ESBD_558459_1789067869073_G.7 Proposed Performance Schedule.pdf
PDF 80 KB Posted
- Attached to
- Camp Mabry Portables
- Solicitation number
- TMD27-CFMO-0046097
- Issued by
- Texas
About this file
This is a Proposed Performance Schedule document for the Camp Mabry Portables project in Texas, outlining the timeline and milestones for contract execution and project delivery. The schedule establishes key dates for project initiation, mobilization, and completion of work activities. The document provides a structured approach to performance expectations, detailing when various phases of the project must commence and conclude to ensure timely delivery of services. The performance schedule serves as a critical planning tool that aligns contractor responsibilities with project objectives and allows for monitoring of progress against established benchmarks throughout the contract period.
The schedule establishes accountability measures and provides clear visibility into contractor performance expectations across all phases of work. By defining specific performance dates and milestones, the document enables the contracting agency to track progress, identify potential delays early, and ensure that work is completed in accordance with the project timeline. This structured approach facilitates project management and provides a framework for evaluating contractor compliance with contractual obligations related to schedule adherence and timely completion of deliverables.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Proposed Performance Schedule - Camp Mabry Portables
Attachment G.7 Proposed Performance Schedule Camp Mabry Portables
Instructions: Respondents must complete and submit this Proposed Performance Schedule with their Bid as required by Section 8 of the Scope of Work.
Milestone Target date North South
Award / Notice to Proceed 11/30 NLT 12/21/2026 — —
As-found foundation survey and report
Units ordered/released for fabrication
CFMO layout reviews complete
THC conditions issued
Units delivered and set
MEP and low-voltage rough-in complete
Acoustic field testing complete —
CFMO occupancy approval No later than 03/30/2027
03/30/2027 03/30/2027
Owner move-in After TMD acceptance After acceptance
After acceptance
Notes: