions for a design-build project, including the scope of work, contract documents, interpretation and intent, ownership of work product, contract time, contract price, payment procedures, termination for convenience, and the representatives of the parties. The contract allows for the establishment of a Guaranteed Maximum Price, which includes a Design-Builder's Contingency, and provisions for sharing any cost savings between the Owner and Design-Builder. The agreement also addresses performance incentives, bonds and insurance, and other contract provisions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Standard Form of Agreement Between Owner and Design- Builder – Cost Plus Fee with an Option for a Guaranteed Maximum Price
Document No. 530 Third Edition, 2022
© Design-Build Institute of America Washington, D.C.
DBIA Contract Document #530
SAMPLE
Design-Build Institute of America - Contract Documents
LICENSE AGREEMENT
By using the DBIA Contract Documents, you agree to and are bound by the terms of this License Agreement.
1. License. The Design-Build Institute of America (“DBIA”) provides DBIA Contract Documents and licenses their use worldwide. You acknowledge that DBIA Contract Documents are protected by the copyright laws of the United States.
You have a limited nonexclusive license to: (a) Use DBIA Contract Documents on any number of machines owned, leased or rented by your company or organization; (b) Use DBIA Contract Documents in printed form for bona fide contract purposes; and (c) Copy DBIA Contract Documents into any machine-readable or printed form for backup or modification purposes in support of your permitted use.
2. User Responsibility. You assume sole responsibility for the selection of specific documents or portions thereof to achieve your intended results, and for the installation, use, and results obtained from the DBIA Contract Documents.
You acknowledge that you understand that the text of the DBIA Contract Documents has important legal consequences and that consultation with an attorney is recommended with respect to use or modification of the text. You will not represent that any of the contract documents you generate from DBIA Contract Documents are DBIA documents unless
(a) the document text is used without alteration or (b) all additions and changes to, and deletions from, the text are clearly shown.
3. Copies. You may not use, copy, modify, or transfer DBIA Contract Documents, or any copy, modification or merged portion, in whole or in part, except as expressly provided for in this license. Reproduction of DBIA Contract Documents in printed or machine-readable format for resale or educational purposes is expressly prohibited. You will reproduce and include DBIA’s copyright notice on any printed or machine-readable copy, modification, or portion merged into another document or program.
4. Transfers. You may not transfer possession of any copy, modification or merged portion of DBIA Contract Documents to another party, except that a party with whom you are contracting may receive and use such transferred material solely for purposes of its contract with you. You may not sublicense, assign, or transfer this license except as expressly provided in this Agreement, and any attempt to do so is void.
5. Term. The license is effective for one year from the date of purchase. DBIA may elect to terminate it earlier, by written notice to you, if you fail to comply with any term or condition of this Agreement.
6. Limited Warranty. DBIA warrants the electronic files or other media by which DBIA Contract Documents are furnished to be free from defects in materials and workmanship under normal use during the Term. There is no other warranty of any kind, expressed or implied, including, but not limited to the implied warranties of merchantability and fitness for a particular purpose. Some states do not allow the exclusion of implied warranties, so the above exclusion may not apply to you. This warranty gives you specific legal rights and you may also have other rights which vary from state to state.
DBIA does not warrant that the DBIA Contract Documents will meet your requirements or that the operation of DBIA Contract Documents will be uninterrupted or error free.
7. Limitations of Remedies. DBIA’s entire liability and your exclusive remedy shall be: the replacement of any document not meeting DBIA’s "Limited Warranty" which is returned to DBIA with a copy of your receipt, or at DBIA’s election, your money will be refunded. In no event will DBIA be liable to you for any damages, including any lost profits, lost savings or other incidental or consequential damages arising out of the use or inability to use DBIA Contract Documents even if DBIA has been advised of the possibility of such damages, or for any claim by any other party. Some states do not allow the limitation or exclusion of liability for incidental or consequential damages, so the above limitation or exclusion may not apply to you.
8. Acknowledgement. You acknowledge that you have read this agreement, understand it and agree to be bound by its terms and conditions and that it will be governed by the laws of the District of Columbia. You further agree that it is the complete and exclusive statement of your agreement with DBIA which supersedes any proposal or prior agreement, oral or written, and any other communications between the parties relating to the subject matter of this agreement.
DBIA Document No. 530 Page 1 © 2022 Design-Build Institute of America
INSTRUCTIONS
For DBIA Document No. 530 Standard Form of Agreement Between Owner and Design-Builder – Cost Plus Fee with an Option for a Guaranteed Maximum Price (2022 Edition)
Checklist Use this Checklist to ensure that the Agreement is fully completed and all exhibits are attached.
Page 1 Owner’s name, address and form of business Page 1 Design-Builder’s name, address and form of business Page 1 Project name and address Section 2.1.3 Identify other exhibits to the Agreement _______ Section 4.2 Note the optional provisions that are provided Section 4.3.2 Complete blanks for additional sum for use of Work Product Section 5.2.1 Complete blanks for calendar days and note the optional language that is provided Section 5.2.2 Insert any interim milestones (optional) Section 5.4 Complete blanks for liquidated damages and note the optional provisions that are provided _______ Section 5.5 If the parties select the option provided they have to insert an amount
Section 5.6 Complete blanks for early completion bonus and note the optional provision that is provided _______ Section 5.7 Note the optional provisions that are provided Section 6.1.2 Insert basis for pricing preliminary services (optional) Section 6.2.1 Choose basis for Fee and complete blanks Section 6.2.2 Insert financial arrangements for adjustments and note optional provisions Section 6.3.3 Complete blanks for markup; insert or attach personnel names, etc.
_______ Section 6.3.4 Note the optional provision that is provided _______ Section 6.4.4 Note the optional provision that is provided Section 6.6.1.1 Complete blanks for GMP, and note the optional provision that is provided Section 6.6.1.2 Complete blanks for Design-Builder’s Contingency Section 6.6.3.1 Choose method for sharing savings; complete blanks _______ Section 6.7.1 Note optional provision Section 7.1.1 Complete blanks for day of month Section 7.2.1 Complete blanks for retention percentage and note optional provision _______ Section 7.2.2 Note the optional provision that is provided Section 7.4 Complete blanks for interest rate Section 8.1.1 Choose overhead/profit method for termination for convenience Section 8.2.1 Complete blanks for percentages Section 8.2.2 Complete blanks for percentages Section 9.1.1 Insert Owner’s Senior Representative’s name, etc. (optional) Section 9.1.2 Insert Owner’s Representative’s name, etc. (optional) Section 9.2.1 Insert Design-Builder’s Senior Representative’s name, etc. (optional) Section 9.2.2 Insert Design-Builder’s Representative’s name, etc. (optional) Section 10.1 Attach Insurance Exhibit Section 10.2 Insert amount and conditions of bonds or other security and note the options that are provided Section 11.1 Insert any other provisions (optional) Last Page Owner’s and Design-Builder’s execution of the Agreement
DBIA Document No. 530 Page 2
General Instructions
No.
Subject
Instruction
1. Standard Forms
Standard form contracts have long served an important function in the United States and international construction markets. The common purpose of these forms is to provide an economical and convenient way for parties to contract for design and construction services. As standard forms gain acceptance and are used with increased frequency, parties are able to enter into contracts with greater certainty as to their rights and responsibilities.
2.
DBIA Standard Form Contract
Documents
Since its formation in 1993, the Design-Build Institute of America (“DBIA”) has regularly evaluated the needs of owners, design-builders and other parties to the design-build process in preparation for developing its own contract forms. Consistent with DBIA’s mission of promulgating best design-build practices, DBIA believes that the design-build contract should reflect a balanced approach to risk that considers the legitimate interests of all parties to the design-build process. DBIA’s Standard Form Contract Documents reflect a modern risk allocation approach, allocating each risk to the party best equipped to manage and minimize that risk, with the goal of promoting best design-build practices.
3. Use of Non-DBIA Documents
To avoid inconsistencies among documents used for the same project, DBIA’s Standard Form Contract Documents should not be used in conjunction with non-DBIA documents unless the non-DBIA documents are appropriately modified on the advice of legal counsel.
Moreover, care should also be taken when using different editions of the DBIA Standard Form Documents on the same project to ensure consistency.
4. Legal Consequences
DBIA Standard Form Contract Documents are legally binding contracts with important legal consequences. Contracting parties are advised and encouraged to seek legal counsel in completing or modifying these Documents.
5. Reproduction
DBIA hereby grants to purchasers a limited license to reproduce its Documents consistent with the License Agreement accompanying these Documents. At least two original versions of the Agreement should be signed by the parties. Any other reproduction of DBIA Documents is strictly prohibited.
6. Modifications
Effective contracting is accomplished when the parties give specific thought to their contracting goals and then tailor the contract to meet the unique needs of the project and the design-build team. For that reason, these Documents may require modification for various purposes including, for example, to comply with local codes and laws or to add special terms. DBIA’s latest revisions to its Documents provide the parties an opportunity to customize their contractual relationship by selecting various optional contract clauses that may better reflect the unique needs and risks associated with the project.
At no time should a document be re-typed in its entirety. Re-creating the document violates copyright laws and destroys one of the advantages of standard forms – familiarity with the terms.
7. Execution It is good practice to execute two original copies of the Agreement. Only persons authorized to sign for the contracting parties may execute the Agreement.
DBIA Document No. 530 Page 3
Specific Instructions Section Title Instruction
General Purpose of This Agreement
DBIA Document No. 530 (“Agreement”) should be used when the parties intend that Owner pay Design-Builder the Cost of the Work plus a Fee, with or without a Guaranteed Maximum Price (“GMP”). If there is uncertainty about Owner’s Project Criteria, or the Project Criteria remain to be developed by Owner and Design-Builder together, a cost-plus/GMP contracting approach is desirable.
If there is certainty as to Owner’s Project Criteria, a lump sum fixed price for the completion of all design and construction services may be suitable, especially when Owner procures Design-Builder’s services by competitive means. In such case, DBIA Document No. 525 should be used.
General Purpose of These Instructions
These Instructions are not part of this Agreement, but are provided to aid the parties in their understanding of the Agreement and in completing the Agreement.
General Related Documents This Agreement shall be used in conjunction with the General Conditions of Contract.
Other related Contract Documents are listed in Article 2 of this Agreement.
General Date
On Page 1, enter the date when both parties reach a final understanding. It is possible, due to logistical reasons, that the dates when the parties execute the Agreement may be different. Once both parties execute the Agreement, the effective date of the Agreement will be the date recorded on Page 1. This date does not, however, determine Contract Time, which is measured according to the terms of Article 5.
General Parties: Owner and Design-Builder
On Page 1, enter the legal name and full address of Owner and Design-Builder, as well as the legal form of each entity, e.g., corporation, partnership, limited partnership, limited liability company or other.
2.1.2 GMP Exhibit, GMP
Proposal
If a GMP is established upon execution of this Agreement, the GMP Exhibit must be attached pursuant to Section 6.6.1.1. If a GMP is established after execution of this Agreement, the GMP Proposal must be attached pursuant to Section 6.6.2. Both the GMP Exhibit and GMP Proposal will include those Basis of Design Documents Design- Builder uses as the basis for its GMP.
2.1.5 Construction
Documents
After execution of the Agreement, and consistent with the requirements of Section 2.4 of the General Conditions of Contract, Design-Builder will prepare Construction Documents, subject to Owner’s review and approval.
3.2 Order of
Precedence
The Contract Documents are listed in Section 2.1 in the order of their precedence. The GMP Exhibit and GMP Proposal are based on the Basis of Design Documents, which are comprised of various documents. The parties should strongly consider establishing the priority of the various documents comprising the GMP Exhibit or GMP Proposal to avoid disputes should discrepancies arise among the documents. Moreover, Section
2.1.3 recognizes that there may be other exhibits attached to this Agreement. If this is the case, the parties should discuss whether these exhibits should be part of the Basis of Design Documents. If these exhibits are not made part of the Basis of Design Documents, these exhibits will not take priority over the Basis of Design Documents in the event of a conflict.
3.3 Definitions Terms, words and phrases used in the Agreement shall have the same meanings used in the General Conditions of Contract.
3.4 Design
Specifications
Owner is cautioned that if the Project Criteria include design specifications there is case law holding that Design-Builder is entitled to rely on such information, and to the extent such information is not accurate, Design-Builder will be entitled to an adjustment in the Contract Price and/or Contract Time. Accordingly, to avoid such potential liability, Owner should consider using performance specifications.
DBIA Document No. 530 Page 4
4.1 Work Product
This Agreement provides that Design-Builder shall retain ownership of the Work Product it produces, but obligates Design-Builder to grant a limited license to Owner to use the Work Product according to the terms and circumstances described in Sections 4.2, 4.3,
4.4 and 4.5.
4.2 Owner’s Limited License Upon
Payment in Full
Design-Builder shall grant Owner, at Owner’s sole risk, a limited license to use the Work Product at the completion of the Work in connection with Owner’s occupation of the Project. This Section also provides the parties with the option of transferring ownership of some or all of the Work Product to Owner upon payment in full for all Work performed.
Generally, where Owner desires ownership of Work Product, it is sufficient to transfer ownership of unique architectural and design elements.
4.3
Owner’s Limited License Upon
Owner’s Termination for Convenience or Design-Builder’s
Election to Terminate
Owner should not use the Termination for Convenience Clause to obtain Design- Builder’s valuable design concepts, and then seek bids from other design-builders.
Therefore, where Owner terminates this Agreement for its convenience, and then decides to complete the Project with its own or third-party forces, Design-Builder shall grant Owner the rights set forth in Section 4.2, provided Owner pays Design-Builder all amounts due Design-Builder as required by the Contract Documents, including paying Design-Builder an additional sum per Section 4.3.2 for the use of the Work Product. In the event Design-Builder elects to terminate this Agreement for cause, for reasons set forth in Section 11.4 of the General Conditions of Contract, these same conditions apply to Owner’s use of the Work Product.
4.3.2 Additional
Compensation
To minimize disputes, the parties should negotiate prior to the execution of the Agreement the amount Owner shall pay Design-Builder for the use of Design-Builder’s Work Product in the event Owner terminates this Agreement for its convenience or Design-Builder elects to terminate this Agreement for cause. Enter this amount.
4.4
Owner’s Limited License Upon
Design-Builder’s Default
If Design-Builder is properly terminated for default, Owner is granted a limited license to use the Work Product to complete the Project, and Owner shall thereafter have the same rights and obligations as set forth in Section 4.2.
4.5
Owner’s Indemnification for
Use of Work Product
Owner’s use or alteration of the Work Product shall be at its sole risk, and Owner must agree to defend, indemnify and hold harmless Design-Builder and anyone working by or through Design-Builder, including Design Consultants of any tier.
5.1 Date of
Commencement
Design-Builder’s obligation to commence work is triggered by its receipt of a Notice to Proceed unless the parties mutually agree otherwise.
5.2.1 Substantial
Completion of the Entire Work
Enter the calendar days duration by which Substantial Completion has to be achieved.
The parties in this Section have the option of modifying the definition of Substantial Completion set forth in the General Conditions of Contract if they want to use a Temporary Certificate of Occupancy as the benchmark. If this option is selected, Substantial Completion will be deemed to be achieved no later than the date a Temporary Certificate of Occupancy is issued, if applicable to the Project.
5.2.2 Interim Milestones
It may be that some portions of the Work must be completed in phases or within a prescribed period of time to accommodate Owner’s needs. The parties may, at their option, identify these portions of the Work to be completed prior to Substantial Completion of the entire Work. Enter the number of the calendar days, starting from the Date of Commencement, for achieving Substantial Completion of these identified portions of the Work. If these portions of the Work are required to be substantially completed by certain milestone dates, enter those dates. The form does not provide a remedy to Owner if an interim milestone is not met. If Owner has special requirements as it relates to interim milestones, Owner may want to consider a remedy for Design- Builder’s failure to meet an interim milestone, as well as providing a bonus to Design- Builder for satisfying such interim milestone.
DBIA Document No. 530 Page 5
5.4 Liquidated
Damages
Owner should make a good faith evaluation of the amount that is reasonably necessary to compensate it for delay. Owner should not establish liquidated damages to penalize Design-Builder. Moreover, in the event a GMP is not established upon execution of the Agreement, it appears prudent for the parties to refrain from establishing liquidated damages until such time as the GMP is established.
Section 5.4 establishes a grace period between the Scheduled Substantial Completion Date and the assessment of liquidated damages in order to prevent disputes as to which party bears responsibility for only a few days of delay. The parties should enter the calendar days that may pass following the Scheduled Substantial Completion Date before liquidated damages will be assessed.
The parties are also provided the option of establishing liquidated damages if Design- Builder fails to achieve Final Completion within a specified number of days after Substantial Completion. If this option is selected, the parties must negotiate both the number of days and the liquidated damages amount. In negotiating liquidated damages, the parties should keep in mind that the amount of liquidated damages for failing to achieve Final Completion should be a considerably scaled down amount and should reflect the financial harm to Owner. In no case should the total amount of liquidated damages for the Project exceed an amount that is reasonably necessary to compensate Owner for Project delay.
The parties also have the option here of eliminating liquidated damages altogether, in which case Owner can recover actual damages for Project delay at an amount that is capped by the parties. Owner is cautioned that it still cannot recover consequential damages, as they are waived under Section 10.5.1 of the General Conditions of Contract.
5.5 Liquidated
Damages Cap The parties can agree to cap liquidated damages for delay at a negotiated amount.
5.6 Early Completion
Bonus
If the Project economics justify liquidated damages, then it may also be appropriate to couple these liquidated damages with an early completion bonus. The parties should enter the number of calendar days prior to the Scheduled Substantial Completion Date that will set the Bonus Date. Also, enter the amount of the bonus to be paid per day that will allow Owner to share with Design-Builder the economic benefits of early completion.
Moreover, in the event a GMP is not established upon execution of the Agreement, it appears prudent for the parties to refrain from establishing an early completion bonus until such time as the GMP is established. The parties also have the option in Section
5.6 of capping the early completion bonus at a negotiated amount.
5.7 Compensation for
Force Majeure Events
The parties are provided the opportunity of providing Design-Builder the right to receive compensation for Force Majeure Events. By selecting this option, the parties agree to modify Section 8.2.2 of the General Conditions of Contract, in which case the parties have to negotiate how many cumulative days of Force Majeure delays must occur before Design-Builder is entitled to either a negotiated amount per day for delay or the direct costs it has incurred as a result of such delay.
6.1.2 Optional Pricing
This Agreement allows the parties the flexibility to establish within the Contract Price a different payment basis for certain preliminary portions of the Work which may be necessary to permit Design-Builder to furnish Owner with a GMP. Alternatively, the parties may use DBIA Document No. 520 to perform certain preliminary design services prior to setting the GMP. Enter a description of any such services, the basis for determining the price, and the price to be paid.
6.2.1 Design-Builder’s
Fee
Enter the amount of Design-Builder’s Fee as a sum certain or as a percentage of the Cost of the Work. Design-Builder’s Fee shall be commensurate with the services it provides and the risk it assumes in providing single point responsibility to Owner.
DBIA Document No. 530 Page 6
6.2.2 Adjustments to
Design-Builder’s Fee
For additive Change Orders, the parties have to negotiate the Fee Design-Builder will receive. For deductive Change Orders, the parties have the option by checking the appropriate box to signify whether there will be no additional reduction or whether there will be an additional reduction based on a negotiated percentage.
6.3.3
Wages for Design- Builder’s
Employees at Principal or Branch
Offices
DBIA endorses reimbursing salaries and associated benefits of Design-Builder’s Project personnel, such as accountants, stationed at offices other than the field office, when to do so is more efficient and cost effective. Enter the percentage markup to be applied for Project-related overhead associated with such personnel. Insert, or attach as an exhibit, a list of such personnel and their job functions.
6.3.4 Employee Benefits
It may be simpler for the parties to agree on a multiplier (rather than actual costs) to compensate Design-Builder for employee benefits. Accordingly, the parties may want to insert the multiplier to be applied to the wages and salaries of such reimbursable employees.
6.3.7 Costs for
Defective/Non- Conforming Work
The Cost of the Work shall include the costs to repair or correct defective or non-conforming Work (including warranty or corrective work performed after Substantial Completion) unless caused by Design-Builder’s negligence. DBIA believes that Design- Builder should not be penalized for inadvertent mistakes which are inevitable when designing and constructing a Project. To do so would encourage ultra-conservatism in every task, the ultimate cost of which would be greater than a proactive approach to performing the Work.
6.3.23 Warranty Escrow
At this section, the parties are provided the opportunity to establish prior to Final Completion an escrow account in a negotiated amount to be used to reimburse Design- Builder for its costs incurred in performing warranty Work. If funds remain in the escrow account after the expiration of the warranty period, the funds are returned to Owner subject to Design-Builder’s share of any savings. Note that even if the escrow account is exhausted, if funds remain under the GMP, Owner is still obligated to reimburse Design-Builder for its warranty Work.
6.4.4 Allowance Value
This section recognizes that the parties may agree that certain items of Work should be treated as an Allowance Item and priced based on Allowance Values. The Allowance Value for which Design-Builder will be entitled to receive compensation includes direct cost of labor, materials, equipment, transportation, taxes and insurance associated with the Allowance Item. All other costs associated with the Allowance Item, such as design fees, general conditions costs and fee, are deemed to be included in the Contract Price.
However, by checking the box, the parties agree that in the event the actual cost of the Allowance Item is greater than or less than the Allowance Value by a negotiated percentage, then Design-Builder’s right to Fee and markup shall be determined pursuant to Section 6.2.2.
6.6 The Guaranteed
Maximum Price
This Agreement provides the parties flexibility in establishing the Contract Price. Parties can establish a GMP before or after entering into this Agreement, or elect to proceed on the basis of costs plus a fee, without a GMP.
If a GMP method is elected, the GMP should not be established until the Basis of Design Documents are sufficiently defined to make the GMP realistic and meaningful. Setting it too early does not permit reasonable opportunity for scope definition and evaluation of Project risk. On the other hand, setting it too late may not achieve Owner’s objective of having an early price guarantee to enable it to make decisions relative to the Project.
DBIA Document No. 530 Page 7
6.6.1.1 GMP at Agreement
Execution
Enter the GMP, if appropriate. Attach as an exhibit to this Agreement the Basis of Design Documents used to establish the GMP. These documents comprise the GMP Exhibit which shall become a Contract Document pursuant to Section 2.1.1 of the Agreement.
Design-Builder does not guarantee any specific line item provided as part of the GMP.
By selecting the alternate option, Design-Builder agrees to guarantee the line item in its GMP for general conditions costs only. Design-Builder agrees that it is responsible for paying general conditions costs in excess of this line item. Design-Builder does not guarantee any other line items in the GMP.
6.6.1.2 GMP Contingency
Enter the amount of Design-Builder’s Contingency. The Contingency is for the exclusive use of Design-Builder and covers all unanticipated costs incurred that are not the basis of a Change Order. This section sets forth by way of example only the type of costs that would be funded out of the Contingency. Other costs, such as but not limited to any deductibles Design-Builder is obligated to pay, would be subject to reimbursement.
Design-Builder is also required to provide Owner with a monthly status report accounting for the Contingency, including all reasonably foreseen uses and potential uses of the Contingency for the upcoming three months.
While not provided for in the Contingency provision, DBIA recognizes that there may be situations where Owner will want to recapture the Contingency prior to Final Completion.
For example, Owner may want to use amounts in the Contingency to fund changes to the Project. Owner’s desire has to be balanced against Design-Builder’s need to use the Contingency to fund unanticipated costs for which it is liable. Accordingly, balancing these competing concerns is usually accomplished by releasing some of the Contingency to Owner after Design-Builder has bought out the Subcontractors, providing that Design-Builder is not obligated to release Contingency amounts in excess of amounts identified for reasonably foreseen uses or potential uses of the Contingency.
6.6.2.1 GMP Proposal After
Execution of This Agreement
At the request of Owner, Design-Builder shall submit its GMP Proposal, which shall include the items listed in Sections 6.6.2.1.1 to 6.5.2.1.9. If the parties agree to additions or deletions from this list, modify this Section 6.6.2.1 appropriately.
The Agreement provides the parties with flexibility as to when the GMP Proposal will be submitted after execution of the Agreement. Prior to execution of the Agreement the parties should discuss when Owner desires Design-Builder to submit its GMP Proposal.
6.6.2.1.4 Schedule
Given that expedited delivery is one of the primary factors driving many owners to select the design-build method, DBIA strongly believes that the parties should discuss and understand what each party must do to support the Project schedule. The entire Work, both design and construction, should be scheduled. The schedule should indicate the dates for the start and completion of the various stages of the Work, including the date when Owner information and approvals are required, and any Owner-created constraints. The Agreement also provides flexibility to establish the Scheduled Substantial Completion Date prior to submission of the GMP Proposal.
6.6.2.3 Acceptance of GMP
Proposal
If Owner accepts the GMP Proposal, the parties should amend this Agreement to add the final GMP Proposal as a Contract Document pursuant to Section 2.1.2.
6.6.2.4 Failure to Accept
the GMP Proposal
This Agreement provides three options for Owner in the event it fails to accept the GMP Proposal and two choices for Design-Builder if Owner fails to exercise any of the three options. These options are specifically designed to prevent one party from receiving a windfall in the event the parties cannot agree on the GMP and the Agreement is terminated.
The parties should take note that if Owner exercises its option to terminate for convenience, or Design-Builder suspends performance, Design-Builder will not be entitled to payment for uncompleted Work provided by Section 8.2. However, additional payment for Owner’s use of Work Product will be due Design-Builder pursuant to Section 4.3, if Owner proceeds to complete the Project using Design-Builder’s Work Product.
DBIA Document No. 530 Page 8
6.6.3 Savings
One of the benefits of a GMP approach is the possibility that with good management by Design-Builder and timely support from Owner the actual Cost of the Work and Fee may be less than the GMP. This creates a savings pool that should result in a benefit to both Design-Builder and Owner. Sharing these savings creates an incentive for Design- Builder to save costs. Some factors to consider in determining how the Savings are shared include the timing for the establishment of the GMP and the amount of Design- Builder’s Fee established under Section 6.2.1.
6.6.3.1 Savings
Calculations
This section provides that if the actual Cost of the Work and Design-Builder’s Fee is less than the GMP, as such GMP may have been adjusted, the savings, if any, shall be shared. The Agreement offers two choices for distributing Savings. Choose a method and enter the appropriate figures.
6.7 Performance
Incentives
In addition for the potential of Design-Builder to share in Savings as set forth in Section 6.6.3, there may be other performance incentives that will influence Project success.
Such incentives may include award fees tied to Design-Builder achieving certain standards relative to client satisfaction, safety, and personnel retention. The parties are encouraged to discuss the use of such incentives during negotiation of this Agreement.
Any agreement on the use of incentives should be set forth in an exhibit attached to this Agreement.
7.1.1 Progress Payments Enter the day of the month when Design-Builder shall submit its Application for Payment.
7.2.1 Retainage
Enter the percentage Owner will retain from Progress Payments to Design-Builder until fifty percent (50%) of the Work is completed. Owner should recognize that it creates undue hardship to hold retainage on Subcontractors that have completed their work early in the Project. Owner should accordingly consider releasing retainage on Subcontractors that complete work early in the Project, providing that these Subcontractors have satisfactorily performed their portion of the Work.
The parties are provided the option of modifying the retainage provision by checking the box. This option excludes from retainage Design-Builder’s General Conditions costs and amounts paid to Design-Builder’s Design Consultant. The rationale for selecting this option is that Design-Builder is obligated to pay its General Conditions costs in full each month and that under the design-bid-build delivery method, Owner typically does not retain sums from its Designer.
7.2.2 Release of
Retainage
This section requires Owner to release retainage to Design-Builder. If Design-Builder and Owner have established a warranty reserve in accordance with Section 6.3.2.4, the parties shall establish an escrow account at this time.
7.4 Interest
The parties should enter the rate at which interest will accrue on Design-Builder’s payments if unpaid five (5) days after due. Late payment creates a hardship for Design- Builder, its Design Consultants and Subcontractors.
7.5 Record Keeping
Owner is provided access to Design-Builder’s accounting information as it relates to Costs of the Work. However, if the parties have agreed to multipliers or markups, the time to challenge and negotiate those percentages is at the time the parties execute the Agreement and not during the Project or after it has been completed. Accordingly, Owner can at any time audit these percentages only to confirm that such percentage has been properly charged and not to challenge the composition of such percentage.
8.1.1 Termination for Convenience:
Overhead and Profit
The parties should choose prior to execution of the Agreement the method that will be used to determine overhead and profit paid to Design-Builder in the event Owner terminates Design-Builder for its convenience. The parties may choose to set percentage rates for overhead and profit prior to execution of the Agreement, or may choose to determine reasonable sums to be paid for overhead and profit at the time of the termination. If the parties choose to set overhead and profit rates prior to execution of the Agreement, the percentages should be entered in Section 8.1.1.
DBIA Document No. 530 Page 9
8.2
Termination for Convenience:
Additional Payments
Although it is important for Owner to have a process for terminating this Agreement for convenience, the process must consider the interests of Design-Builder. If Owner terminates this Agreement for its own convenience, compensating Design-Builder for its costs will not be adequate because Design-Builder will have committed its resources for a small amount of revenue. Therefore, in addition to the overhead and profit paid in Section 8.1, Owner shall pay Design-Builder an additional sum, calculated as a percentage of the remaining balance of the Contract Price or, if a GMP has not been established, the remaining balance of the most recent estimated Contract Price. Enter the percentages Owner shall pay Design-Builder if Owner terminates this Agreement for its own convenience prior to or after the start of construction.
8.3
Termination for Convenience:
Owner’s Use of Work Product
Owner should not use the Termination for Convenience clause to obtain Design- Builder’s valuable design concepts and then seek lower bids from another design-builder. If Owner terminates this Agreement for its own convenience, and chooses to proceed with the Project using Design-Builder’s Work Product, Owner should pay an additional sum for the use of Design-Builder’s Work Product pursuant to Section 4.3.
Article 9 Representatives of the Parties
Enter the name, title, address and telephone number of Owner’s Senior Representative and Owner’s Representative at Sections 9.1.1 and 9.1.2, respectively.
Enter the name, title, address and telephone number of Design-Builder’s Senior Representative and Design-Builder’s Representative at Sections 9.2.1 and 9.2.2, respectively.
The parties can elect to establish these Representatives during the performance of the Project rather than at the time of execution of this Agreement. If Representatives are identified after execution of the Agreement, an appropriate amendment should be made to the Agreement at the time these individuals are designated.
