ESBD_558459_1789067869073_G.7 Proposed Performance Schedule.pdf

PDF 80 KB Posted

Attached to
Camp Mabry Portables
Solicitation number
TMD27-CFMO-0046097
Issued by
Texas

About this file

This is a Proposed Performance Schedule document for the Camp Mabry Portables project in Texas, outlining the timeline and milestones for contract execution and project delivery. The schedule establishes key dates for project initiation, mobilization, and completion of work activities. The document provides a structured approach to performance expectations, detailing when various phases of the project must commence and conclude to ensure timely delivery of services. The performance schedule serves as a critical planning tool that aligns contractor responsibilities with project objectives and allows for monitoring of progress against established benchmarks throughout the contract period.

The schedule establishes accountability measures and provides clear visibility into contractor performance expectations across all phases of work. By defining specific performance dates and milestones, the document enables the contracting agency to track progress, identify potential delays early, and ensure that work is completed in accordance with the project timeline. This structured approach facilitates project management and provides a framework for evaluating contractor compliance with contractual obligations related to schedule adherence and timely completion of deliverables.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Proposed Performance Schedule - Camp Mabry Portables

Attachment G.7 Proposed Performance Schedule Camp Mabry Portables

Instructions: Respondents must complete and submit this Proposed Performance Schedule with their Bid as required by Section 8 of the Scope of Work.

Milestone Target date North South

Award / Notice to Proceed 11/30 NLT 12/21/2026 — —

As-found foundation survey and report

Units ordered/released for fabrication

CFMO layout reviews complete

THC conditions issued

Units delivered and set

MEP and low-voltage rough-in complete

Acoustic field testing complete —

CFMO occupancy approval No later than 03/30/2027

03/30/2027 03/30/2027

Owner move-in After TMD acceptance After acceptance

After acceptance

Notes: