RFI__2.docx

DOCX document 17 KB Posted

Attached to
IRS_Consolidation
Solicitation number
EQ2PSEU-17-0002
Issued by

About this file

Responses to Questions

View the file

Other files

File Type Posted
RFI__1.docx DOCX document
Pricing_Sheet_(1).pdf PDF
Solicitation.docx DOCX document
SOW_-_IRS_Buildout_working_updated.doc DOC document
SOW_-_IRS_Buildout_working_updated.doc DOC document
SOW_-_IRS_mapsout.pdf PDF
Wage_Determination.docx DOCX document
Solicitation.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Phase 3: It was mentioned in the walk-thru the removing / installation of the antenna might be done by owner. Please clarify.

Antenna will be moved by others

2. Please clarify the locations that will need new carpet or VCT, and clarify the existing conditions. If possible, please indicate brand/manufacturer of new material to be installed.

If an area currently has carpet, it will remain carpet. If the flooring is currently tile it will remain as tile. Any existing carpet or tile that does not need to be removed should remain

3. Please provide specs or clarify the type of cabinetry / countertops to be installed in the breakroom and TCO office.

Cabinetry shall be lowest cost available commercial off the shelf type and counter top shall be plastic laminate.

4. Phase 1 room 400-8 & 400-9 we are removing a wall and making 3 separate offices. Room 400-05 installing new wall. Server room we are installing a new wall. Please clarify ceiling work involved in each area;

a. Complete demo of grid and tile. Installation of new grid / tile throughout each area?

Areas inside new rooms will need new ceiling grids; however, the ceiling grid in the remaining areas should remain.

b. Any additional/relocation of sprinkler heads involved? Sprinkler layout drawing?

Sprinkler heads will need to be adjusted to keep within code. Existing fire suppression plan is now available.

c. Any additional lights necessary?

Lighting to maintain a light level as required for office areas must be maintained. Specific number of additional light fixtures needed is not known.

4. Will all security work be done by owner?

Yes, to include the card reader.

5. Will all fire alarm work be done by owner?

No

6. Phase 2 - 2nd floor calls to “construct tactical storage room, communications room, and seized storage room”.

a. These are all new walls, insulated, to deck correct?

Yes.

b. New grid / ceilings in each room?

Yes.

c. What about lighting in these rooms?

Maintain appropriate illumination for office space. Exact quantity of new fixtures is unknown.

d. Electrical outlets / data in rooms per drawing?

Data outlets are per drawing. Duplex receptacles are minimums; assume outlets every 8’ on new walls

e. New flooring in rooms?

Maintain existing flooring if possible. Carpet is tile, so minimal replacement if needed

f. Any sprinkler work necessary?

Sprinkler heads will need to be adjusted to keep within code. Existing fire suppression plan is now available.

g. New doors? (Hardware is new according to drawings) Phase 2 - 2nd floor Processing room: Calls to install 1 door between processing room and interview room. Drawings also show new door on west wall towards conference room, but that’s not on statement of work that I see. Please clarify.

Install the door on the west wall as per the drawing.