10.1 Insurance
Attach an Insurance Exhibit setting forth in detail the insurance coverages required for the Project. Parties are advised to familiarize themselves with the terms of Article 5 of the General Conditions of Contract, Insurance and Bonds, and to consult their insurance advisor.
10.2 Bonds
Enter the type and amount of bonds or other performance security required for the Project. Where bonding is not required by statute, Owner may want to evaluate the project risks versus the bonding costs in deciding what type of performance security to require.
11.1 Other Provisions
Insert any other provisions. For example, the parties may elect to have disputes resolved through litigation rather than arbitration in which case the optional language in this Section should be included.
TABLE OF CONTENTS
Article Name Page
Article 1 Scope of Work
Article 2 Contract Documents
Article 3 Interpretation and Intent
Article 4 Ownership of Work Product
Article 5 Contract Time
Article 6 Contract Price
Article 7 Procedure for Payment
Article 8 Termination for Convenience
Article 9 Representatives of the Parties
Article 10 Bonds and Insurance
Article 11 Other Provisions
DBIA Document No. 530 Page 1
Standard Form of Agreement Between Owner and Design-Builder – Cost Plus Fee with an Option for a Guaranteed Maximum Price
This document has important legal consequences. Consultation with an attorney is recommended with respect to its completion or modification.
This AGREEMENT is made as of the day of in the year of 20 , by and between the following parties, for services in connection with the Project identified below:
OWNER:
(Name and address)
DESIGN-BUILDER:
(Name and address)
PROJECT:
(Include Project name and location as it will appear in the Contract Documents)
In consideration of the mutual covenants and obligations contained herein, Owner and Design-Builder agree as set forth herein.
DBIA Document No. 530 Page 2
Article 1
Scope of Work
1.1 Design-Builder shall perform all design and construction services, and provide all material, equipment, tools and labor, necessary to complete the Work described in and reasonably inferable from the Contract Documents.
Article 2
Contract Documents
2.1 The Contract Documents are comprised of the following:
2.1.1 All written modifications, amendments, minor changes and Change Orders to this Agreement issued in accordance with DBIA Document No. 535, Standard Form of General Conditions of Contract Between Owner and Design-Builder (2022 Edition) (“General Conditions of Contract”);
2.1.2 The GMP Exhibit referenced in Section 6.6.1.1 herein or, if applicable, the GMP Proposal accepted by Owner in accordance with Section 6.6.2 herein;
2.1.3 This Agreement, including all exhibits (list, for example, performance standard requirements, performance incentive arrangements, markup exhibits, allowances, unit prices or exhibit detailing offsite reimbursable personnel) but excluding, if applicable, the GMP Exhibit;
2.1.4 The General Conditions of Contract; and
2.1.5 Construction Documents prepared and approved in accordance with Section 2.4 of the General Conditions of Contract.
Article 3
Interpretation and Intent
3.1 Design-Builder and Owner, prior to execution of the Agreement (and again, if applicable, at the time of acceptance of the GMP Proposal by Owner in accordance with Section 6.6.2 hereof), shall carefully review all the Contract Documents, including the various documents comprising the Basis of Design Documents, for any conflicts or ambiguities. Design-Builder and Owner will discuss and resolve any identified conflicts or ambiguities prior to execution of the Agreement or, if applicable, prior to Owner’s acceptance of the GMP Proposal.
3.2 The Contract Documents are intended to permit the parties to complete the Work and all obligations required by the Contract Documents within the Contract Time(s) for the Contract Price. The Contract Documents are intended to be complementary and interpreted in harmony so as to avoid conflict, with words and phrases interpreted in a manner consistent with construction and design industry standards. In the event inconsistencies, conflicts or ambiguities between or among the Contract Documents are discovered after execution of the Agreement, or if applicable, after Owner’s acceptance of the GMP Proposal, Design-Builder and Owner shall attempt to resolve any ambiguity, conflict or inconsistency informally, recognizing that the Contract Documents shall take precedence in the order in which they are listed in Section 2.1 hereof. (Note, the parties are strongly encouraged to establish in the GMP Exhibit or GMP Proposal (as applicable) the priority of the various documents comprising such exhibit or proposal.)
DBIA Document No. 530 Page 3
3.3 Terms, words and phrases used in the Contract Documents, including this Agreement, shall have the meanings given them in the General Conditions of Contract.
3.4 If Owner’s Project Criteria contain design specifications: (a) Design-Builder shall be entitled to reasonably rely on the accuracy of the information represented in such design specifications and their compatibility with other information set forth in Owner’s Project Criteria, including any performance specifications; and (b) Design-Builder shall be entitled to an adjustment in the Contract Price and/or Contract Time(s) to the extent Design-Builder’s cost and/or time of performance have been adversely impacted by such inaccurate design specification.
3.5 The Contract Documents form the entire agreement between Owner and Design-Builder and by incorporation herein are as fully binding on the parties as if repeated herein. No oral representations or other agreements have been made by the parties except as specifically stated in the Contract Documents.
Article 4
Ownership of Work Product
4.1 Work Product. All drawings, specifications and other documents and electronic data, including such documents identified in the General Conditions of Contract, furnished by Design-Builder to Owner under this Agreement (“Work Product”) are deemed to be instruments of service and Design-Builder shall retain the ownership and property interests therein, including but not limited to any intellectual property rights, copyrights and/or patents, subject to the provisions set forth in Sections 4.2 through 4.5 below.
4.2 Owner’s Limited License upon Project Completion and Payment in Full to Design-Builder.
Upon Owner’s payment in full for all Work performed under the Contract Documents, Design-Builder shall grant Owner a limited license to use the Work Product in connection with Owner’s occupancy of the Project, conditioned on Owner’s express understanding that its alteration of the Work Product without the involvement of Design-Builder is at Owner’s sole risk and without liability or legal exposure to Design- Builder or anyone working by or through Design-Builder, including Design Consultants of any tier (collectively the “Indemnified Parties”), and on Owner’s obligation to provide the indemnity set forth in Section 4.5 below.
[At the parties’ option, the following may be used in lieu of Section 4.2.]
Upon Owner’s payment in full for all Work performed under the Contract Documents, Design- Builder: (a) grants Owner a limited license to use the Work Product in connection with Owner’s occupancy of the Project; and (b) transfers all ownership and property interests, including but not limited to any intellectual property rights, copyrights and/or patents, in that portion of the Work Product that consists of architectural, engineering and other design elements and specifications that are unique to the Project. The parties shall specifically designate those portions of the Work Product for which ownership in the Work Product shall be transferred. Such grant and transfer are conditioned on Owner’s express understanding that its alteration of the Work Product without the involvement of Design-Builder is at Owner’s sole risk and without liability or legal exposure to Design-Builder or anyone working by or through Design-Builder, including Design Consultants of any tier (collectively the “Indemnified Parties”), and on Owner’s obligation to provide the indemnity set forth in Section 4.5 below.
4.3 Owner’s Limited License upon Owner’s Termination for Convenience or Design-Builder’s Election to Terminate. If Owner terminates this Agreement for its convenience as set forth in Article 8 hereof, or if Design-Builder elects to terminate this Agreement in accordance with Section 11.4 of the General Conditions of Contract, Design-Builder shall, upon Owner’s payment in full of the amounts due Design-Builder under the Contract Documents, grant Owner a limited license to use the Work Product to complete the Project and subsequently occupy the Project, and Owner shall thereafter have the same rights as set forth in Section 4.2 above, conditioned on the following:
DBIA Document No. 530 Page 4
4.3.1 Use of the Work Product is at Owner’s sole risk without liability or legal exposure to any Indemnified Party, and on Owner’s obligation to provide the indemnity set forth in Section 4.5 below, and
4.3.2 Owner agrees to pay Design-Builder the additional sum of Dollars ($ ) as compensation for the right to use the Work Product to complete the Project and subsequently use the Work Product in accordance with Section 4.2 if Owner resumes the Project through its employees, agents, or third parties.
4.4 Owner’s Limited License upon Design-Builder's Default. If this Agreement is terminated due to Design-Builder's default pursuant to Section 11.2 of the General Conditions of Contract, then Design- Builder grants Owner a limited license to use the Work Product to complete the Project and subsequently occupy the Project, and Owner shall thereafter have the same rights and obligations as set forth in Section
4.2 above. Notwithstanding the preceding sentence, if it is ultimately determined that Design-Builder was not in default, Owner shall be deemed to have terminated the Agreement for convenience, and Design- Builder shall be entitled to the rights and remedies set forth in Section 4.3 above.
4.5 Owner’s Indemnification for Use of Work Product. If Owner is required to indemnify any Indemnified Parties based on the use or alteration of the Work Product under any of the circumstances identified in this Article 4, Owner shall defend, indemnify and hold harmless such Indemnified Parties from and against any and all claims, damages, liabilities, losses and expenses, including attorneys’ fees, arising out of or resulting from the use or alteration of the Work Product.
Article 5
Contract Time
5.1 Date of Commencement. The Work shall commence within five (5) days of Design-Builder’s receipt of Owner’s Notice to Proceed (“Date of Commencement”) unless the parties mutually agree otherwise in writing.
5.2 Substantial Completion and Final Completion.
5.2.1 Substantial Completion of the entire Work shall be achieved no later than ( ) calendar days after the Date of Commencement (“Scheduled Substantial Completion Date”).
[At the parties’ option, the following supplemental language may be inserted at the end of
Section 5.2.1 if the Project is subject to a Temporary Certificate of Occupancy.]
The parties agree that the definition for Substantial Completion set forth in Section 1.2.18 of the General Conditions of Contract is hereby modified to read as follows:
“Substantial Completion is the date on which the Work, or an agreed upon portion of the Work, is sufficiently complete in accordance with the Contract Documents so that Owner can occupy and use the Project or a portion thereof for its intended purposes, provided, however, that Substantial Completion shall be deemed to have been achieved no later than the date of issuance of a Temporary Certificate of Occupancy issued by the local building official.”
5.2.2 Interim milestones and/or Substantial Completion of identified portions of the Work (“Scheduled Interim Milestone Dates”) shall be achieved as follows: (Insert any interim milestones for portions of the Work with different scheduled dates for Substantial Completion.)
DBIA Document No. 530 Page 5
5.2.3 Final Completion of the Work or identified portions of the Work shall be achieved as expeditiously as reasonably practicable. Final Completion is the date when all Work is complete pursuant to the definition of Final Completion set forth in Section 1.2.8 of the General Conditions of Contract.
5.2.4 All of the dates set forth in this Article 5…